Attachment 1 - Amended Construction and Tree Management Plan · OPW25/0206
Plans and drawings: the text below has words only, no drawings.
Very large file (10.8 MB): may take a few minutes to open.
In terms of tree removal, only the trees identified on the tree removal and tree retention plans are to be
removed. The focus is on those trees deemed of lesser value, thereby reducing the number of higher-
value trees that need to be removed in accordance with the approval, once obtained. The project will
benefit from ongoing arborist guidance throughout the construction process to support the protection of
the trees identified to be retained.
Install tree protection management - this includes ground protection along the boardwalk design and
flagging ‘No-Go’ / Exclusion Zones / TPZs. These will predominately be around the cabin sites – Refer to
ATTACHMENT C.
Tree Protection Fencing
Due to the nature of the site, standard Tree Protection Fencing will not be achievable throughout the
site. The typical steel mesh panels are not suitable to create the Exclusion Zones.
Refer to ATTACHMENT C - Tree Protection Fencing for additional detailed information.
These protection measures will be established by the contractor with guidance from the project arborist.
Fencing the site
Temporary fencing and signage will be erected to delineate the construction site and protect the
surrounding environment, particularly the sensitive ecological areas that have been identified. Refer to
ATTACHMENT D. for the location of proposed fencing. This fence is shown as an indicative line,
however, in reality, the fence will have an organic format as it moves between vegetation and tree
locations.
As with all elements that impact any existing site conditions, the Arborist will be in attendance when the
site fence is located.
Inspection and Signoff
Site inspection of individual tree/vegetation and construction fencing to be undertaken by the site
manager/contractor, project arborist, and project ecologist prior to any site construction activities (other
than those identified above).
Signoff notification (in writing) to be provided by the project ecologist in addition to the arborist signoff
confirming the tree protection requirements are as per ATTACHMENT C.
4.5. Site Setup and Preparation:
Site Mobilisation:
Establish Contractor Site Facilities at the northern carpark, cabins 1, 12 &13 and 14 & 15 locations – refer
to, ATTACHMENT D. These will include prefabricated offices, amenities, material laydown areas and the
potential of shared facilities with the RACV Resort, including parking for contractors.
Temporary utilities such as water, electricity, and sanitation will be installed in designated areas to ensure
minimal disruption to the natural surroundings. These site facilities will be carefully positioned to minimize
their footprint and located within designated areas for future accommodation units.
Designated pathways and Temporary Construction Access zones will be used for movement around the
site to limit ground disturbance.
Ground protection measures, such as geotextiles, mulch, and track mats, will be employed to prevent soil
compaction and erosion.
Construction and Tree Management Plan - REV03 Page of 45
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Attachment 1 - Amended Construction and Tree Management Plan.pdfRelated documentApplication case desk ↗
About this file
- File size
- 10.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.