Attachment 1 - Amended Construction and Tree Management Plan · OPW25/0206

of 40

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (10.8 MB): may take a few minutes to open.

Log in to see the plans as drawn
                  In terms of tree removal, only the trees identified on the tree removal and tree retention plans are to be
                   removed. The focus is on those trees deemed of lesser value, thereby reducing the number of higher-
                   value trees that need to be removed in accordance with the approval, once obtained. The project will
                   benefit from ongoing arborist guidance throughout the construction process to support the protection of
                   the trees identified to be retained.
                  Install tree protection management - this includes ground protection along the boardwalk design and
                   flagging ‘No-Go’ / Exclusion Zones / TPZs. These will predominately be around the cabin sites – Refer to
                   ATTACHMENT C.

          Tree Protection Fencing
               Due to the nature of the site, standard Tree Protection Fencing will not be achievable throughout the
                 site. The typical steel mesh panels are not suitable to create the Exclusion Zones.
               Refer to ATTACHMENT C - Tree Protection Fencing for additional detailed information.
               These protection measures will be established by the contractor with guidance from the project arborist.

          Fencing the site
              Temporary fencing and signage will be erected to delineate the construction site and protect the
                 surrounding environment, particularly the sensitive ecological areas that have been identified. Refer to
                 ATTACHMENT D. for the location of proposed fencing. This fence is shown as an indicative line,
                 however, in reality, the fence will have an organic format as it moves between vegetation and tree
                 locations.
              As with all elements that impact any existing site conditions, the Arborist will be in attendance when the
                 site fence is located.

          Inspection and Signoff
               Site inspection of individual tree/vegetation and construction fencing to be undertaken by the site
                 manager/contractor, project arborist, and project ecologist prior to any site construction activities (other
                 than those identified above).
               Signoff notification (in writing) to be provided by the project ecologist in addition to the arborist signoff
                 confirming the tree protection requirements are as per ATTACHMENT C.

4.5.       Site Setup and Preparation:

          Site Mobilisation:
               Establish Contractor Site Facilities at the northern carpark, cabins 1, 12 &13 and 14 & 15 locations – refer
                 to, ATTACHMENT D. These will include prefabricated offices, amenities, material laydown areas and the
                 potential of shared facilities with the RACV Resort, including parking for contractors.
               Temporary utilities such as water, electricity, and sanitation will be installed in designated areas to ensure
                 minimal disruption to the natural surroundings. These site facilities will be carefully positioned to minimize
                 their footprint and located within designated areas for future accommodation units.
               Designated pathways and Temporary Construction Access zones will be used for movement around the
                 site to limit ground disturbance.
               Ground protection measures, such as geotextiles, mulch, and track mats, will be employed to prevent soil
                 compaction and erosion.



Construction and Tree Management Plan - REV03                                                                    Page    of 45

Used in these records

About this file

File size
10.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment 1 - Amended Construction and Tree Management Plan.pdf · 10.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.