NOOSA COUNCIL IDAS Development Application Decision Notice 14
- pest control (particularly mosquitoes)
- soil erosion and sediment control;
- water quality protection;
- groundwater protection;
- air quality protection;
- acid sulphate soil management;
- storage and handling of hazardous substances;
- noise and vibration management;
- waste management;
- cultural heritage management;
- visual amenity protection;
- bushfire control;
- environmental emergencies;
- community liaison.
77. The Environmental Management Plan shall incorporate the requirement for monthly environmental
compliance monitoring and annual audit reports to be submitted to Council for the construction
stages of the development. The format and content of these reports shall be in hard copy and
digital form, generally in accordance with the following:
77.1 Include tables of the monitoring results (digital form should be in Excel).
77.2 Include individual charts plotting the results for all parameters required in the monitoring.
77.3 Include a brief written discussion of the results and recommend any necessary actions.
78. The Applicant and all future owners of the site shall comply with the EMP.
Sediment and Erosion Control Plan
79. Detailed staged Sediment and Erosion Control Plans shall be prepared for the site, to the
reasonable satisfaction of Council and implemented by the owner. The Plans shall be in
accordance with the Institution of Engineers Australia ‘Engineering Guidelines for Queensland Soil
and Sediment Control’ (June 1996) and in particular using Checklist No. 3 from that document. The
Sediment and Erosion Control Plans shall cover all development on site (during the construction,
establishment and operational phases), ecological restoration and remediation works. All
recommendations of the Plans shall be implemented.
80. The Sediment and Erosion Control Plans shall also ensure the protection of the areas of ‘Retained
and Enhanced Vegetation’ shown on the Vegetation Clearing Plan dated 23 July 2004 both on and
external to the site, and shall:
- identify existing erosion problems, and
- specify appropriate remedial actions.
81. All necessary erosion and sediment control devices shall be incorporated within the development
precincts. That is areas shown as ‘Selective Clearing’ on the Vegetation Clearing Plan dated 23
July 2004.
Stormwater and Water Quality Management Plan
H o:\database\onestop\decision.doc
Print Date: 26 February 2020, 3:13 PM