               NOOSA COUNCIL IDAS Development Application Decision Notice                                                            23


                         158.      Prior to endorsement of the Plan of Survey, a State Survey Mark shall be provided within the site.
                                   It shall be levelled and located to the requirements of Council’s Surveying Section. A ‘Form 6’ shall
                                   be submitted for Council's records.
                                   Each State or other Permanent Survey Mark shall be installed clear of overhead vegetation, making
                                   it suitable for Global Positioning Equipment, and accurately connected to at least one real property
                                   corner by a registered Surveyor.
                         General

                         159.      Alterations to lot sizes, number of lots and layout may be required following the issue of a
                                   Development Permit for Operational Works in respect of the internal roadworks design.

                         160.      In conjunction with the lodgement of the Plan of Survey for Council endorsement, legal
                                   documentation shall be presented to Council and shall be submitted in the correct form with the
                                   fees prescribed in Council's adopted fee schedule.

                         161.      Pursuant to Section 3.7.3(3)(b) of the Integrated Planning Act, all outstanding rates and charges
                                   due and payable to Noosa Council in respect of the lots being reconfigured shall be paid prior to
                                   endorsement of the Plan of Survey.

                         162.      A programme of works is to be submitted with any application for any Development Permit for
                                   Operational Works detailing the construction schedule and proposed environmental protection
                                   measures.
                                   Where the program is changed for any reason whatsoever, a copy of the revised program shall be
                                   submitted to Council’s Works Inspector within seven (7) days.

                         163.      The person acting on this permit shall apply and obtain for all other necessary permits including
                                   crane permits, road opening permits, hoarding permits, footpath occupation permits and/or any
                                   other approvals required under any other Act.
               Additional Condition

                         164.      For the purpose of these conditions the “site” is the areas identified as lots 1-33, the areas shown
                                   as Park on the Vegetation Clearing Plan dated 23 July 2004 and the area shown as Park-Public
                                   Esplanade     on      the   Vegetation        Clearing     Plan      dated      23      July    2004.




               H o:\database\onestop\decision.doc


                                                                                                                    Print Date: 26 February 2020, 3:13 PM
Log in to download the original file

Approval Package.pdf · 280 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.