               18.    A Construction Management Plan for the development must be submitted to and approved
                      by Council at least 5 working days prior to the commencement of any Building works or at
                      least 5 working days prior to the pre-start meeting for Operational Works. The Construction
                      Management Plan shall include but not be limited to:
                      a.      site working hours;
                      b.      communication and consultation processes with surrounding premises;
                      c.      control and suppression of –
                              (i)      noise
                              (ii)     vibration;
                              (iii)    dust;
                              (iv)     odours and exhausts control; and
                              (v)      site working hours
                      d.      employee and contractor induction and education processes.
               19.    A Traffic Management Plan for each separate construction phase of the development must
                      be submitted to and approved by Council at least 5 working days prior to the commencement
                      of any works or at least 5 working days prior to the pre-start meeting for Operational
                      Works. The Traffic Management Plan must include but not be limited to:
                      a.      limiting the routes for the heavy vehicles to the major road network and define the route
                              to the site;
                      b.      indicate provision for on-site and off-site parking and shuttle buses (if required) for the
                              required workforce;
                      c.      indicate the location of loading and unloading areas;
                      d.      indicate the location of any “holding” areas for heavy vehicles;
                      e.      operating hours.
               20.    Construction staff must not park within the Council carparks in Belmore Terrace, Duke Street,
                      Webb Road or any other surrounding street. Parking must either be on site or at a suitable
                      off-site location serviced via a shuttle bus. Details must be included in the Traffic
                      Management Plans for the site.
                      Bicycle/Scooter Provision
               21.    Four bicycle racks (capable of accommodating 8 bikes) and 4 scooter spaces must be
                      provided on site at the rear of the building. The works must be undertaken in accordance
                      with an Operational Works approval and clearly shown on the plans for carparking.
                      Stormwater Drainage
               22.    The site must be provided with a stormwater drainage system connecting to a lawful point of
                      discharge. The works must be undertaken in accordance with an Operational Works
                      approval and must include in particular:
                      a.      Connection of any new works on site and in the carparking area to the existing
                              stormwater drainage system;
                      b.      The works in Webb Road must be generally in accordance with drawing number
                              16636-SK01 Revision A prepared by TOD Noosa and include sufficient detail:
                              i.       To quantify the catchment and calculate runoff to the proposed inlet and define
                                       overland flow component bypassing the inlet in a 1% AEP event
                              ii.      To demonstrate improved inlet capture
                              iii.     To demonstrate how the adjacent 1in 4 fill batter is to be stabilised to avoid scour
                                       when flows bypass the proposed inlet
                              iv.      To demonstrate that cars parked in the adjacent carparking spaces will not be
                                       flooded in a 1% AEP event


                                                                                                            Page 6 of 10
Document Set ID: 24552745
Version: 6, Version Date: 25/02/2026

Used in these records

About this file

File size
171 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval - MCU17 0024 03 (As Publihed).pdf · 171 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.