Council archive · source document
Response to Information Request - Final 21 March 2024 · MCU23/0096
“Adamson Town Planning, specialising in providing higher order town planning advice”
Having regard to the Sustainability Building Design Code, the following comments are made,
while having regard the advice provided from the project architect (refer Attachment 8):
• The proposed PAC has been designed to maximise energy efficiency (PO1).
• The proposed development provides for onsite water storage and reuse with the
provision of unground tanks on the eastern side of the PAC (PO2).
• The development minimises as far as practical sealed surfaces containing a number of
landscaped areas with stormwater runoff directed to a new bio-basin located within
the landscaped open space area to the east of the PAC. Further, makes use of other
small, landscaped areas to the west of the PAC and rain gardens within the
landscaped area at frontage (PO3 & PO4).
• Vegetation has been incorporated into the design as shown on the proposal plans, to
provide a high level of amenity within the site and for some shading (PO5 & PO6).
The total amount of site cover is 26%, which is well below the expected site cover of
50% under the Community Facilities Zone Code. Further, the GSLC is very conscious
about maintaining the current amount of open space on the site for use by students.
• The design of the development is responsive to Noosa Shire’s sub-tropical climate
and the site’s characteristics including topography, the orientation, proposed
vegetation, and the prevailing winds for reasons explained by the project architect
(refer Attachment 8).
Having regard to the comments made by the project architect, the proposed Landscape
Concept Plan (Attachment 4) and the updated SWMP (Attachment 7), the proposed
development complies with the Sustainability Building Design Code.
Issue – Traffic and Parking
Council acknowledges that the Good Shepard Lutheran College site is in a sensitive location
with regards to traffic and parking. As a result, preliminary construction and traffic
management plans will be required to be submitted with future Operational Works
Applications on the site to demonstrate how construction and associated traffic impacts will be
managed and/or mitigated. It is noted that the carpark works are proposed as Stage 2,
however it may be more logical to construct the ultimate carpark layout first to reduce the
overall construction and traffic impacts across the site from Stage 1.
Information Required
12. In 2022, Parking Area C was removed. Provide further information to Council if this is the
case. If this parking area is still being utilised, how will the loss of parks in Area C be
managed during the construction of Stage 1?
22 | P a g e
23002 – Good Shepherd Lutheran College – Preliminary Approval & Performing Arts Centre
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Response to Information Request - Final 21 March 2024.pdfRelated documentApplication case desk ↗
About this file
- File size
- 1.1 MB (small file)
- File type
No other editions are linked here.