Hi Dan and Alex

I have been advised by the Chair of the Body Corporate of the Hastings that we have Committee approval to go ahead with application to Council.

Most of the other issues are relating to the  emotion being caused by the significant building works going on atm in the Complex with builders (and their subbies) not following the construction guidelines.

Let’s get it in asap and then go from there.

Thanks 
Alison



	Begin forwarded message:

	From: John raftery <[email protected] <mailto:[email protected]> >
	
	Subject: Fw: THE HASTINGS CTS 21433- VOCM - PROPOSED PLANS FOR RENOVATION OF LOT 22
	
	Date: 3 September 2023 at 14:48:32 BST
	
	To: Alison Payne <[email protected] <mailto:[email protected]> >
	

	Alison

	I am having phone problems in Portugal. This motion already has enough "yes" votes to pass.

	You may be wary about the third part, which asks you to come back to the committee. It is my intention to try to link your proposal to the pool renovation. It makes sense for every lot owner for you to build at around the same time as the pool is renovated.

	The resort managers have a motion before the EGM that, if passed would help the cash flow in their business but be of little or no use to most owners and be a big burden on many owners. If it is passes (and I doubt it would have the numbers, but you never know) it would have your build starting sometime in 2028, at the earliest. 
	
	
	The sting in the tail for you, is exactly when the pool renovation might start. It could start as early as the winter of next year. Put your plans into Council and wait for the outcome of the EGM. When we send an application to Council, I will add a letter (if I am still Chair) that your application be considered and( approved if there are no problems from Council's viewpoint)  no later than the pool's application because it makes sense for both builds to occur at the same time.
	
	
	When my phone problems are fixed, I will email again.
	
	
	Regards
	
	
	John 

________________________________

	
	From: John raftery <[email protected] <mailto:[email protected]> >
	Sent: Friday, 1 September 2023 11:47 AM
	To: Julie King <[email protected] <mailto:[email protected]> >
	Subject: Re: THE HASTINGS CTS 21433- VOCM - PROPOSED PLANS FOR RENOVATION OF LOT 22
	 
	I vote YES

________________________________

	From: Julie King <[email protected] <mailto:[email protected]> >
	Sent: Friday, 1 September 2023 11:15 AM
	To: [email protected] <mailto:[email protected]>  <[email protected] <mailto:[email protected]> >; [email protected] <mailto:[email protected]> <[email protected] <mailto:[email protected]> >; [email protected] <mailto:[email protected]>  <[email protected] <mailto:[email protected]> >; [email protected] <mailto:[email protected]> <[email protected] <mailto:[email protected]> >; [email protected] <mailto:[email protected]>  <[email protected] <mailto:[email protected]> >;[email protected] <mailto:[email protected]>  <[email protected] <mailto:[email protected]> >; [email protected] <mailto:[email protected]> <[email protected] <mailto:[email protected]> >
	Cc: Adelle Sirett <[email protected] <mailto:[email protected]> >
	Subject: THE HASTINGS CTS 21433- VOCM - PROPOSED PLANS FOR RENOVATION OF LOT 22
	 
	TO THE BODY CORPORATE COMMITTEE
	Good morning Committee 
	Please read the below and provide your vote YES / NO / ABSTAIN to the motion, by reply email or by printing this email and circling your vote. Your vote can be provided back to Team Body Corporate by email.

	*	As this is a matter for Committee consideration, we request that you return your vote to this office by Friday 1 September 2023 at 5pm. 

	*	Conditions

	If Committee wish to alter or include further conditions to those set out in the attached Voting Paper, please discuss amongst yourselves and provide written advice of the agreed
	conditions.
	VOCM - PROPOSED PLANS FOR RENOVATION OF LOT 22
	COMMITTEE MOTION
 

That the committee approve the design (for changing the external appearance of Lot 22) as attached, noting it complies with the guidelines approved by the committee with respect to Site Cover and Gross Floor Area, subject to the following conditions:-

 

*	Confirmation of appropriate approval by Noosa Shire Council to be provided to the Body Corporate prior to commencement of works;
*	That once approval by Noosa Shire Council has been given, the Lot owner returns to Body Corporate with details of the effect the construction works will have on the pool area; and
*	That should the Body Corporate common property be affected by the construction works, Committee may impose further conditions before approval is finally given.

 

Please see attached dropbox link to updated plans for Lot 22 with additional dimensions included as requested.
230822 - Payne Vineburg - Sketch Design Issue <https://www.dropbox.com/s/1j372oeims77q36/230822%20-%20Payne%20Vineburg%20-%20Sketch%20Design%20Issue.pdf?dl=0> 
 

 
 
YES  /  NO  /   ABSTAIN

 

Please circle your intended vote if printing 
this email, and provide the vote back to
[email protected] <mailto:[email protected]> 
Post to PO Box 385, Noosa Heads QLD 4567 

	 

	 

	Julie King
	Administration Team
	Team Body Corporate
	Ph: 07 5473 5622
	teambc.com.au <http://www.teambc.com.au/> 
	  

	 

	

	 

	
	
	This email and any attachments are confidential and may be privileged too.  If you receive it by mistake then please let us know and don’t use the email or any attachment.  We don’t waive any copyright confidentiality or privilege in this email or any attachment. It is your responsibility to virus scan and use other checks in relation to this email and its attachments and Team Body Corporate accepts no responsibility for any damage or loss (arising from negligence or otherwise) which may occur.
	
	For important updates on the Corona Virus (COVID-19) and how it may affect your Body Corporate, please go to our website teambc.com.au <http://teambc.com.au/>

Used in these records

About this file

File size
1.4 MB (small file)
File type
MSG

No other editions are linked here.

Original file

Log in to download the original file

Fwd THE HASTINGS CTS 21433- VOCM - PROPOSED PLANS FOR RENOVATION OF LOT 22.eml.msg · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.