MCU210117 & OPW210199 - Reps to Council's Conditions · MCU21/0117

Attached to the e-mail MCU21/0117 & OPW21/0199 - Change Representations - 5 Pearl Street and 54 Elm Street, Cooroy.

of 8

Text shows just the words. Original shows the document exactly as it was published.

Check the original when the exact wording matters.

size to adequately redirect the stormwater generated from the proposed development. Additionally, the
proposed stormwater infrastructure has sufficient capacity to redirect the stormwater from Lot 1 RP153798 if
required.

As such, it is an unreasonable requirement for the subject site to be encumbered by a drainage easement in
addition to the proposed stormwater infrastructure. The proposed stormwater design has the capacity to
intercept and redirect runoff from the adjacent Lot 1 RP153798, and thus an easement is not required.


Proposed Amendment to Condition 35

The site must be provided with a stormwater drainage system connecting to a lawful point of discharge
and be in accordance with the Queensland Urban Drainage Manual (QUDM). The works must include in
particular:

        a. The works generally as shown on the Approved Plan No. 2101-C30 Issue D as prepared by Recor
              Consulting,

        b. collection and discharge of stormwater to the trunk drainage network in Pearl Street.,

        c. extension of the site stormwater system to accommodate stormwater from Lot 1 RP153798
              external to the site,

        d. cut off drains within the courtyards of Unit 1 and Unit 2 to intercept runoff from Lot 1 RP153798 and
              direct such flows to the stormwater pits located in these courtyards.,

        e. the use of gravity stormwater drainage and not surcharge pits.




Condition 98

The development site must be landscaped. The works must be undertaken in accordance Noosa Plan PSP 2
– Landscaping and generally in accordance with the approved Landscaping Plans and in particular:

a. A dense 2m minimum landscaped setback to the full length of the site’s frontage to Pearl Street
(excluding access).

b. A dense 2m minimum landscaped setback to the full length of the site’s frontage to Elm Street.

c. A dense 1m minimum landscaped setback to all side boundaries (excluding bin enclosure area for U5-U11).

d. Retention of all existing street trees.


Representations to Condition 98

Condition 98 is a duplication of Condition 29 and therefore not relevant. The applicant proposes that
Condition 98 is deleted.



                                                                      PO Box 1818       07 5474 3873
                                                                      Noosa Heads       [email protected]
                                                                      QLD 4567          rgstrategic.com.au

Used in these records

About this file

File size
222 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

MCU210117 & OPW210199 - Reps to Council's Conditions.pdf · 222 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.