SUPERSEDED Negotiated Decision Notice MCU17/0004

of 1

Text shows just the words. Original shows the document exactly as it was published.

Officer:	Wilhelm Koschade
Direct Telephone:	07 53296215
Our Reference:	MCU17/0004
Your Reference:	n/a

31 May 2017

Noosa Town Planning
1/75 Main Ave
WILSTON  QLD  4051

[email protected]

Dear Sir/Madam

Negotiated Decision Notice
Sustainable Planning Act 2009
I refer to your application and the representations you made in respect to the decision notice. On  Council decided your representations.
Details of the decision are as follows:
1.	APPLICATION DETAILS
Application No:	REC17/0002, MCU17/0004 & OPW17/0005
Street Address:	46 & 48 Elizabeth St NOOSAVILLE  QLD  4566
Real Property Description:	Lot 2 RP 78252 & Lot 3 RP78252
Planning Scheme:	The Noosa Plan (28 October 2016)

2.	DECISION DETAILS
Council on 2 May 2017 decided to issue the following type of approval:
Development Permit for a Reconfiguration of a Lot (Boundary Alteration);
Development Permit for a Material Change of Use (Duplex x 2); and
Development Permit for Operational Works (Stormwater, Earthworks, Landscaping, Carparking and Access).
In relation to representations, Council on 26 May 2017 decided to:
A.	Approve a change to Condition 2.
3.	RELEVANT PERIOD OF APPROVAL

The relevant period for the Reconfiguration of a Lot (Boundary Alteration) approval is 4 years starting the day the approval takes effect.

The relevant period for the Material Change of Use (Duplex x 2) approval is 4 years starting the day the approval takes effect.

The relevant period for the Operational Works (Earthworks, Stormwater, Access, Landscaping & Carparking) approval is 2 years starting the day the approval takes effect.

4.	ASSESSMENT MANAGER CONDITIONS

Development Permit for a Reconfiguration of a Lot (Boundary Alteration)

When Conditions Must Be Complied With
Unless otherwise stated, all works required by the conditions of this Decision Notice be completed prior to submission of the subdivision plan to Council for compliance assessment.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.

Plan No.	Rev.	Plan/Document Name	Date
10-2952AD	-	Plan of Proposed Reconfiguration of Lot 2 & 3 on RP78252 & General Site Levels, prepared by MWA	21/03/2017
All lot numbering on the subdivision plan to be submitted to Council for compliance assessment must remain as shown on the Approved Plans.
The development must be undertaken and operated in a manner that causes no detrimental effect upon the amenity of the neighbourhood by reason of the creation of excessive noise, lighting nuisance or other emissions.
Water & Sewer Connections
An underground connection to reticulated water and sewerage must be provided to each lot in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to each lot.
Electricity and Telecommunication Services
Reticulated electricity and telecommunication services must be provided to each lot in accordance with the standards and requirements of the relevant service provider.
Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications.
Certification must be submitted to Council from all relevant service providers which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction.

Development Permit for Material Change of Use (2 x Duplex)
PLANNING
When Conditions must be Complied With
Unless otherwise stated, all conditions of this Decision Notice must be complied with prior to the use commencing, and then compliance maintained at all times while the use continues.
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
16012/WD.104	P1	Site Plan, drawn by Kidd + Co	19/05/2017
16012/WD.105	P1	Upper Site Plan, drawn by Kidd + Co	19/05/2017
16012/WD.200	P1	Ground Plan Unit 1, drawn by Kidd + Co	19/05/2017
16012/WD.201	P1	Upper Plan Unit 1, drawn by Kidd + Co	19/05/2017
16012/WD.205	P1	Elevations Unit 1 (North & South), drawn by Kidd + Co	19/05/2017
16012/WD.206	P1	Elevations Unit 1 (East & West), drawn by Kidd + Co	19/05/2017

Building Height
The maximum height of the development must not exceed 8.0 metres above the finished ground level and the natural ground level.
Certification must be submitted to Council from a Licensed Surveyor which certifies that the buildings do not exceed the maximum height requirement of this Decision Notice.
Performance Bond
Security in the form of a cash bond or trading bank guarantee to the sum of $20,000 must be submitted to Council, to secure performance of all conditions of this approval, prior to the pre-start meeting. The cash bond or trading bank guarantee will be returned on performance of the conditions of approval less any costs incurred by Council in respect of enforcing performance of this permit. Council reserves the right to call upon the bond or guaranteed sum to effect compliance with conditions.
Water & Sewer Connections
An underground connection to reticulated water and sewerage must be provided to the development site in accordance with the standards and requirements of Northern SEQ Distributor–Retailer Authority (Unitywater).
A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority (Unitywater) must be submitted to Council that certifies an underground connection to reticulated water and sewerage has been provided to the development site.
Building Appearance
All air conditioning units or other mechanical equipment must be located at ground level, or otherwise fully enclosed or screened such that they are not visible from the street frontages nor adjoining properties.
All deck and balcony areas above ground floor must not be enclosed by permanent fixtures such as shutters, louvres, glass panelling or the like, except where required to satisfy any privacy condition of this Decision Notice.
Fencing and Walls
Any street fencing must be set back an average of 1 metre from the front property boundary. Any fencing on the front boundary must either:
not exceed a maximum height of 1.2m
be of open construction.
The area of land between the fence and the front property boundary must be densely landscaped to screen any fencing from the street.
Clothes Drying Areas
Each dwelling unit must be provided with access to an outdoor clothes line which is screened from public view.
Protection of Privacy
To ensure privacy is protected between adjoining units and properties, any window or deck area which overlooks or impacts on the privacy of any adjoining property or unit must either:
Have a minimum window sill height of 1.5 metres above floor level;
Be fitted with translucent glazing; or
Be fitted with a fixed external screen.
Community Management Statement
Any proposed Community Management Statement required for the development pursuant to the Body Corporate and Community Management Act 1997 must be submitted to Council for endorsement at the same time as submission of the Building Format Plan (or similar) to Council for compliance assessment.
All clauses and by-laws of the proposed Community Management Statement must accord with the requirements of this Decision Notice
Landscaping
The development site must be landscaped. The works must be undertaken in accordance with the approved Landscaping Plans and Planning Scheme Policy PSP 3 – Landscaping Plants and Guidelines and include in particular:
2 street trees evenly spaced on both sides of the proposed common driveway within the road reserve.
All landscape works must be established and maintained in accordance with the approved design for the life of the development, and in a manner that ensures healthy, sustained and vigorous plant growth.  All plant material must be allowed to grow to full form and be refurbished when its life expectancy is reached.
All landscape works must be maintained generally in accordance with the approved design for the life of the development.
Waste Storage
The developer must provide waste storage and disposal facilities in accordance with Planning Scheme Policy 9, Waste Management, including an external imperviously paved area correctly sized for all refuse and recycling containers and suitably screened from public places and neighbouring properties.
A bin wash area is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket trap. The drain outlet is to be designed to prevent storm water entry to the sewerage system which can be achieved by a bunded area, with a nib wall height of 100mm maximum, enclosing a wash area of 700mm x 700mm minimum (max 0.7m²).  Alternatively the waste area can be roofed, or any other appropriate design approved by Council.
Noise
Written certification must be provided from a suitably qualified person confirming that sound pressure levels from all mechanical plant and equipment comply with the following :
Air-conditioning and Refrigeration
7am to 10pm: Maximum level allowable = background + 5dB(A)
10pm to 7am: Maximum level allowable =  background + 3dB(A)
Pumps
7am to 7pm: Maximum level allowable = background + 5dB(A)
7pm to 10pm: Maximum level allowable = background + 3dB(A)
10pm to 7am: No audible noise.
Assessment and certification is required immediately after installation of the equipment and prior to any occupation of the building.  All equipment must be operating at the same time to test the overall noise level created, with the measurement location at either the residential boundary or outside the most exposed part of an affected building - whichever is the closest to the plant/equipment.
The certification must be submitted to Council, which certifies that operational noise from any fixed plant and equipment complies with the requirements of this Decision Notice.
ENGINEERING
Approved Plans
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
16012/SK.101	D	Site Plan, drawn by Kidd + Co	18/12/16
External Works
Elizabeth Street must be upgraded for the length of its frontage to the subject site.  The works must be undertaken in accordance with an Operational Works approval and must include in particular:
construction of a pedestrian footpath in accordance with the conditions of this Decision Notice
removal of the existing property access and reinstatement of the kerb, footpath and verge area to match the balance of the site frontage, including the provision of topsoil and turf where the existing verge is grassed
This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009 being non-trunk infrastructure.
Site Access and Driveways
A sealed access driveway must be provided from Elizabeth Street to all parking and manoeuvring areas of the development. The works must be generally in accordance with the approved plans and must include in particular a driveway crossover in accordance with Council’s standard drawings RS-049 and RS-050.
The proposed gate across the driveway must be either deleted or relocated to a location within the site such that the visitor carspaces are freely available.
Car Parking
A minimum of 6 car parking spaces must be provided and marked on the site and be made available and accessible at all times. The works must be undertaken generally in accordance with the approved plans and must include in particular:
2 visitor parking spaces within the total, which are clearly marked for that purpose and accessible at all times for visitor use
Dimensions, crossfalls and gradients in accordance with Australian Standard AS2890: Parking Facilities
All car parking areas, access driveways and turning bays must be maintained exclusively for vehicle parking and manoeuvring and kept in a tidy and safe condition at all times.
Directional signage must be provided to direct visitors to the car parking spaces provided on site.
Pedestrian and Bicycle Facilities
Pedestrian and bicycle facilities must be provided for the development.  The works must be undertaken generally in accordance with the approved plans and must include in particular a 2 metre wide footpath within the road verge for the entire length of the site’s frontage to Elizabeth Street. The final alignment of the path must be determined on-site in conjunction with Council’s Construction Officer.
This condition is imposed pursuant to s665 of the Sustainable Planning Act 2009 being non-trunk infrastructure.
Stormwater Drainage
The site must be provided with a stormwater drainage system connecting to a lawful point of discharge.  The works must be undertaken generally in accordance with the approved plans.
Electricity and Telecommunication Services
Unless otherwise stipulated by telecommunications legislation at the time of construction, the development must be provided with all necessary conduits, pits and pipes to accommodate the future connection of optic fibre technology telecommunications.
Certification must be submitted to Council from all relevant service providers which certifies that the development has met the requirements of this Decision Notice and all applicable legislation at the time of construction.
Easements
An easement for stormwater drainage purposes must be registered against the title of the proposed lots in favour of the benefitted adjoining properties. The easements must be a minimum of 1.5m wide or of sufficient width to wholly encompass the drainage structures and any overland flowpath.
The proposed reciprocal easements for access and services must be of sufficient width to wholly encompass the access driveway and any necessary vehicle manoeuvring areas.
Unless otherwise agreed in writing by the relevant service provider, any public or third party infrastructure located on the subject site must be placed within an easement registered against the title of the property.
All easements must be designed in accordance with the planning scheme and granted at no cost to the Grantee.  Where the Grantee is Council or a service authority, the easement documentation must be in accordance with the Grantee’s standard easement terms.  Draft easement documentation must be submitted to Council for endorsement.
All works must be kept clear of any existing or proposed easements on the subject land, unless agreed otherwise in writing by the Grantee.
Earthworks and Retaining Walls
Filling works required on site shall be carried out in accordance with Council’s Planning Scheme Policy PSP5 – Engineering Design Standards, so as not to cause the additional ponding of water on any adjoining lands or the blockage of, or interference with, any natural watercourses.
All fill and associated batters must be contained entirely within the subject site unless written permission from the respective landowner(s) is provided to Council. All earthworks must be undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on Earthworks for Commercial and Residential Developments.
Where the development involves excavation or filling over, or adjacent to, drainage, water supply or sewerage infrastructure, all access chamber surface levels must be adjusted to provide a freeboard of 100mm above the finished ground surface level.
All retaining walls must be designed and constructed in accordance with the planning scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade safety fence.
Damage to Services and Assets
Any damage caused to existing services and assets as a result of the development works must be repaired at no cost to the asset owner at the following times:
where the damage would cause a hazard to pedestrian or vehicle safety, immediately; or
where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and assets must first be referred to the relevant service authority for approval.

Development Permit for Operational Works (Earthworks, Stormwater, Access, Landscaping & Carparking)
APPROVED PLANS
Development undertaken in accordance with this approval must generally comply with the approved plans of development. The approved plans are listed in the following table unless otherwise amended by these conditions.
Plan No.	Rev.	Plan/Document Name	Date
26281-OW3	-	Operational Works: Earthworks & RW Details prepared by SCG Consulting Engineers	November 2016
26281-OW6	A	Operational Works: Driveway & Access prepared by SCG Consulting Engineers	7 February 2017
26281-SW1	A	Operational Works: Stormwater Management prepared by SCG Consulting Engineers	7 February 2017
160614 01	A	Specification, drawn by Seed Landscape Design	14/12/2016
160614 02	B	Landscape Plan, drawn by Seed Landscape Design	19/12/2016
160614 03	B	Planting Plan, drawn by Seed Landscape Design	19/12/2016
160614 04	B	Details, drawn by Seed Landscape Design	19/12/2016
PRIOR TO COMMENCEMENT OF WORKS
Engineering
Tree protection fencing must be installed under the supervision of the Project Arborist.  (Refer to Retention of Existing Trees Conditions)
All necessary approvals from external service providers (eg Unitywater) and external parties on which the development works are proposed have been obtained and a copy supplied to Council.
A condition report including photographs of the frontage of the site must be completed and submitted to Council at the prestart meeting and prior to any works commencing.
Certificates demonstrating currency of public liability insurance and works insurance covering the works must be submitted to Council at the prestart meeting.
Council must be contacted at least 5 working days prior to any works commencing to organise a pre-start. The contact number to arrange a pre-start meeting is 5329 6245. The pre-start meeting must include the relevant parties for the following aspects of the works:
Civil engineering works;
Landscape works;
Erosion and sediment control works;
Other relevant parties
A Construction Management Plan must be submitted to Council prior to the pre-start meeting and must specifically address the following:
Traffic Management during all aspects of the construct phase including:
A Traffic Management Control Plan in accordance with Manual of Uniform Traffic Control Devices (MUTCD) detailing all temporary signage and traffic control measures prior to construction
Maintenance of safe pedestrian access across the frontage of the site both during daily construction and after daily construction has ceased
Proposed fencing to the site during the construction phase of the development
Adequate parking arrangements for construction workers
No queuing of trucks is permitted on residential streets, especially prior to 7.00am. Further parked trucks must have engines turned off
Maintenance and protection of water quality and existing drainage lines through the construction site through the implementation of appropriate erosion and sediment control measures
Works programme identifying key components of the works and their respective durations
Establishment of a communication protocol with the general public, adjoining owners, emergency services and local businesses to advise of agreed construction times, impacts on traffic and services and other relevant issues
identification of complaint management procedures including:
contact details for the on-site manager
dispute resolution procedures
For haulage operations involving significant volumes of fill material or excavated material being transported onto or off the site: details on the location of external fill sites/sources, the haulage route, type of vehicle to be utilised during filling operations and frequency of usage.  NB any damage to the existing road system as a result of haulage operations shall be fully repaired at the applicant’s expense
Any changes to the details associated with the supervising RPEQ or Principal Contractor during construction, must be notified to Council in writing within five business days of the change occurring.
Any conflict between the development and an existing or proposed service must be referred to the relevant service authority for determination prior to commencement of works. The developer is solely responsible for any costs associated with modifications to existing infrastructure.
DURING CONSTRUCTION
Engineering
The developer must meet any costs to repair damage to any Council asset during construction, where damage is a result of the development works. Damage to assets must be repaired immediately where it creates a hazard to the community. In circumstances where the damage does not create a hazard to the community, it must be repaired immediately on completion of the works associated with the development.
All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ) who is independent of the Developer and Principal Contractor, and they must certify that all works conform to the Operational Works permit. Where municipal works are involved, such confirmation must be submitted for the respective hold points prior to any site inspection by Council Officers.
All works must be constructed and work procedure undertaken in accordance with:
The approved plans/documents and conditions detailed in this Decision Notice
All relevant Noosa Council Planning Scheme Policies, standard drawings, standard specifications and guidelines
The latest version of the Healthy Waterways document “Water Sensitive Urban Design Technical Design Guidelines for South East Queensland” for all water quality devices to be constructed on site
Pavement Design and Construction
Pavement design for privately owned works must be undertaken in accordance with the relevant standards.  Structural integrity of the driveway and car park areas will remain the responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
Safe pedestrian access on all streets in the vicinity of the development must be maintained at all times. Should footpath/road closures be necessary to carry out construction works, Council’s Engineering Officer must be notified prior to the proposed closure and all requirements complied with.
All frontage works must match neatly with existing road and verge/footpath features. Additional works beyond the frontage may be required to provide an acceptable transition to existing road and verge/footpath profiles.
Electrical conduits or other services proposed to be installed within existing and proposed road reserves under existing sealed carriageways, concrete pathways, concrete/sealed driveways or significant vegetation must be installed by boring. Trenching is not permitted, unless specifically approved by Council.
Pathways
All pathways must be constructed in accordance with the following requirements:
All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065.
All paths must have a slip resistant surface
Expansion and contraction joints must provide a flush finish. Installation of joints by saw cutting is preferred to ensure a smooth ride for cyclists
The required work includes any modifications to ensure the footpath finishes flush with all existing service covers and the like, or alternatively these services are raised or altered, so as not to create a pedestrian safety hazard
Pathways must:
terminate in a manner that ensures smooth transition to existing surfaces for public safety
be designed and constructed to comply with the Disability Discrimination Act (DDA), Access to Premises Standard, Austroads and relevant sections of AS1428 Design for access and mobility
Site Access and Driveways
Driveway crossovers must be constructed in accordance with Council’s Standard Drawings RS-049 and RS-050
Any existing unnecessary or redundant property accesses must be removed, and the kerb, footpath and verge area reinstated to match the existing footpath and/or verge treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed or turf, and must be maintained by the developer until established.
The following must be complied with during the construction of the required crossover/driveway:
The driveway surfacing must consist of either an approved hot mixed asphaltic concrete or patterned/plain concrete.
The driveway must be constructed so as not to concentrate stormwater runoff onto neighbouring properties
Underground service conduits for water supply, electricity and any other services must be provided as part of the access driveway
Where there is an existing pedestrian path, a matching crossfall must be provided for the driveway on the alignment of the path, for the full width of the path
The property access must be located a minimum of 1m clear of existing power poles, streetlights or other signage. The developer is responsible for any necessary relocation of existing services to provide this clearance and must contact the relevant service authorities and comply with their requirements in relation to these works.
Earthworks and Retaining Walls
All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines on Earthworks for Commercial and Residential Development, with geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and uniformity of fill shall be provided by a RPEQ and submitted to Council prior to the occupation of the building.
Fall protection must be provided to retaining walls that are over 1m high.
Slope and batters are a maximum grade of:
1 in 6 where in proximity to waterbodies
1 in 4 for grassed areas.
1 in 3 for planted areas
1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
Appropriate scour protection must be provided at the outlet of all stormwater pipes including temporary outlets.
Works associated with this permit must not adversely impact on the existing drainage conditions on other properties (eg by blocking or interfering with natural overland flows).
Construction of all internal stormwater drainage works must comply with the relevant section/s of Australian Standard AS/NZS 3500.3.
Environment
Prescribed Water Contaminants (as defined in the Environmental Protection Act 1994) must not be released from the site or to waters within the site, or be likely to be released should rainfall occur, unless all reasonable and practicable measures are taken to prevent or minimise the release and concentration of contamination.
Erosion and sediment control measures must be installed and maintained to minimise erosion on the site and to minimise the export of sediment and associated pollutants from the site. The erosion and sediment control measures must be designed, installed and maintained in accordance with current best practice standards (refer to advisory notes).
Prior to the completion of the development, all site surfaces must be effectively stabilised using methods which have achieved effective short-term stabilisation and which will continue to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes). For the purpose of this condition, an effectively stabilised surface is defined as one that does not, or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
Certification
Upon completion of the work a certificate must be issued by an RPEQ certifying that the works have been constructed in accordance with the Operational Works permit.
As Constructed Plans (Council)
Prior to acceptance of civil works to become Council assets “On Maintenance”, the lodgement of satisfactory “As Constructed” records must be submitted to Council. The “As Constructed” information must include:
Drawings and data certified by a qualified experienced Civil Engineer (RPEQ) for design intent, and certified by a Licensed Surveyor in regard to the cadastre and the location, level and type of all services and structures
The data must be in accordance with Council’s – Planning Scheme Policy 5 – Engineering Design Standards – Roads, Drainage and Earthworks, and fully detail levels for all engineering works including but not limited to drainage structures, finished ground levels and pavement surface levels
The data must be submitted in hardcopy form and digital format (Asset Design and As Constructed (ADAC)) in GDA94 Zone 56 coordinate values. Guidelines on the use of ADAC are available at www.adac.com.au
On Maintenance
All municipal works must be accepted ‘On Maintenance’ by Council in accordance with Council’s relevant Planning Scheme Policy prior to acceptance of the works. To achieve ‘On Maintenance’, the supervising RPEQ must submit to Council:
certification that all works have been undertaken and completed in accordance with the requirements of this Permit
as Constructed details in accordance with Council’s Planning Scheme Policy
maintenance and operational manuals for all proprietary or site specific devices
Off Maintenance
Prior to requesting an Off Maintenance inspection the developer must provide a written request for the Off Maintenance inspection.
A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged where:
a Council inspection reveals works do not comply with approval requirements
submitted certification falsely states works comply with approval requirements.
5.	REFERRAL AGENCIES

Not Applicable.

6.	REFERENCED DOCUMENTS

Not Applicable.

7.	ADVISORY NOTES

The following notes are included for guidance and information purposes only and do not form part of the assessment manager conditions:
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries out an activity must take all reasonable and practicable measures to ensure the activity does not harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Unit on 07 3247 6212 to discuss any obligations under the ACH Act.
Equitable Access and Facilities
The plans for the proposed building work have NOT been assessed for compliance with the requirements of the National Construction Code - Building Code of Australia (Volume 1) as they relate to people with disabilities.  Your attention is also directed to the fact that in addition to the requirements of the National Construction Code as they relate to people with disabilities, one or more of the following may impact on the proposed building work:
the Disability Discrimination Act 1992 (Commonwealth);
the Anti-Discrimination Act 1991 (Queensland); and
the Disability (Access to Premises – Buildings) Standards.
Development Compliance Inspection
Prior to the commencement of the use, please contact Council's DA Planning Section to arrange a Development Compliance Inspection.
Infrastructure Charges
This Development Permit will trigger an “Infrastructure Charge Notice” to be issued in accordance with Council’s “Charges Resolution” made pursuant to the Sustainable Planning Act 2009 and in conjunction with the State Planning Regulatory Provision (Adopted Charges).
ENVIRONMENTAL HEALTH
Building Works
Noise from residential building works shall comply with the following –
Limited to between 6:30am to 6:30pm Monday to Saturday.
All reasonable measures are taken to minimise noise emissions.
Not permitted on Sunday or public holidays.
Measurement of Noise
Measurement of sound pressure levels (adjusted for tonality and impulse) must be in accordance with either: (a) Australian Standard AS1055.1 “Acoustics–Description and measurement of environmental noise – General procedures”, or (b) The relevant “Noise Measurement Manual” as provided by the Department of Environment and Heritage Protection.
A qualified person is considered to be either: (a) a Registered Professional Engineer of Queensland, or (b) an environmental consultant with a minimum of 3 years current experience in the field of acoustics.
Acoustic Advice & Design
It is highly recommended that the developer seek the advice and design input of a qualified acoustic consultant at the plan development stage to ensure the development does not cause a noise nuisance under the Environmental Protection Act 1994.  Attention should be given to the following (but not limited to) :
building design and construction
design, selection and installation of fixed plant and equipment
the location of air conditioning and heating units, refrigeration plant, pumps, mechanical exhausts and plant rooms etc
the use of acoustic enclosures/screens around noisy plant and  equipment
operating times
Environmental Protection
The development should be undertaken in a manner that causes no unlawful environmental nuisance under the Environmental Protection Act 1994 by the creation of excessive noise, lighting, waste, atmospheric pollutants (including dust or odours) or other releases to the environment.
In accordance with the Environmental Protection Act 1994, all sand, silt, mud, paint, cement, concrete, builder’s waste or other prescribed contaminants should not to be released to or be placed where it could reasonably be expected to move into a roadside gutter, storm water drain or a watercourse.  On the spot fines apply for such offences.
Building and Construction Industry (Portable Long Service Leave) Levy
The QLeave levy must be paid prior to the issue of a development permit where it is required.  Council will not be able to issue a Decision Notice without receipt of details that the Levy has been paid.  QLeave contact: 1800 803 481 (free call) or (07) 3212 6855.
Community Title Scheme - Private Infrastructure
All private infrastructure for the development must be designed to meet the planning scheme requirements unless otherwise agreed by the relevant authority

8.	PROPERTY NOTES

Not Applicable.

9.	PRELIMINARY APPROVAL OVERRIDING PLANNING SCHEME

Not Applicable.

10.	FURTHER DEVELOPMENT PERMITS REQUIRED

Compliance Assessment for Boundary Alteration (Plan Seal)
Development Permit for Building Work (All Building Works)

11.	SELF ASSESSABLE CODES

Not Applicable.

12.	SUBMISSIONS

Not Applicable.

13.	REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME

Not Applicable.

14.	RIGHTS OF APPEAL
You are entitled to appeal against this decision.  A copy of the relevant appeal provisions from the Sustainable Planning Act 2009 is attached.
During the appeal period, you as the applicant may suspend your appeal period and make written representations to Council about the conditions contained within the development approval.  If Council agrees or agrees in part with the representations, a “negotiated decision notice” will be issued.  Only one “negotiated decision notice” may be given.  Taking this step will defer your appeal period, which will commence again from the start the day after you receive a “negotiated decision notice”.

DECISION NOTICE HISTORY
Original Decision Notice – 2 May 2017
Change to an Existing Approval – 26 May 2017, Change to Condition 2.,

Yours faithfully

Wilhelm Koschade
Development Planner

Enc:	Approved Plans/Documents
Appeal Rights
Infrastructure Charges

cc	Unitywater

	Appeal Rights SUSTAINABLE PLANNING ACT 2009 & SUSTAINABLE PLANNING REGULATION 2009

The following is an extract from the Sustainable Planning Act 2009  (Chapter 7).
MATERIAL CHANGE OF USE, RECONFIGURING A LOT & OPERATIONAL WORKS

Division 8 	Appeals to court relating to development applications and approvals

461 	Appeals by applicants
(1) 	An applicant for a development application may appeal to the court against any of the following—
(a) 	the refusal, or the refusal in part, of the development application;
(b) 	any condition of a development approval, another matter stated in a development approval and the identification or inclusion of a code under section 242;
(c) 	the decision to give a preliminary approval when a development permit was applied for;
(d) 	the length of a period mentioned in section 341;
(e) 	a deemed refusal of the development application.
(2) 	An appeal under subsection (1)(a), (b), (c) or (d) must be started within 20 business days (the applicant’s appeal period) after—
(a) 	if a decision notice or negotiated decision notice is given—the day the decision notice or negotiated decision notice is given to the applicant; or
(b) 	otherwise—the day a decision notice was required to be given to the applicant.
(3) 	An appeal under subsection (1)(e) may be started at any time after the last day a decision on the matter should have been made.

462 	Appeals by submitters—general
(1) 	A submitter for a development application may appeal to the court only against—
(a) 	the part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	the part of the approval relating to the assessment manager’s decision under section 327.
(2) 	To the extent an appeal may be made under subsection (1), the appeal may be against 1 or more of the following—
(a) 	the giving of a development approval;
(b) 	any provision of the approval including—
(i) 	a condition of, or lack of condition for, the approval; or
(ii) 	the length of a period mentioned in section 341 for the approval.
(3) 	However, a submitter may not appeal if the submitter—
(a) 	withdraws the submission before the application is decided; or
(b) 	has given the assessment manager a notice under section 339(1)(b)(ii).
(4) 	The appeal must be started within 20 business days (the submitter’s appeal period) after the decision notice or negotiated decision notice is given to the submitter.

463 	Additional and extended appeal rights for submitters for particular development applications
(1) 	This section applies to a development application to which chapter 9, part 7 applies.
(2) 	A submitter of a properly made submission for the application may appeal to the court about a referral agency’s response made by a prescribed concurrence agency for the application.
(3) 	However, the submitter may only appeal against a referral agency’s response to the extent it relates to—
(a) 	if the prescribed concurrence agency is the chief executive (environment)—development for an aquacultural ERA; or
(b) 	if the prescribed concurrence agency is the chief executive (fisheries)—development that is—
(i) 	a material change of use of premises for aquaculture; or
(ii) 	operational work that is the removal, damage or destruction of a marine plant.
(4) 	Despite section 462(1), the submitter may appeal against the following matters for the application even if the matters relate to code assessment—
(a) 	a decision about a matter mentioned in section 462(2) if it is a decision of the chief executive (fisheries);
(b) 	a referral agency’s response mentioned in subsection (2).

464 	Appeals by advice agency submitters
(1) 	Subsection (2) applies if an advice agency, in its response for an application, told the assessment manager to treat the response as a properly made submission.
(2) 	The advice agency may, within the limits of its jurisdiction, appeal to the court about—
(a) 	any part of the approval relating to the assessment manager’s decision about any part of the application requiring impact assessment under section 314; or
(b) 	any part of the approval relating to the assessment manager’s decision under section 327.
(3) 	The appeal must be started within 20 business days after the day the decision notice or negotiated decision notice is given to the advice agency as a submitter.
(4) 	However, if the advice agency has given the assessment manager a notice under section 339(1)(b)(ii), the advice agency may not appeal the decision.

465 	Appeals about decisions relating to extensions for approvals
(1) 	For a development approval given for a development application, a person to whom a notice is given under section 389, other than a notice for a decision under section 386(2), may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.
(3) 	Also, a person who has made a request under section 383 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

466 	Appeals about decisions relating to permissible changes
(1) 	For a development approval given for a development application, the following persons may appeal to the court against a decision on a request to make a permissible change to the approval—
(a) 	if the responsible entity for making the change is the assessment manager for the application—
(i) 	the person who made the request; or
(ii) 	an entity that gave a notice under section 373 or a pre-request response notice about the request;
(b) 	if the responsible entity for making the change is a concurrence agency for the application—the person who made the request.
(2) 	The appeal must be started within 20 business days after the day the person is given notice of the decision on the request under section 376.
(3) 	Also, a person who has made a request under section 369 may appeal to the court against a deemed refusal of the request.
(4)	An appeal under subsection (3) may be started at any time after the last day the decision on the matter should have been made.

467 	Appeals about changing or cancelling conditions imposed by assessment manager or concurrence agency
(1) 	A person to whom a notice under section 378(9)(b) giving a decision to change or cancel a condition of a development approval has been given may appeal to the court against the decision in the notice.
(2) 	The appeal must be started within 20 business days after the day the notice of the decision is given to the person.

[word/footer1.xml]
PD-DA-FM387/1-13/04/2010	Page 10 of 2

[word/footer2.xml]
PO Box 141		P. (07) 5329 6500	[email protected]	
	TEWANTIN  QLD  4565	F. (07) 5329 6501	www.noosa.qld.gov.au
				Page 1 of 17

[word/footer3.xml]
Page 8 of 17

[word/footer4.xml]
PD-DA-FM387/1-13/04/2010	Page 1 of 2

[word/header3.xml]
MCU17/0004

[Attachment: image4.png (image text)]
 
 
 

 
 
 

a
mm

  

NOOSA
COUNCIL

Used in these records

About this file

File size
118 KB (small file)
File type
DOCX

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Negotiated Decision Notice MCU17_0004.docx · 118 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.