The level of risk associated with each potential impact was then determined by combining
likelihood and consequence using the matrix in Table 7.2.
Table 7.2. Risk Evaluation Matrix
Consequences
Likelihood
Very Low Low Moderate High Very High
Very High Medium Medium High Very Very High
High
High Low Medium Medium High Very High
Moderate Low Low Medium High High
Low Very Low Low Low Medium High
Very Low Very Low Very Low Low Medium Medium
Source: Adapted from AS/NZS 31000:2009
Waste Management Public Benefit Assessment Page 31