STORMWATER MANAGEMENT PLAN
Client: Thomco (No 2087) Pty Ltd Location: 215 David Low Way, Peregian Beach
Table 2 – Site stormwater quality objectives (as per WQO’s for Wallum Tannin-stained Streams)
Pollutant Water Quality Objectives
Turbidity <20 NTU
Suspended Solids (SS) <6 mg/L (annual mean concentration)
Chlorophyll a <5 µg/L
Total Nitrogen <500 µg/L (annual mean concentration)
Oxidised N <60 µg/L
Ammonia N <20 µg/L
Organic N <420 µg/L
Total Phosphorus <50 µg/L (annual mean concentration)
Filterable Reactive Phosphorous
<20 µg/L
(FRP)
Dissolved Oxygen (% saturation) 85 – 110 % saturation
pH 5.0 - 7.0
Secchi Depth N/A
Conductivity 500 µS/cm
Aim for no visible oils, petrochemicals, films or
Hydrocarbons
odours
Litter Aim for no anthropogenic material greater
than 5 mm in any dimension.
3.2 Area of Treatment
The total area of the proposed development is approximately 1.165 ha consisting of groundcover,
roof area and road area. With the topography of the site and the proposed development layout, the
entire site can be treated for water quality purposes.
The treatable area of the site has been divided into three (3) catchments. The three (3) catchments
are discussed further in Section 4.2 and can be seen in the Preliminary Stormwater Management
Layout in Appendix B.
4.0 WATER QUALITY MODELLING ASSESSMENT/APPROACH
4.1 Scenario Methodology
The site was modelled using split catchment source nodes, comprised of roof area, road area and
groundcover nodes.
4.2 Proposed Stormwater Treatment Train
The following mitigation measures are proposed for the overall stormwater management at the site.
Stormwater runoff from the site will be treated by three (3) bioretention basins prior to discharge off
site.
Covey Associates Pty Ltd 6 Project No: 162042
Consulting Engineers 100949Rpt Issue B
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Very large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.