2.3 TOPOGRAPHY AND CATCHMENT CHARACTERISTICS
The topography and catchment characteristics for the development site, broken down between both Sites A and B, are
discussed below:
2.3.1 Site A – Western Lot
− The high point of the existing site is RL 9.47m AHD located on the eastern side of the site;
− The development falls from the high point at an approximate grade of 2.5% to a low point of RL 3.88m AHD in the
south-western corner;
− During both minor and major storm events, runoff from the site discharges as overland flow over the western
boundary of the development site and onto the environmental zone and natural drainage channel, and is ultimately
conveyed through culverts below Hofmann Drive to Eenie Creek and Lake Weyba;
− As the roadways surrounding the site have been built assuming a fully developed catchment, there is no external
catchment.
2.3.2 Site B – Eastern Lot
− The high point of the existing site is RL 10.63m AHD located on eastern side of the site;
− The development falls from the high point at an approximate grade of 1% to a low point of RL 9.2m AHD in the
south-west corner;
− During both minor and major storm events, runoff from the site discharges as overland flow over the western
boundary of the development site and onto the private access roadway, and is ultimately conveyed to the
stormwater drainage system along the access roadway to Eenie Creek and Lake Weyba;
− Site B is split into two sub-catchments, with a high-point located midway along the private access road frontage,
with flows directed either towards the north-west onto the private access road and around Site A to the
environmental zone and natural drainage channel, or towards the south-west onto the private access roads; and
− As the roadways surrounding the site have been built assuming a fully developed catchment, there is no external
catchment.
See the survey plan in Appendix C for more information.
2.4 EXISTING FLOODING CONDITIONS
From Noosa Shire Council Plan Interactive Mapping, it has been obtained for the site and states the following:
− No flood levels or flags for building development purposes exist for the development site.
− The interactive mapping system within Noosa Shire Council Plan confirms that the development site is not affected
by Eenie Creek or overland flow flooding.
− It is expected that the site is at a low risk of flood inundation.
www.bornhorstward.com.au Page 3
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Appendix C- Serviceability Report.PDFRelated documentApplication case desk ↗
About this file
- File size
- 15.6 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.