Issue – Acid Sulfate Soils Management
Council have identified that the proposed development is encumbered by Council’s Acid
Sulfate Soils hazard overlay. The submitted documentation does not include an Acid Sulfate
Management Plan or make reference to a Dewatering Plan.
Information Required
32.   Demonstrates through a geotechnical report, if the proposed development triggers
      assessment against the Acid Sulfate Soils Overlay Code of The Noosa Plan 2020. If
      assessment is required, provide a site specific Acid Sulfate Soils Management Plan. The
      Acid Sulfate Soils Management Plan must be prepared by a suitably qualified person
      (RPEQ – Registered Professional Engineer of Queensland).
33.   Demonstrate through a geotechnical report, that the proposed development will not
      encounter water during excavations. If the proposed development is likely to encounter
      water during excavation, provide a Dewatering Plan demonstrating how Acid Sulfate
      affected water encountered during excavation will be treated and disposed of. The
      Dewater Plan must be prepared by a suitably qualified person (RPEQ – Registered
      Professional Engineer of Queensland).


Issue – Erosion and Sediment Control
The proposed development will alter the existing drainage conditions of the site during
construction. Council is concerned how sediment leaving the site will be controlled and treated
and how erosion of the site and neighbouring properties will be managed.
Information Request
34.   Provide a Sediment and Erosion Control plan that demonstrates how the site will control
      contaminates leaving the site without causing erosion damage to the site and
      neighbouring properties. The plan must be prepared by a suitably qualified person
      (RPEQ – Registered Professional Engineer of Queensland) and include, but not be
      limited to:
      a. a Maintenance Plan that includes:
             i.   maintenance timeframes
             ii. quantitative or qualitative method of assessing the functionality of each
                 measure
             iii. review of overall measures
      b. Demonstrate how water collected on site will be treated before being leaving the site
         (bio-basin, etc.).


3.    DUE DATE FOR RESPONSE TO INFORMATION REQUEST

The due date for providing the requested information is 2 March 2022. Email your response
to [email protected]. Please advise Council of your response to this information request
in accordance with section 13 of the Development Assessment Rules.
If you do not provide a response before the due date, it will be taken as if you have decided
not to respond to the information request and Council will continue with the assessment of
your application.
4.    OTHER DETAILS

You can follow the progress of this application online at www.noosa.qld.gov.au. The “Online
Services” page can be accessed via "Quick Links" on the left hand side of the screen.



                                                                                     Page 10 of 11
Log in to download the original file

RFI - Traffic Engineering Report.pdf · 19.6 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.