4.2 Car Park Layout
Table 4-2 identifies the characteristics of the proposed parking area with respect to the Council
requirements. The last column identifies the compliance of each design aspect.
Table 4-2: Parking Design Requirements
Design Aspect Minimum AS2890.1 Proposed Provision Compliance
Standard
Parking space length:
− Standard bay 5.4m 5.4m Compliant
Parking space width:
− Staff 2.4m 2.6m Compliant
− Public 2.6m 2.6m
− Vallet 2.4m 2.6m
− PWD 2.4m + 2.4m ‘Shared Area’ 2.4m + 2.4m ‘Shared Area’
Aisle Width:
− Parking aisle 5.8m 6.5m Compliant
− Circulation aisle/ramp 5.8m 6.0-6.5m
Parking envelope clearance – Space 0.3m clear of wall Space 0.3m clear of wall Compliant
space adjacent to wall
Maximum Gradient:
− PWD parking 1:40 (2.5%) Flat Compliant
− Parking bay 1:20 (5.0%) 1:20 (5.0%)
− Parking aisle 1:16 (6.25%) 1:20 (5.0%)
− Ramp 1:5 (20%) 1 in 10 (10.0%)
Height Clearance
− General Min. 2.2m (2.3m PWD) 2.3m Compliant
The proposed car park layout complies with Council’s / Australian Standard requirements and is therefore
considered acceptable.
The proposed porte cochere has been designed to accommodate a 21 seater mini bus, which will be used to
shuttle guests that do not have access to a private vehicle.
Relevant swept paths for the car park and the porte cochere, which demonstrate the acceptability of the
design, are contained in Appendix C.
Information Request (2 December 2023) – Item 28
The proposed modified car park layout has been designed to comply with the relevant standards and has been
certified by RPEQ Brian Camilleri (RPEQ 07577).
Site: 3-7 Serenity Close, Noosa Heads – Proposed Resort Complex 17
Reference: 22BRT022 RP01_1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.