               DEVELOPMENT ASSESSMENT DELEGATED REPORT

               Author                   Senior Development Engineer, Daniel Epps
                                        Development Assessment



                  APPLICATION DETAILS

                  Application No.                   OPW25/0042

                  Applicant                         Calile Malouf Investments P/L TTE

                  Proposal                          Operational Works - Drainage Works, Earthworks

                  Properly Made Date                21 March 2025

                  Information Request Date          16 April 2025

                  Information Response Date         10 June 2025

                  Decision Due Date                 12 August 2025

                  Report Reviewed &                 Will Lowe – 12/08/2025
                  Finalised By


                  PROPERTY DETAILS

                  Property Address                  7 Serenity Cl Noosa Heads Qld 4567

                  RP Description                    Lot 11 SP 195871, Lot 10 SP 335472

                  Land Area                         1213.0000 m²
                                                    11880.000 m²

                  Existing Use of Land              Vacant (Tourist Accommodation)


                  STATUTORY DETAILS

                  SEQRP Designation                 Urban Footprint

                  Zone                              Tourist Accommodation & Environmental Management and
                                                    Conservation

                  Precinct                          Not applicable

                  Local Plan Area                   Noosa Heads

                  Overlays                          Acid Sulfate Soils, Biodiversity, Waterways and Wetlands,
                                                    Bushfire Hazard, Landslide Hazard, and Koala Habitat Area

                  Assessment Type                   Code




Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025
Full text of the other 18 pages

Page 2

               1.     PROPOSAL
               The application seeks approval for Operational Works - Drainage Works, Earthworks.
               The locality and proposal plan are included below.




                                                        Figure 1 – Locality




                                                Figure 2 – Earthworks Plan (1 of 2)

                                                                                               Page 2 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 3

                                        Figure 3 – Earthworks Plan (2 of 2)




                                         Figure 4 – Drainage & RIP Plan



                                                                              Page 3 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 4

               2.     APPLICATION BACKGROUND
               The application is to address the conditions of the higher order approval (132008.176.05).
               3.     SITE DETAILS
               3.1. Site History
               The subject site is the final undeveloped site within Serenity Close.
               3.2. Site Description
               The subject site is approximately 2.4 hectares. The site generally grades from the northwest to the
               southeast with the levels ranging from 22m AHD to 8m AHD. The site consists of loose to dense,
               poorly graded dune sand with high permeability.
               An existing stormwater drainage easement and stormwater line traverses the middle of the site,
               discharging to an existing reserve to the southeast.
               3.3. Surrounding Land Uses
               The subject site is surrounded by low-to-high residential uses, community facilities and the major
               centre (Noosa Junction).
               4.     ASSESSMENT
               4.1. Instruments for Statutory Assessment
               Under the Planning Act 2016 the application must be assessed against each of the following
               statutory planning instruments to the extent they are relevant to the development:
               •      State Planning Policy;
               •      South East Queensland Regional Plan;
               •      Planning Regulation 2017; and
               •      Noosa Plan 2020 (25 September 2020).
               4.2. Noosa Plan 2020
               The following codes from the Noosa Plan 2020 are applicable to this development:
               •      Works Codes – Earthworks, Water Quality and Drainage Code, Transport Code
               •      Overlay Code – Acid Sulfate Soils
               The application has been found to generally comply with all applicable statutory instruments. The
               pertinent issues arising out of the assessment are discussed below:
               Existing Services (Sewer & Stormwater)
               As part of the development of the site, the existing sewer and stormwater infrastructure is to be
               removed and their associated easements extinguished. The infrastructure is to be reconstructed
               on an alternate alignment. To address concerns regarding overland flow and excess gap flow, an
               ephemeral stream (overland flow path) is proposed to control and capture flow.
               The proposed stormwater infrastructure realignment (including the ephemeral stream) was largely
               assessed as part of the higher order approval by Council’s external stormwater consultant. The
               proposed works satisfies the conditions of the higher order approval and remain consistent with
               what was previously assessed.
               To achieve the minimum freeboard within the ephemeral channel, the channel should remain either
               grassed or rock-lined and not be planted. Any future Operational Works – Landscaping must
               remain consistent with the design assumptions contained within the Approved Plans and
               Reference Documents.
               Haulage Operations
               The excavation of the subject site is scheduled to last 12-14 weeks and include the removal of up
               to 100,000m3 of material. Council staff indicated concerns regarding the impact haulage activities

                                                                                                    Page 4 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 5

               would have on the local road network. To satisfy the relevant provisions of the Transport Code, the
               applicant has prepared a Road Safety Audit (RSA), Traffic Impact Assessment (TIA), Pavement
               Impact Assessment (PIA), Traffic Management Plan (TMP) and Traffic Guidance Systems (TGS).
               Road Safety Audit (RSA)
               The RSA has been referred to Council’s Road Reserves team who have indicated support for the
               recommendations made in the RSA. The proposed haulage route navigates Grant Street which is
               a split level local road including on-street parking.
               The findings of the report largely relate to heavy vehicles (HV’s) trafficking Grant Street.
               Recommendations have been made for restricting on-street car parking near corners to allow safe
               turning widths for HV’s. Recommendations for extending traffic and pedestrian management
               controls are also included.
               An updated TMP and TGS including the findings of the RSA will need to be provided to Council
               prior to works commencing.
               Traffic Impact Assessment (TIA)
               The TIA has been referred to Council’s Transport and Traffic team who have indicated support for
               the proposal. The daily haulage operations will include 150 trucks (75 loaded, 75 unloaded) with
               maximum peak hour movements of up to 10 vehicles per hour during the AM/PM/Weekday peaks.
               Traffic data for the Weyba-Reef-Mary roundabout in Noosaville has been forwarded to the
               consulting traffic engineer (Colliers) to assist in the planning and operational of haulage activities.
               Council have indicated significant concerns regarding an increase in traffic during the Christmas
               holiday period. An agreement between Council, Colliers, and the developer to revisit haulage
               operations during the holiday period if required is reflected in a condition of the approval.
               Pavement Impact Assessment (PIA)
               The PIA provides an assessment based on the concept of Standard Axle Repetitions (SARs) for
               local order roads where the overall pavement impact of truck movements will exceed 5% pavement
               design threshold. In this instance, this is relevant for Serenity Close, Banksia Avenue and Grant
               Street.
               The assessment considers and adopts the following parameters:
               •      5,000 loaded trips and 5,000 unloaded trips (assumed volume of 20m3)
               •      Austroads Heavy Vehicle Class 9 (i.e., truck and dog or articulated vehicle)
               •      SAR 4 Granular Pavement, Unloaded SAR – 0.51, Loaded SAR – 4.93
               •      Marginal Cost - $0.136 / SAR-km
               •      Length of Affect Road (i.e., Serenity Close, Banksia Avenue and Grant Street) – 0.85km
               The overall pavement impact is estimated to be ~2,200 SARs in the unloaded direction and
               ~21,000 SARs in the loaded direction. The report proposes a pavement impact offset of $3,145.00
               and recommends additional road repairs during the works (i.e., potholes). It is recommended the
               pavement impact offset is paid prior to Council attending the prestart meeting.
               The PIA has been prepared TMR’s Guidelines and is satisfactory in addressing the relevant
               provisions of The Noosa Plan 2020 – Transport Code.
               Traffic Management Plan (TMP) & Traffic Guidance Systems (TGS)
               The TMP & TGS has been referred to Council’s Traffic Infrastructure Services team who reviewed
               the documents in conjunction with the RSA and have indicated support for the proposal. An
               updated TMP and TGS including the findings of the RSA will need to be provided to Council prior
               to works commencing.
               The TMP & TGS must be implemented in accordance with a Road Reserve Permit from Council.




                                                                                                        Page 5 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 6

               Summary
               The proposed works generally comply with the relevant provisions of The Noosa Plan 2020.
               Engineering recommends the following conditions.
               5.     CONSULTATION
               5.1. Referral Agencies
               Not Applicable
               5.2. Internal Council Referrals
               The application was forwarded to the following internal Council officers for review and/or comment:
               •      Planning Coordinator – Development Assessment
               •      Senior Environment Officer – Development Assessment
               •      Traffic & Transport, IPDD, Assets – Infrastructure Services
               5.3. Other Referrals
               The application was forwarded to the following external experts for review and comment:
               •      Leon Rowlands – Stormwater
                      Condition 46 [of the higher order approval] has been satisfied and the remainder of the
                      application is complaint with the Water Quality and Drainage Code, apart from the following
                      issues which should be conditioned:
                      o       ESC standard conditions should be applied.
                      o       Ensure as part of final landscape design that RIP 3B and RIP 5 are provided with
                              surface levels or an overland flowpath (which may be informal) that will allow any
                              surcharge flows from these devices to flow to a lawful point of discharge without
                              impacting any of the development buildings or facilities.
                      o       Landscape OPW to be consistent with the design assumptions of the overland flow
                              assessment.
                      o       It is also noted that additional times were included in the FIR around the landscape
                              finish and the roughness values for the overland flowpath assumed in the design. The
                              design assumptions are:
                                      ▪ Grass or rock invert for the channel; and
                                      ▪ Landscaped batters
                              A sensitivity test was provided with higher roughness (0.06) applied to the base of the
                              channel, corresponding to landscaped plantings of shrubs and groundcovers. This
                              showed that the freeboard to floor levels would not be exceeded. However, the
                              freeboard would be reduced in some locations to less than the required value.
                              Therefore, it is recommended that when the landscape OPW is submitted, the base of
                              the channel should remain either grassed or rock-lined and not be planted.
               6.     CONCLUSION & REASONS FOR DECISION
               The proposed development generally complies with the requirements of the planning scheme and
               does not raise any significant issues that cannot be addressed by reasonable and relevant
               conditions. The application is therefore recommended for approval.
               The report is provided in accordance with Section 63(5) of the Planning Act 2016.
               RECOMMENDATION
               With regard to Application No OPW25/0042 for Operational Works - Drainage Works, Earthworks
               situated at 7 Serenity Cl Noosa Heads Qld 4567 and described as Lot 11 SP 195871, Lot 10 SP
               335472, it is recommended the application be approved in accordance with the following details
               for the Decision Notice:



                                                                                                       Page 6 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 7

               1.      APPLICATION DETAILS

                   Application No:                  OPW25/0042

                   Street address:                  7 Serenity Cl Noosa Heads Qld 4567

                   Real property description:       Lot 11 SP 195871, Lot 10 SP 335472

                   Planning Scheme:                 Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               Council decided to issue the following type of approval:
               •       Development Permit for Operational Works - Drainage Works, Earthworks
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.
               4.      ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.      Development undertaken in accordance with this approval must generally comply with the
                       approved plans of development. The approved plans are listed in the following table unless
                       otherwise amended by these conditions.

                          Plan No.              Rev.        Plan/Document Name                   Date

                          A6769-24-EW01         A           EARTHWORKS LAYOUT – SHEET 1          27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW02         A           EARTHWORKS LAYOUT – SHEET 2          27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW03         A           EARTHWORKS SECTIONS SHEET 1          27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW04         A           EARTHWORKS SECTIONS SHEET 2          27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW05         A           EARTHWORKS SECTIONS SHEET 3          27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW06         A           EARTHWORKS DETAILS – SHEET 1         27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-EW07         A           EARTHWORKS DETAILS – SHEET 2         27 February
                                                                                                 2025
                                                            Prepared by ALTA

                          A6769-24-D01          B           DRAINAGE LAYOUT                      12        March
                                                                                                 2025
                                                            Prepared by ALTA




                                                                                                      Page 7 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 8

                         A6769-24-D02    A     RIP & RIC DETAILS                27 February
                                                                                2025
                                               Prepared by ALTA

                         A6769-24-D03    B     DRAINAGE    CROSS   SECTIONS   – 12     March
                                               SHEET 1                          2025
                                               Prepared by ALTA

                         A6769-24-D04    A     DRAINAGE    CROSS   SECTIONS   – 27 February
                                               SHEET 2                          2025
                                               Prepared by ALTA

                         A6769-24-D05    A     DRAINAGE    CROSS   SECTIONS   – 27 February
                                               SHEET 3                          2025
                                               Prepared by ALTA

                         A6769-24-D06    A     DRAINAGE    CROSS   SECTIONS   – 27 February
                                               SHEET 4                          2025
                                               Prepared by ALTA

                         A6769-24-D07    A     DRAINAGE LONG SECTION            27 February
                                                                                2025
                                               Prepared by ALTA

                         A6769-24-D08    A     RAPID INFILTRATION DEVICE SITE 27 February
                                               LAYOUT & CATCHMENT PLAN        2025
                                               Prepared by ALTA

                         A6769-24-D09    A     RAPID INFILTRATION CULVERT ‘RIC’ 27 February
                                               LAYOUT                           2025
                                               Prepared by ALTA

                         A6769-24-D10    A     RAPID INFILTRATION CULVERT ‘RIC’ 27 February
                                               SECTION                          2025
                                               Prepared by ALTA

                         A6769-24-WQ01   A     WATER QUALITY LAYOUT             27 February
                                                                                2025
                                               Prepared by ALTA

                         A6769-24-WQ02   A     WATER QUALITY DETAILS            27 February
                                                                                2025
                                               Prepared by ALTA

                         A6769-24-CA01   A     EXTERNAL CATCHMENT LAYOUT        27 February
                                                                                2025
                                               Prepared by ALTA

                         A6779/25/SWMP   OpW(A) STORMWATER MANAGEMENT PLAN Feb 2025
                                                – Operational Works
                                               Prepared by ALTA




                                                                                  Page 8 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 9

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 12 August 2027, unless an application to extend the currency period
                      is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Pavement Impact Assessment
               3.     A one-time Pavement Impact Offset payment of $3,145 must be submitted to Council prior
                      to the pre-start meeting.
               4.     The developer shall bear all costs associated with the repair of any damage to Council assets
                      resulting from haulage operations. This includes, but is not limited to, damage to roads,
                      kerbs, footpaths, and other infrastructure. Where such damage poses a hazard to the
                      community or may lead to further deterioration, repairs must be undertaken immediately.
                      Bonds
               5.     A site control and/or compliance bond of $100,000 is to be submitted to Council prior to the
                      pre-start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
                      The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               6.     Bonds must:
                      a.      have approval of the bond calculations and amount from Council prior to lodgement.
                      b.      be lodged with Council and accompanied by the Bond Administration Fee/s.
                      c.      be requested for release by writing to Council, when relevant approval requirements
                              have been met.
                      Overland Flow Path
               7.     The final planting of the overland flow path undertaken as part of a future permit for
                      Operational Works – Landscaping must remain consistent with the design roughness values.
                      The base of the channel must remain either grassed or rock-lined and not be planted.
                      RIP 3B and RIP 5
               8.     The final planting of RIP 3B and RIP 5 (as shown on the Approved Plans) undertaken as part
                      of a future permit for Operational Works – Landscaping must provide surface levels, or an
                      overland flow path, that will allow any surcharge flows to drain to a lawful point of discharge.
                      Earthworks Haulage Hold Point
               9.     A construction hold point meeting with a Council delegate is required if haulage operations
                      are not completed by 1 December 2025. Council may, at its discretion, direct the applicant
                      to halt all haulage operations until the end of the school holidays.
               10.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods;
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods;

                                                                                                        Page 9 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 10

                      c.      Been revised to address predicted rainfall events; and
                      d.      Achieve the desired environmental outcomes.


               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               11.    An updated Construction/Traffic Management Plan and Traffic Guidance Scheme must be
                      submitted to Council for agreement prior to the pre-start meeting and must specifically
                      address the following:
                      a.      All recommendations identified in the Road Safety Audit (included in reference
                              documents).
                      b.      Methods for addressing traffic impacts identified in the Traffic Impact Assessment
                              (included in reference documents) and including:
                              i.        Demonstrating how the project will ensure haulage does not exceed 75 inbound
                                        or 75 outbound trucks per day, and no more than 10 trucks in / 10 trucks out per
                                        hour.
                              ii.       How truck movements will be monitored and verified (e.g. through delivery
                                        dockets, traffic counters, or similar).
                      c.      A Dilapidation Report for the haulage route commencing from the Serenity Close cul-
                              de-sac and concluding at the Reef – Eenie Creek roundabout (inclusive). The report
                              must include:
                              i.        a video inspection of the defined route; and
                              ii.       an itemised list of each existing defect.
                      d.      Construction/Traffic Management during all aspects of the construct phase including:
                              i.        A Parking Management Plan for construction workers
                              ii.       A waste collection/haulage conflict management plan prepared in collaboration
                                        with Noosa Council’s Waste Team identifying waste collection times and haulage
                                        schedules designed to avoid traffic conflicts.
                              iii.      A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                        Control Devices (MUTCD) detailing all temporary signage and traffic control
                                        measures prior to construction.
                              iv.       Restricting on-street car parking to facilitate safe turning widths for HV’s. (*)
                                        (*) Refer to Advisory Note
                              v.        Maintenance of safe vehicle and pedestrian access across the frontage of the
                                        site both during daily construction and after daily construction has ceased.
                              vi.       Proposed fencing to the site during the construction phase of the development.
                      e.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures.
                      f.      Works programme identifying key components of the works and their respective
                              durations.
                      g.      Establishment of a communication protocol including an on onsite public information
                              session, and correspondence to adjoining owners, emergency services and local
                              businesses to advise of agreed construction times, impacts on traffic and services and
                              other relevant issues.



                                                                                                              Page 10 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 11

                      h.      Include a post out to the local residents and businesses, including all the residents
                              along the haulage route up to Reef-Eenie Creek roundabout advising of the proposed
                              development including the expected time frames and the site contact details.
                      i.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      j.      identification of complaint management procedures including:
                              i.        contact details for the on-site manager.
                              ii.       dispute resolution procedures.
                      k.      details on the location of external fill/dump sites/sources, the haulage route, type of
                              vehicle to be utilised during filling operations and frequency of usage. Note any
                              damage to the existing road system as a result of haulage operations shall be fully
                              repaired at the applicant’s expense.
               12.    All works must be carried out in accordance with a site specific Geotechnical Report prepared
                      by a qualified person* and endorsed prior to a prestart meeting.
                      *(Refer to Advisory Note)
               13.    Prior to the commencement of municipal works associated with this development, Council
                      requires the provision of a bank guarantee, or a cash bond, of not less than 10% (minimum
                      of $5000) of the value of the municipal works.
               14.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.
               15.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
               16.    All necessary approvals from external service providers (e.g., Unitywater) and external
                      parties on which the development works are proposed have been obtained and a copy
                      supplied to Council.
               17.    Copies of the approved plans, duly signed by the consultant Registered Professional
                      Engineer of Queensland (RPEQ) must be provided to Council’s Engineering Officer
                      Construction at the prestart meeting. All plans must be issued “FOR CONSTRUCTION”.
               18.    A condition report of the drainage system must be completed for agreement prior to Council
                      attending the prestart meeting.
                      The condition report is to include CCTV inspection of the existing stormwater network
                      commencing from the existing stormwater pit and manhole fronting 6 Serenity Close (Lot 0
                      on SP188261) and concluding at the existing 600x600 grated field inlet (shown as “1/1” on
                      the Approved Plans).
               19.    A condition report including photographs of the frontage of the site must be completed and
                      submitted to council at the prestart meeting / prior to any works commencing.
               20.    Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               21.    Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Erosion and sediment control works;
                      c.      Other relevant parties.
               22.    Implement all recommendations and communication strategies as identified in condition 11.


                                                                                                      Page 11 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 12

               DURING CONSTRUCTION
                      Engineering
               23.    The developer must meet any costs to repair damage to any Council asset during
                      construction, where damage is a result of the development works. Damage to assets must
                      be repaired immediately where it creates a hazard to the community. In circumstances where
                      the damage does not create a hazard to the community, it must be repaired immediately on
                      completion of the works associated with the development.
               24.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               25.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use approval viz.
                              132008.176.05 to which this approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines; and
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Works within Road Reserve/Reinstatement
               26.    Safe vehicle and pedestrian access on all streets in the vicinity of the development must be
                      maintained at all times. Should footpath/road closures be necessary to carry out construction
                      works, Council’s Development Engineering Officer must be notified prior to the proposed
                      closure and all requirements complied with.
               27.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               28.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Earthworks and Retaining Walls
               29.    All earthworks shall be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill shall be provided by a RPEQ and submitted to Council prior to Council signing
                      the Plan of Survey.
               30.    All earthworks and associated batters/retaining structures, both above and below ground
                      level, both temporary and permanent, must be contained entirely within the subject site
                      unless written permission from the respective landowner(s) is provided to Council.
               31.    Fall protection must be provided to retaining walls that are over 1m high.
               32.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;


                                                                                                      Page 12 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 13

                      c.      1 in 3 for planted areas; and
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               33.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               34.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g., by blocking or interfering with natural overland flows).
               35.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
               36.    Prior to the completion of the development, all site surfaces must be effectively stabilised
                      using methods which have achieved effective short-term stabilisation, and which will continue
                      to achieve effective stabilisation in the medium- to long-term (refer to E&SC Advisory Notes).
                      For the purpose of this condition, an effectively stabilised surface is defined as one that does
                      not or is not likely to result in visible evidence of soil loss caused by sheet, rill or gully erosion
                      or lead to sedimentation, or lead to water contamination.
                      Bioretention Basins – Construction
               37.    During construction and establishment of the bioretention devices, the supervising RPEQ
                      must ensure that the device was constructed in accordance with the document Construction
                      and Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
                      Design, 2009) and that the forms contained in section 3.15 including the associated
                      supporting information and data are completed. These forms and certification from the RPEQ
                      that the device has been constructed in accordance with the Construction and Establishment
                      Guidelines: Swales, Bioretention Systems and Wetlands (Water by Design, 2009), all
                      conditions of approval, and the approved engineering drawings must be submitted to Council
                      prior to commencement of use.
               38.    A construction hold point with a council delegate shall be established once the bioretention
                      device underdrainage pipe work is installed. At the time of inspection, a sample of the
                      drainage layer, transition layer, and filtration media materials must be stockpiled onsite.
                      Laboratory results must be provided for the filter media which demonstrate that the media
                      complies with the specifications contained in the latest version of the “Guidelines for Soil
                      Filter Media in Bioretention Systems” (produced by the Facility for Advancing Water
                      Biofiltration) and that the minimum hydraulic conductivity specified on the approved
                      engineering plans will be achieved. In addition, laboratory results must be provided
                      demonstrating that the transition layer and drainage layer meet the following bridging criteria:
                      a.      D15 (drainage layer) ≤ 5 × D85 (transition layer)
                      b.      D15 (transition layer) ≤ 5 × D85 (filter media).
                      The drainage layer, transition layer, and filtration media materials must not be installed until
                      the catchment draining to the bioretention device has 70% groundcover as determined by
                      Council’s delegate.
                      Erosion and Sediment Control
               39.    Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
                      Regulation 2019) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination. These
                      measures must be designed, implemented and maintained in accordance with “Best Practice
                      Erosion and Sediment Control” published by the International Erosion Control Association
                      (Australasian Chapter) (IECA, 2008), to the extent that such measures and practices are also
                      consistent with the following:
                      a.      Minimise Erosion:

                                                                                                           Page 13 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 14

                              i.        For areas of the site which drain to a sediment basin, implement drainage and
                                        erosion control measures prior to rainfall which prevent or minimise rill erosion
                                        and gully erosion
                              ii.       For areas of the site which do not drain to a sediment basin, implement drainage
                                        and erosion control measures prior to rainfall (including contingency measures)
                                        which prevent or minimise erosion, including rain drop erosion, chemical erosion,
                                        rill erosion and gully erosion
                              iii.      Prior to the sealing of the plan of survey for the development, all site surfaces
                                        must be effectively stabilised using methods which have achieved effective short-
                                        term stabilisation and which will continue to achieve effective stabilisation in the
                                        medium to long-term. For the purpose of this condition, an effectively stabilised
                                        surface is defined as one that does not, or is not likely to result in visible evidence
                                        of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead
                                        to water contamination.
                      b.      Manage concentrated stormwater flows
                              i.        Prior to each rainfall event ensure concentrated stormwater flow paths are
                                        provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
                                        structurally stable in all rainfall events for the following sources:
                                        a)    From stormwater catchments upslope of the area of disturbance which are
                                              either stable or external to the site, ensure stormwater is diverted or
                                              managed either:
                                              I.    around the site or through the site without causing erosion and
                                                    without contaminating the flow; or
                                              ii    if it is impractical to convey the flows around or through the site,
                                                    convey the flows into appropriately sized sediment basins without
                                                    causing erosion.
                                        b)    From all disturbed areas of the site to sediment basin(s) without causing
                                              erosion
                      c.      Minimise sediment released from the site
                              i.        Prior to each rainfall event ensure concentrated stormwater flow paths are
                                        provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
                                        structurally stable in all rainfall events for the following sources:
                                        a)    Each basin is sized and operated in accordance with either a Type-A or
                                              Type-B sediment basin as documented in IECA (2008) Appendix B (June
                                              2018).
                                        b)    Each basin is to be provided with an automated system of flocculent dosing
                                              and a suitable supply of flocculent/coagulant, with the type of
                                              flocculent/coagulant determined based on Chemical Coagulants and
                                              Flocculants Fact Sheet (IECA, 2018).
                                        c)    Markers are provided within each basin indicating the maximum sediment
                                              storage level and any additional water storage capacity for water reuse.
                                        d)    During discharge from the primary outlet system, the concentration of total
                                              suspended solids (“TSS”) discharged does not exceed 50mg/L and that pH
                                              is within the range of 6.5-8.5 unless entering a naturally acidic environment.
                              ii.       Install and maintain additional sediment control measures within the site, as
                                        necessary to maximise sediment capture.
                              iii.      Minimise the tracking of dirt from the site onto roadways. Ensure that all dirt on
                                        roadways caused by vehicles leaving the site is removed without causing water
                                        contamination, prior to rainfall and at least at the end of each work day.

                                                                                                               Page 14 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 15

               40.    Earthworks and the implementation of erosion and sediment controls are undertaken in ways
                      which ensure flooding characteristics (including stormwater quantity characteristics) external
                      to the development site are not worsened during construction for all events up to and
                      including the 1% AEP (1 in 100 year ARI) event.
               41.    Drainage paths must be regularly inspected to ensure the sediment fences/measures are not
                      being bypassed as a result of sediment build up. Sediment laden runoff must be prevented
                      from leaving the subject site and entering neighbouring properties and/or stormwater
                      systems.
               42.    Soil exposure must be limited on the site to a distance of no more than 2m beyond the extent
                      of earthworks shown on the approved plans except where the exposed soil is effectively
                      stabilised without delay and prior to rainfall occurring.
               43.    A log book for the Erosion and Sediment Control measures and inspections must be
                      maintained by the site manager and made readily available to Council when requested. The
                      supervising engineer must verify and endorsed the E&SC measures upon their installation,
                      and periodically check these measures and the log book during construction and the
                      stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
                      fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
                      whether the device should be replaced or repaired. Documentation is to include how the
                      damage was caused and what measures can be implemented to reduce the possibility of
                      repeat occurrences. Any damage to either permanent or temporary water quality control
                      structures or devices is to be immediately rectified at the contractor’s expense.
                      The effectiveness of the erosion and sediment control devices must be monitored. All ESC
                      measures are to be inspected:
                      a.      at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      b.      within 24 hours of expected rain; or
                      c.      within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
                      Damage to Services and Assets
               44.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION
                      Certification
               45.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               46.    A condition report of the drainage system must be completed for agreement prior to the
                      acceptance of “On Maintenance”.
                      The condition report is to include the following CCTV inspections:
                      a.      inspection of the proposed stormwater network, commencing from the existing
                              600x600 grated field inlet (shown as “1/1” on the Approved Plans) and concluding at
                              the existing headwall outlet (shown as “OUT/1” on the Approved Plans). The inspection
                              is to include reporting on all pipes and structures.


                                                                                                        Page 15 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 16

                      b.      inspections of the existing stormwater network commencing from the existing
                              stormwater pit and manhole fronting 6 Serenity Close (Lot 0 on SP188261) and
                              concluding at the existing 600x600 grated field inlet (shown as “1/1” on the Approved
                              Plans).
                      As Constructed Plans and ADAC XML Files (Council)
               47.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.        Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                        conformance with applicable standards and specifications, along with the
                                        relevant descriptions of assets, services and structures and;
                              ii.       Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
                                        information, levels and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      On Maintenance
               48.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
                      Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit;
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy; and
                      c.      maintenance and operational manuals for all proprietary or site specific devices.
                      Off Maintenance
               49.    Prior to requesting an Off Maintenance inspection, the developer must provide a written
                      request for the Off Maintenance inspection.
               50.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements; or
                      b.      submitted certification falsely states works comply with approval requirements.
               51.    A final inspection and approval of the completed reinstatement works by Council’s Inspector
                      is required. Please contact Council on 5329 6500 to arrange for the inspection.


                                                                                                       Page 16 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 17

               5.      REFERENCE DOCUMENTS

                Plan No.                Rev.   Plan/Document Name                                     Date

                BBNE01676-              1      Overland Flow Assessment                               9 June 2025
                0001-REP-001
                                               Prepared by Engeny

                22BRT0122               N.A.   Traffic Impact Assessment (TIA) Prepared by N.A.
                                               Colliers

                N.A.                    N.A.   Traffic Guidance Scheme Prepared by AVADA N.A.
                                               Traffic

                25040286                0      Traffic Management Plan Prepared by AVADA 28/04/2025
                                               Traffic

               6.      REFERRAL AGENCIES

               Not applicable.
               7.      ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                       General Advisory Notes
               1.      As this driveway is a private structure, the owner bears full responsibly for the standard of its
                       construction, maintenance and any liabilities associated with its construction. It is
                       recommended that professional advice be sought for the construction of the driveway to
                       ensure that the driveway is constructed in accordance with standard drawings RS-051.
               2.      Council has undertaken an audit check of the Operational Works drawings in relations to the
                       proposed works. A detailed check of the calculations and drawings has not been undertaken,
                       as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects of
                       the engineering design. Council reserves the right to require further amendments and/or
                       additions at a later date should design errors become apparent.
               3.      Council reserves the right to call up any performance bond held or levy charges against the
                       property, should emergency works be required to be undertaken by Council to make the site
                       safe due to inactivity on the development site for extended periods of time.
               4.      Should any changes or modifications to the approved plans be required as a result of
                       construction constraints, a “Request to change an existing approval” under the Planning Act
                       2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                       application along with the appropriate fees.
                       Prestart, On and Off Maintenance Inspections Request
               5.      Contact Council on 5329 6500 to arrange a prestart or an inspection giving a minimum of 5
                       business days’ notice of preferred inspection time.
               6.      If Council officers are required to undertake additional inspections of the same works, a
                       reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                       applicable at the time.
               7.      A minimum maintenance period of 12 months will apply to all municipal works and thereafter
                       until such time as the works are performing in accordance with the approved design unless
                       noted otherwise.




                                                                                                        Page 17 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 18

                      Qualified Person
               8.     For the purpose of preparing a Geotechnical Report, and for certifying geotechnical stability
                      for the development, a qualified person is considered to be a person who:
                      a.      is a Registered Professional Engineer of Queensland (RPEQ); and
                      b.      has a degree in civil engineering or engineering geology; and
               9.     c. has a minimum of 5 years experience in the field of geotechnical engineering or
                      engineering geology.
                      Environmental Advisory Notes
               10.    The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               11.    Accepted best practice standards include International Erosion Control Association
                      Australasia Best Practice Erosion and Sediment Control.
               12.    Qualified Person, for the purpose of erosion and sediment control is a Certified Professional
                      in Erosion and Sediment Control (CPESC) or suitably experienced Registered Professional
                      Engineer of Queensland (RPEQ).
               13.    As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •    appropriate for slopes and slope lengths; and
                              •    are consistent with best practice environmental management practices such as in
                                   the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                      Performance Bond Agreement
               14.    An applicant for a development application may make an agreement with an assessment
                      manager, referral agency or other person to establish the responsibilities, or secure the
                      performance, of a party to the agreement about a development condition.
                      Road Reserve Permit
               15.    This development permit provides the applicant with written authority to undertake the
                      prescribed works. Any additional activities that are undertaken inside Council’s road reserve
                      for the purpose of acting on this development permit may require a Road Reserve Permit.
                      These additional activities may include, but are not limited to, hoarding, pedestrian
                      diversions, laneway closures, etc. To apply for a Road Reserve Permit, or for more
                      information, Contact Council’s Road Reserve Officer at [email protected] Act 2014 – Fire Ant Control
               16.    Developers must remain vigilant for the presence of fire ants. Under the Biosecurity Act 2014,
                      individuals and businesses are responsible for ensuring that they follow the movement
                      controls for specific organic materials to help prevent the spread of fire ants within South
                      East Queensland’s fire ant biosecurity zones. Movement of a fire ant carrier from within a fire
                      ant biosecurity zone may need a biosecurity instrument permit. More information is available
                      on https://www.fireants.org.au/treat/business-andindustry/movement-controls.



                                                                                                       Page 18 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Page 19

               8.     PROPERTY NOTES

               Not applicable.
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

                Type of Development Permit Required             Subject of the required Development Permit

                Development Permit for Operational Works        Landscaping,    Roadworks,     External   Works,
                                                                Access

               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               During the appeal period, you as the applicant may suspend your appeal period and make written
               representations to Council about the conditions contained within the development approval. If
               Council agrees or agrees in part with the representations, a negotiated decision notice will be
               issued. Only one negotiated decision notice may be given.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available online at
               www.noosa.qld.gov.au or at Council Offices.




                                                                                                    Page 19 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Used in these records

About this file

File size
4.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW25 0042.pdf · 4.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.