Skip to the record
Accept no imitations.

Council archive · source document

Delegated Report - Code - Planning OPW25 0042 · OPW25/0042

of 19

Text shows just the words. Original shows the document exactly as it was published.

                      b.      inspections of the existing stormwater network commencing from the existing
                              stormwater pit and manhole fronting 6 Serenity Close (Lot 0 on SP188261) and
                              concluding at the existing 600x600 grated field inlet (shown as “1/1” on the Approved
                              Plans).
                      As Constructed Plans and ADAC XML Files (Council)
               47.    Prior to acceptance of civil works to become Council assets “On Maintenance”, satisfactory
                      “As-Constructed” records must be submitted to Council. The bundle of “As Constructed”
                      information shall include:
                      a.      As-Constructed Engineering Drawings. Data is to be submitted in an electronic drawing
                              file format (.dwg), with all plans clearly endorsed “As-Constructed”, along with the
                              accompanying hardcopies (PDFs of the As-Constructed .dwg drawing files), and;
                      b.      ADAC XML Digital File. ADAC File format (ADAC - Asset Design As Constructed)
                              prepared in accordance with industry standards and recorded in “MGA - UTM56 /
                              GDA94” projection.
                              Please Note: Further information and advice relating to the as-constructed drawing
                              presentation, as-constructed survey capture and associated guidelines for preparation
                              of a compliant ADAC XML digital file are available on the webpage titled “As-
                              Constructed Guidelines” and accessible at the Noosa Council Website: Planning &
                              Development / Development Tools & Guidelines / As-Constructed Guidelines.
                      c.      The “As-Constructed” drawings will require certification by a:
                              i.        Qualified experienced Civil Engineer (RPEQ) confirming design intent and
                                        conformance with applicable standards and specifications, along with the
                                        relevant descriptions of assets, services and structures and;
                              ii.       Registered Cadastral Surveyor (Qld) in regard to the cadastral and locational
                                        information, levels and applicable survey datum.
                      d.      The data must be in accordance with Council’s “Planning Scheme Policy 6 –
                              Engineering Design Standards”, and fully detail the levels for all engineering works
                              including but not limited to the drainage network and structures, finished ground and
                              pavement surface levels.
                      On Maintenance
               48.    All municipal works must be accepted ‘On Maintenance’ by Council in accordance with
                      Council’s relevant Planning Scheme Policy prior to plan sealing. To achieve ‘On
                      Maintenance’, the supervising RPEQ must submit to Council:
                      a.      certification that all works have been undertaken and completed in accordance with the
                              requirements of this Permit;
                      b.      as Constructed details in accordance with Council’s Planning Scheme Policy; and
                      c.      maintenance and operational manuals for all proprietary or site specific devices.
                      Off Maintenance
               49.    Prior to requesting an Off Maintenance inspection, the developer must provide a written
                      request for the Off Maintenance inspection.
               50.    A re-inspection fee in accordance with Council’s Fees and Charge Register will be charged
                      where:
                      a.      a Council inspection reveals works do not comply with approval requirements; or
                      b.      submitted certification falsely states works comply with approval requirements.
               51.    A final inspection and approval of the completed reinstatement works by Council’s Inspector
                      is required. Please contact Council on 5329 6500 to arrange for the inspection.


                                                                                                       Page 16 of 19

Document Set ID: 23831232
Version: 12, Version Date: 12/08/2025

Used in these records

About this file

File size
4.6 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Delegated Report - Code - Planning OPW25 0042.pdf · 4.6 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.