Skip to the record
Trusted by locals. Built for Noosa.

Council archive · source document

Minor Change Existing Approval OPW19 0266 03 · OPW19/0266.03

of 18

Text shows just the words. Original shows the document exactly as it was published.

                                                                                  Officer:            Will Lowe
                                                                                  Direct Telephone:   07 53296129
                                                                                  Our Reference:      OPW19/0266.03
                                                                                  Your Reference:     23022

               31 October 2023


               Adams + Sparkes Town Planning
               C/- Adams + Sparkes Town Planning
               PO Box 1000
               BUDDINA QLD 4575


               [email protected]



               Dear Sir/Madam,
                                             Decision Notice – Minor Change
                                                         Planning Act 2016

               I refer to your application received on 17 October 2023, requesting a minor change to an existing
               development approval. Council decided your requested changes.
               Details of the decision are as follows:
               1.      APPLICATION DETAILS

                   Application No:              OPW19/0266.03

                   Street address:              215 David Low Way Peregian Beach Qld 4573

                   Real property description:   Lot 1 SP 286680

                   Planning Scheme:             Noosa Plan 2020 (25 September 2020)

               2.      DECISION DETAILS

               The following type of approval was issued on 13 October 2020
               •       Development Permit for Operational Works - Earthworks, Landscaping, Stormwater
               In relation to the request to make a minor change to the existing approval, Council on
               27 October 2023, decided to approve the requested changes. The changes are detailed below.
               A.      Approve the change.
               B.      Amend conditions 1.
               3.      CURRENCY PERIOD OF APPROVAL

               The currency period for this development approval is stated in the conditions below.




               ABN 97.969.214.121                                                             PO Box 141
               noosa.qld.gov.au                                                        Tewantin QLD 4565
               [email protected]                                                        07 5329 6500
                                                                                                        Page 1 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023
Full text of the other 17 pages

Page 2

               4.     ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                         Plan No.      Rev.   Plan/Document Name                               Date

                         18164/C01     C      Bulk Earthworks Layout Plan                      22/11/2019
                                              Prepared by Morgan Consulting Engineers

                         18164/C02     B      Bulk Earthworks Layout Plan – Sheet 1            17/09/2019
                                              Prepared by Morgan Consulting Engineers

                         18164/C03     C      Bulk Earthworks Layout Plan – Sheet 2            22/11/2019
                                              Prepared by Morgan Consulting Engineers

                         18164/C04     B      Bulk Earthworks Sections                         17/09/2019
                                              Prepared by Morgan Consulting Engineers

                         18164/C10     H      Siteworks and Drainage Layout Plan               20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C11     H      Siteworks and Drainage Plan – Sheet 1            20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C12     I      Siteworks and Drainage Plan – Sheet 2            20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C13     D      Siteworks and Drainage Details                   12/03/2020
                                              Prepared by Morgan Consulting Engineers

                         18164/C14     F      Bio-Retention Basin Details                      20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C15     G      Detention Tank Details – Sheet 1                 20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C16     G      Detention Tank Details – Sheet 2                 20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C21     F      Stormwater Longitudinal Sections                 20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C24     C      Stormwater Drainage Manhole Details              20/6/2022
                                              Prepared by Morgan Consulting Engineers

                         18164/C50     C      Retaining Wall Plan – Sheet 1                    17/09/2019
                                              Prepared by Morgan Consulting Engineers



                                                                                                  Page 2 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 3

                         18164/C51     D   Retaining Wall Plan – Sheet 2                 22/11/2019
                                           Prepared by Morgan Consulting Engineers

                         18164/C52     B   Retaining Wall Details                        17/09/2019
                                           Prepared by Morgan Consulting Engineers

                         WD-A-100      8   Site Plan – Ground Floor Detail               April 2019
                                           Prepared by Red Door Architecture

                         SK-B-001      2   Ground Floor Plan                             2019
                                           Prepared by Red Door Architecture

                         WD-B-740      1   Entry Gates Details                           2019
                                           Prepared by Red Door Architecture

                         0             O   Cover Sheet                                   12/10/2023
                                           Prepared Andrew Gold Landscape Architect

                         1             O   Landscape Work Notes                          12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         2a            O   Planting Schedule                             12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         2b            O   Planting Images                               12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         2C            O   Planting Images                               12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         3             O   Overall Landscape Plan                        12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         4             O   As-constructed Fences Plan                    12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         5             O   Existing Trees Plan                           12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         6             O   Surface Finishes Plan 1                       12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         7             O   Surface Finishes Plan 2                       12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         8             O   Surface Finishes Plan 3                       12/10/2023
                                           Prepared by Andrew Gold Landscape Architect

                         9             O   Surface Finishes Plan 4                       12/10/2023


                                                                                           Page 3 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 4

                                                 Prepared by Andrew Gold Landscape Architect

                         10              O       Surface Finishes Plan 5                                  12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         11              O       Planting Plan 1                                          12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         12              O       Planting Plan 2                                          12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         13              O       Planting Plan 3                                          12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         14              O       Planting Plan 4                                          12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         15              O       Planting Plan 5                                          12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

                         16              O       Details                                                  12/10/2023
                                                 Prepared by Andrew Gold Landscape Architect

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 13 October 2022, unless an application to extend the currency period
                      is approved by Council.
               SITE SPECIFIC CONDITIONS
               3.     Prior to any clearing of the 18 non-juvenile koala habitat trees within mapped Low Value
                      Bushland habitat, as identified in the Fauna Management Plan, the significant residual impact
                      of the clearing must be offset. To this end, a notice of election in accordance with Section 18
                      of the Queensland Environmental Offsets Act 2014 must be endorsed by Council.
               4.     The building works of the development are proposed to be staged (Stage 1 – Motel; Stage 2
                      – Dwellings units). Prior to commencing the use of the Motel and construction of Stage 2
                      buildings, a comprehensive and updated Traffic Management plan must be provided to
                      council.
                      The TMP must be in accordance with Manual of Uniform Traffic Control Devices (MUTCD)
                      detailing all temporary signage and traffic control measures, including but not limited to, the
                      interface between construction related traffic (Stage 2 buildings) and motel related traffic
                      (operational).
               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               5.     All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               6.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council prior to the prestart meeting.




                                                                                                             Page 4 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 5

               7.     A detailed condition report of the existing retaining wall (Peregian Beach Hotel – on the
                      eastern boundary of the proposed development) must be provided to council prior to the
                      prestart meeting. This report must include, but not be limited to: photographs; and a
                      document, prepared by a RPEQ, outlining the findings of the wall’s visual assessment.
               8.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               9.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6245. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Electrical reticulation works;
                      d.      Erosion and sediment control works;
                      e.      Other relevant parties.
               10.    A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;
                              ii.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased;
                              iii.     Proposed fencing to the site during the construction phase of the development;
                              iv.      Adequate parking arrangements for construction workers;
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off.
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures.
                      c.      Works programme identifying key components of the works and their respective
                              durations.
                      d.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues.
                      e.      identification of complaint management procedures including:
                              i.       contact details for the on-site manager;
                              ii.      dispute resolution procedures.
                      f.      For haulage operations involving significant volumes of fill material or excavated
                              material being transported onto or off the site: details on the location of external fill
                              sites/sources, the haulage route, type of vehicle to be utilised during filling operations
                              and frequency of usage. NB any damage to the existing road system as a result of
                              haulage operations must be fully repaired at the applicant’s expense.
               11.    Any changes to the details associated with the supervising RPEQ or Principal Contractor
                      during construction, must be notified to council in writing within five business days of the
                      change occurring.




                                                                                                          Page 5 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 6

               12.    Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.
                      Environment
               13.    Lot 900SP286680 (western park area) must:
                      a.      Be protected with a 1.8m high temporary safety fence.
                      b.      Have the fence installed prior to the prestart meeting and maintained for the entire
                              period of construction.
                      c.      Have ‘Exclusion Zone’ (‘No Go’) signage fixed to the fence at 10m centres.
                      d.      Have no construction material, equipment or personnel entering the park except to
                              undertake approved civil works.
                      e.      Be protected from any damage.
                      *(Refer to Advisory Note)
               14.    Vegetation in Rufous Lane must:
                      a.      Be protected with a 1.8m high temporary safety fence.
                      b.      Have the fence installed prior to the prestart meeting and maintained for the entire
                              period of construction.
                      c.      Have ‘Exclusion Zone’ (‘No Go’) signage fixed to the fence at 10m centres.
                      d.      Have no construction material, equipment or personnel entering the park except to
                              undertake approved civil works.
                      e.      Be protected from any damage.
               DURING CONSTRUCTION
                      Engineering
               15.    All works must be supervised by a Registered Professional Engineer of Queensland (RPEQ)
                      who is independent of the Developer and Principal Contractor, and they must certify that all
                      works conform to the Operational Works permit. Where municipal works are involved, such
                      confirmation must be submitted for the respective hold points prior to any site inspection by
                      Council Officers.
               16.    All works must be constructed and work procedure undertaken in accordance with:
                      a.      The approved plans/documents and conditions detailed in this Decision Notice;
                      b.      The relevant conditions of the higher order Material Change of Use and
                              Reconfiguration of Lot approval viz. MCU16/0153 & REC16/0041 to which this
                              approval relates;
                      c.      All relevant Noosa Council Planning Scheme Policies, standard drawings, standard
                              specifications and guidelines;
                      d.      The latest version of the Healthy Waterways document “Water Sensitive Urban Design
                              Technical Design Guidelines for South East Queensland” for all water quality devices
                              to be constructed on site.
                      Roadworks
               17.    All pavement widening or construction of new pavement must join neatly to the existing
                      pavement so that there are no irregularities in line or level resulting at or adjacent to the join
                      for the length of the construction. Where necessary the existing pavement must be brought
                      to a satisfactory standard to allow for the above.




                                                                                                         Page 6 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 7

               18.    The installation and/or modification of any traffic signs, street signs, line marking and Raised
                      Reflective Pavement Markings (RRPMs) must be in accordance with the Manual of Uniform
                      Traffic Control Devices (MUTCD). New or relocated signage must be installed using the VLok
                      installation system. All new signage must be Class 1 retroreflective material in accordance
                      with AS 1906.1, Retroreflective materials and devices for road traffic control purposes – Part
                      1: Retroreflective sheeting.
               19.    The developer must notify Council’s Traffic Engineer for any works involving the removal or
                      modification of existing council traffic signs and/or parking bays prior to such works
                      commencing.
               20.    Root barriers are required to be installed behind the back of kerb for all new kerbs within 5m
                      of a trunk of a tree.
                      Pavement Design and Construction
               21.    Pavement design for privately owned works must be undertaken in accordance with the
                      relevant standards. Structural integrity of the driveway and car park areas will remain the
                      responsibility of the property owner/developer and must be certified by an RPEQ.
                      Works within Road Reserve/Reinstatement
               22.    Safe pedestrian access on all streets in the vicinity of the development must be maintained
                      at all times. Should footpath/road closures be necessary to carry out construction works,
                      Council’s Engineering Officer must be notified prior to the proposed closure and all
                      requirements complied with.
               23.    All frontage works must match neatly with existing road and verge/footpath features.
                      Additional works beyond the frontage may be required to provide an acceptable transition to
                      existing road and verge/footpath profiles.
               24.    Electrical conduits or other services proposed to be installed within existing and proposed
                      road reserves under existing sealed carriageways, concrete pathways, concrete/sealed
                      driveways or significant vegetation must be installed by boring. Trenching is not permitted,
                      unless specifically approved by Council.
                      Pathways
               25.    All pathways must be constructed in accordance with the following requirements:
                      a.      All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065;
                      b.      Provision must be made for disabled access at all kerb crossings associated with
                              pathways, in accordance with Council's current standards;
                      c.      All paths must have a slip resistant surface;
                      d.      Expansion and contraction joints must provide a flush finish. Installation of joints by
                              saw cutting is preferred to ensure a smooth ride for cyclists;
                      e.      The required work includes any modifications to ensure the footpath finishes flush with
                              all existing service covers and the like, or alternatively these services are raised or
                              altered, so as not to create a pedestrian safety hazard.
               26.    Pathways must:
                      a.      terminate in a manner that ensures smooth transition to existing surfaces for public
                              safety;
                      b.      be designed and constructed to comply with the Disability Discrimination Act (DDA),
                              Access to Premises Standard, Austroads and relevant sections of AS1428 Design for
                              access and mobility.
                      Site Access and Driveways
               27.    Driveway crossovers must be constructed generally in accordance with council’s Standard
                      Drawings RS-049 and RS-050 and respective addendums.



                                                                                                       Page 7 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 8

               28.    Any existing unnecessary or redundant property accesses must be removed, and the kerb,
                      footpath and verge area reinstated to match the existing footpath and/or verge treatments.
                      Grassed verge areas to be reinstated must be provided with 100 mm topsoil and grass seed
                      or turf, and must be maintained by the developer until established.
               29.    The following must be complied with during the construction of the required
                      crossover/driveway:
                      a.      The driveway surfacing must consist of either an approved hot mixed asphaltic
                              concrete or patterned/plain concrete;
                      b.      The driveway must be constructed so as not to concentrate stormwater runoff onto
                              neighbouring properties;
                      c.      Where there is an existing pedestrian path, a matching crossfall must be provided for
                              the driveway on the alignment of the path, for the full width of the path;
                      d.      The property access must be located a minimum of 1m clear of existing power poles,
                              streetlights or other signage. The developer is responsible for any necessary relocation
                              of existing services to provide this clearance and must contact the relevant service
                              authorities and comply with their requirements in relation to these works.
                      Earthworks and Retaining Walls
               30.    All earthworks must be undertaken in accordance with the provisions of AS 3798 Guidelines
                      on Earthworks for Commercial and Residential Development, with geotechnical testing
                      undertaken in accordance with Section 8 of the Standard, and to a minimum of ‘Level 1’ as
                      defined in Appendix B. Test results as required by AS 3798, and a certificate of quality and
                      uniformity of fill must be provided by a RPEQ and submitted to Council prior to Council
                      signing the Plan of Survey.
               31.    All earthworks must be undertaken in accordance with the recommendations of report 20014-
                      001-Rev0, titled “Acid Sulfate Soil & Groundwater Management Plan”, prepared by Tectonic
                      Geotechnical & Environmental Engineers and dated 17 February 2020.
               32.    Fall protection must be provided to retaining walls that are over 1m high.
               33.    Slope and batters are a maximum grade of:
                      a.      1 in 6 where in proximity to waterbodies;
                      b.      1 in 4 for grassed areas;
                      c.      1 in 3 for planted areas;
                      d.      1 in 2 for combined structural engineering and planting solutions.
                      Stormwater Drainage
               34.    Appropriate scour protection must be provided at the outlet of all stormwater pipes including
                      temporary outlets.
               35.    Works associated with this permit must not adversely impact on the existing drainage
                      conditions on other properties (e.g. by blocking or interfering with natural overland flows).
               36.    Construction of all internal stormwater drainage works must comply with the relevant
                      section/s of Australian Standard AS/NZS 3500.3.
                      Stormwater Harvesting
               37.    Operating stormwater harvesting tanks must be provided for the development. The tanks
                      must be provided in accordance with an approval for Building Works and must include in
                      particular:
                      a.      a total tank capacity of 3kL per residential unit and 200kL for the hotel;
                      b.      provision of a pump and irrigation system for each tank to enable stormwater reuse for
                              irrigation purposes of landscape areas.



                                                                                                           Page 8 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 9

                      Bioretention Basins – Construction
               38.    The 150mm diameter collector pipe and riser sections of the sub-soil drains of the
                      bioretention device are to be provided as solid-walled pipes and not slotted. The Sub-soil
                      pipes may be laid on zero grade for a saturated zone system. The drainage layer is to be
                      increased to a minimum depth of 350mm.
               39.    During construction and establishment of the bioretention devices, the supervising RPEQ
                      must ensure that the device was constructed in accordance with the document Construction
                      and Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
                      Design, 2009) and that the forms contained in section 3.15 including the associated
                      supporting information and data are completed. These forms and certification from the RPEQ
                      that the device has been constructed in accordance with the Construction and Establishment
                      Guidelines: Swales, Bioretention Systems and Wetlands (Water by Design, 2009), all
                      conditions of approval, and the approved engineering drawings must be submitted to Council
                      prior to commencement of use.
               40.    A construction hold point with a council delegate shall be established once the bioretention
                      device underdrainage pipe work is installed. At the time of inspection, a sample of the
                      drainage layer, transition layer, and filtration media materials must be stockpiled on-site.
                      Laboratory results must be provided for the filter media which demonstrate that the media
                      complies with the specifications contained in the latest version of the “Guidelines for Soil
                      Filter Media in Bioretention Systems” (produced by the Facility for Advancing Water
                      Biofiltration) and that the minimum hydraulic conductivity specified on the approved
                      engineering plans will be achieved. In addition laboratory results must be provided
                      demonstrating that the transition layer and drainage layer meet the following bridging criteria:
                      a.      D15 (drainage layer) ≤ 5 × D85 (transition layer);
                      b.      D15 (transition layer) ≤ 5 × D85 (filter media).
                      The drainage layer, transition layer, and filtration media materials shall not be installed until
                      the catchment draining to the bioretention device has 70% groundcover as determined by
                      Council’s delegate.
                      Bioretention Basins – Maintenance
               41.    The bioretention device must be maintained in accordance with the document titled ‘Bio-
                      Retention Operational Management and Maintenance Guideline’ provided as Appendix E of
                      the ‘Site Based Stormwater Management Plan’ prepared by Morgan Consulting Engineers
                      dated 12th March 2020. The approved Operational Works drawings for the stormwater quality
                      treatment system and detailed life cycle costing of the system must be attached as an
                      addendum to this document. Records of all maintenance activities undertaken must be kept
                      and made available to Council upon request.
               42.    Any proposed Community Management Statement required for the development must
                      include the document titled ‘Bio-Retention Operational Management and Maintenance
                      Guideline’ provided as Appendix E of the ‘Site Based Stormwater Management Plan’
                      prepared by Morgan Consulting Engineers dated 12th March 2020 and must include the full
                      cost of maintaining the system in accordance with this document. The cost of maintaining
                      the system must be included in the proposed levies for each unit owner.
                      Environment
               43.    Prescribed Water Contaminants (as defined in Schedule 9 of Environmental Protection
                      Regulation 2008) must not be released from the site or to waters within the site, or be likely
                      to be released should rainfall occur, unless all reasonable and practicable measures are
                      taken to prevent or minimise the release and concentration of contamination. These
                      measures must be designed, implemented and maintained in accordance with “Best Practice
                      Erosion and Sediment Control” published by the International Erosion Control Association
                      (Australasian Chapter) (IECA, 2008), to the extent that such measures and practices are also
                      consistent with the following:



                                                                                                        Page 9 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 10

                      (a)     Minimise Erosion
                              (i)       For areas of the site which drain to a sediment basin, implement drainage and
                                        erosion control measures prior to rainfall which prevent or minimise rill erosion
                                        and gully erosion;
                              (ii)      For areas of the site which do not drain to a sediment basin, implement drainage
                                        and erosion control measures prior to rainfall (including contingency measures)
                                        which prevent or minimise erosion, including rain drop erosion, chemical erosion,
                                        rill erosion and gully erosion;
                              (iii)     Prior to the sealing of the plan of survey for the development, all site surfaces
                                        must be effectively stabilised using methods which have achieved effective short-
                                        term stabilisation and which will continue to achieve effective stabilisation in the
                                        medium to long-term. For the purpose of this condition, an effectively stabilised
                                        surface is defined as one that does not, or is not likely to result in visible evidence
                                        of soil loss caused by sheet, rill or gully erosion or lead to sedimentation, or lead
                                        to water contamination.
                      (b)     Manage concentrated stormwater flows
                              (i)       Prior to each rainfall event ensure concentrated stormwater flow paths are
                                        provided with capacity in accordance with IECA (2008) Table 4.3.1 and are
                                        structurally stable in all rainfall events for the following sources:
                                      (a) From stormwater catchments upslope of the area of disturbance which are
                                          either stable or external to the site, ensure stormwater is diverted or managed
                                          either:
                                         (i) around the site or through the site without causing erosion and without
                                             contaminating the flow; or
                                         (ii) if it is impractical to convey the flows around or through the site, convey the
                                              flows into appropriately sized sediment basins without causing erosion
                                      (b) From all disturbed areas of the site to sediment basin(s) without causing erosion
                      (c)     Minimise sediment released from the site
                              (i)       Install and maintain sediment basins for each disturbed catchment area of the
                                        site and including undisturbed catchments which cannot be diverted, such that:
                                      (a) Each basin is sized and operated in accordance with either a Type-A or Type-B
                                          sediment basin as documented in IECA (2008) Appendix B (June 2018).
                                      (b) Each basin is to be provided with an automated system of flocculant dosing and
                                          a suitable supply of flocculant/coagulant, with the type of flocculant/coagulant
                                          determined based on Chemical Coagulants and Flocculants Fact Sheet (IECA,
                                          2018).
                                      (c) Markers are provided within each basin indicating the maximum sediment
                                          storage level and any additional water storage capacity for water reuse.
                                      (d) During discharge from the primary outlet system, the concentration of total
                                          suspended solids (“TSS”) discharged does not exceed 50mg/L and that pH is
                                          within the range of 6.5-8.5 unless entering a naturally acidic environment.
                              (ii)      Install and maintain additional sediment control measures within the site, as
                                        necessary to maximise sediment capture.
                              (iii)     Minimise the tracking of dirt from the site onto roadways. Ensure that all dirt on
                                        roadways caused by vehicles leaving the site is removed without causing water
                                        contamination, prior to rainfall and at least at the end of each work day.




                                                                                                               Page 10 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 11

               44.    Sediment and erosion control measures must be in place prior to works commencing. If such
                      measures are not in place or are not satisfactory, “on the spot” fines may be issued. Such
                      fines can be issued if sediments from the site are found to enter or have the potential to enter
                      Council’s stormwater system, natural waterways, any downstream stormwater filtration
                      system or adversely impacting on other properties. The sediment and erosion control design
                      and measures have NOT been approved, it is the site's Supervising Engineer who is
                      responsible for ensuring that the sediment and erosion control measures have:
                      a.      Been duly designed by an RPEQ or CPESC and constructed in accordance with "best
                              practise" methods,
                      b.      Been revised by an RPEQ or CPESC to address the issues raised by changes in the
                              projected construction schedule and/or methods,
                      c.      Been revised to address predicted rainfall events, and
                      d.      Achieve the desired environmental outcomes.
                      Council may request further controls to be installed should the implemented measures be
                      found inefficient.
               45.    Earthworks and the implementation of erosion and sediment controls are undertaken in ways
                      which ensure flooding characteristics (including stormwater quantity characteristics) external
                      to the development site are not worsened during construction for all events up to and
                      including the 1% AEP (1 in 100 year ARI) event.
               46.    Drainage paths must be regularly inspected to ensure the sediment fences/measures are not
                      being bypassed as a result of sediment build up. Sediment laden runoff must be prevented
                      from leaving the subject site and entering neighbouring properties and/or stormwater
                      systems.
               47.    Soil exposure must be limited on the site to a distance of no more than 2m beyond the extent
                      of earthworks shown on the approved plans except where the exposed soil is effectively
                      stabilised without delay and prior to rainfall occurring.
               48.    A log book for the Erosion and Sediment Control measures and inspections must be
                      maintained by the site manager and made readily available to Council when requested. The
                      supervising engineer must verify and endorsed the E&SC measures upon their installation,
                      and periodically check these measures and the log book during construction and the
                      stabilisation stages. Any defects in erosion and sediment control devices, such as sediment
                      fences, are to be inspected and documented. Upon Inspection, the contractor is to determine
                      whether the device should be replaced or repaired. Documentation is to include how the
                      damage was caused and what measures can be implemented to reduce the possibility of
                      repeat occurrences. Any damage to either permanent or temporary water quality control
                      structures or devices is to be immediately rectified at the contractor’s expense.
                      The effectiveness of the erosion and sediment control devices must be monitored. All ESC
                      measures are to be inspected:
                      •       at least daily (when work is occurring on site) or weekly (when work is not occurring on
                              site); or
                      •       within 24 hours of expected rain; or
                      •       within 18 hours of a rainfall event (i.e. an event of sufficient intensity and duration to
                              mobilise sediment on site).
                      Fauna Management
               49.    A qualified person* must be engaged to manage fauna prior and during clearing to:
                      a.      Ensure works are carried out in accordance with the approved Fauna Management
                              Plan and the Nature Conservation Act 1992.
                      b.      Undertake pre-clearing inspections including fauna relocation and removal or blocking
                              of all vacant hollows.


                                                                                                        Page 11 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 12

                      c.      Ensure clearing works avoids nesting times of animals and birds.
                      d.      Provide a written report to Council with the request for the prestart meeting of all pre-
                              clearing activities and initiatives.
                      e.      Co-ordinate staging and sequence of clearing with fauna protection.
                      f.      Protect and recover fauna during clearing operations (fauna not previously removed).
                      g.      Manage the translocation of animals and recovery procedures in accordance with
                              relevant legislation.
                      h.      Undertake protection works for mulching of any stockpiled vegetation.
                      i.      Provide certification to Council prior to the issue of building approval, the works were
                              conducted in accordance with the approved Fauna Management Plan.
                      *(Refer to Advisory Note)
                      Removal of Existing Trees and Vegetation
               50.    Vegetation removal, felling and lopping must:
                      a.      Retain old growth tree hollows and suitably relocate and distribute for nesting fauna.
                      b.      Mulch all other wood and leaf material (without root balls, soil or debris and minimising
                              weed seeds) for re-usable mulch.
                      c.      Have mulch for re-use in landscape or rehabilitation stockpiled and aged for a minimum
                              of three months.
                      d.      Have mulch stockpiles no larger than 1000m3, 2.5m in height and with 10m separation
                              between piles*.
                      e.      Allow for existing endemic ground flora to be translocated to suitable landscaping and
                              rehabilitation areas.
                      f.      Conclude with the area being stabilised against erosion, landscaped, rehabilitated and
                              revegetated.
                      *(Refer to Advisory Note)
                      Landscaping Works
               51.    Landscape works must be supervised, undertaken and certified by qualified persons*. All
                      works must be completed in accordance with this Decision Notice, prior to the
                      commencement of use for each stage.
                      (* Refer to Advisory Note)
               52.    All landscape works must be established and maintained in accordance with the approved
                      design for the life of the development, and in a manner that ensures healthy, sustained and
                      vigorous plant growth. All plant material must be allowed to grow to full form and be
                      refurbished when its life expectancy is reached.
               53.    Landscape works must:
                      a.      Ensure compliance with the approved Landscape Plans, as amended by Council.
                      b.      Ensure native trees of a minimum bag size of 100L are established to replace existing
                              trees to be removed from the site, at the rate of 1 replacement tree for every tree
                              removed that has a diameter greater than 200mm measured at 1.2 metres from ground
                              surface level.
                      c.      Ensure amenity or sales signage and ancillary infrastructure is not installed within the
                              road reserve.
                      d.      Ensure permanent irrigation is not installed within the road reserve.
                      e.      Ensure works are in accordance with the approved bushfire report.



                                                                                                        Page 12 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 13

                      f.      Any fencing has muted natural tones to blend with the natural environment.
                      g.      Ensure mulch is aged, comprised of leaf and limb material of varying sizes, free of
                              foreign matter including anthropogenic waste, rock, soil/sediment contamination and is
                              applied to all planting areas to ensure a minimum 100mm depth once settled.
                      h.      Turfed areas must be must be free of pest, diseases and weeds and level with adjoining
                              surfaces.
                      i.      Ensure all biobasin batters are adequately stabilised and densely planted.
                      Bushfire Management
               54.    A qualified person* must be engaged for the duration of the works to ensure:
                      a.      Works are carried out in accordance with the referenced Bushfire Management
                              PlanA3-FINAL 280319 Report, where required by these conditions.
                      b.      Bushfire Management PlanA3-FINAL 280319 must be certified and endorsed by
                              Council as meeting the requirements of the higher order approval by a suitably qualified
                              person*, prior to the issue of building approval.
                      c.      Emergency Response Plan -Essence of Peregian Beach Hotel must be certified and
                              endorsed by Council as meeting the requirements of the higher order approval by a
                              suitably qualified person*, prior to the issue of building approval.
                      d.      Emergency Response Plan -Essence of Peregian Beach Residential Units must be
                              certified and endorsed by Council as meeting the requirements of the higher order
                              approval by a suitably qualified person*, prior to the issue of building approval.
                              (* Refer to Advisory Note)
                      Environmental Management Plan
               55.    All works must be in accordance with the approved Environmental Management Plan.
               56.    Prior to issue of any building approval, certification from a qualified person* must be provided
                      to Council certifying compliance with the approved Environmental Management Plan.
                      (* Refer to Advisory Note)
                      Damage to Services and Assets
               57.    Any damage caused to existing services and assets as a result of the development works
                      must be repaired at no cost to the asset owner at the following times:
                      a.      where the damage would cause a hazard to pedestrian or vehicle safety, immediately;
                              or
                      b.      where otherwise, upon completion of the works associated with the development.
                      Any repair work which proposes to alter the alignment or level of existing services and assets
                      must first be referred to the relevant service authority for approval.
               FOLLOWING CONSTRUCTION / PRIOR TO COUNCIL SIGNING THE PLAN OF SURVEY
                      Certification
               58.    Upon completion of the work a certificate must be issued by an RPEQ certifying that the
                      works have been constructed in accordance with the Operational Works permit.
               59.    Certification that the existing retaining wall (Peregian Beach Hotel – on the eastern boundary
                      of the proposed development) has not been damaged nor structurally compromised by the
                      development works, must be provided by the supervising engineer.
               60.    A final inspection and approval of the works and completed reinstatement works by Council’s
                      Inspector is required. Please contact Council on 5329 6245 to arrange for the inspection.




                                                                                                       Page 13 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 14

                      Maintenance Bonds
               61.    The developer is responsible for the maintenance of all development works which are to
                      become Council assets (includes civil infrastructure, landscaping, open space areas, park
                      improvements) for a minimum period of 12 months or as otherwise advised by Council. This
                      period will commence from Council’s formal acceptance of the development “on
                      maintenance”.
               62.    The developer must submit a Maintenance Bond to Council to ensure the above works are
                      maintained during this period. The maintenance bond must be:
                      a.      5% of the agreed value of the development obligations; or
                      b.      $1500, whichever is the greater amount.
               5.     REFERRAL AGENCIES

               Not applicable.
               6.     REFERENCED DOCUMENTS

                           JOOO488            2      Fauna Management Plan prepared by 21/11/2019
                                                     North Coast Environmental Services

                           JOOO488            2      Environmental Management Plan prepared 21/11/2019
                                                     by North Coast Environmental Services

                                                     Bushfire    Management      PlanA3-FINAL 19/03/2019
                                                     280319

                                                     Emergency Response Plan -Essence of Undated
                                                     Peregian Beach Residential Units

                                                     Emergency Response Plan -Essence of Undated
                                                     Peregian Beach Hotel

               7.     ADVISORY NOTES

               The following notes are included for guidance and information purposes only and do not form part
               of the assessment manager conditions:
                      General Advisory Notes
               1.     Council has undertaken an audit check of the Operational Works drawings in relations to the
                      proposed works. A detailed check of the calculations and drawings has not been undertaken,
                      as they have been certified by a RPEQ. The RPEQ bears full responsibility for all aspects
                      of the engineering design. Council reserves the right to require further amendments and/or
                      additions at a later date should design errors become apparent.
               2.     Council reserves the right to call up any performance bond held or levy charges against the
                      property, should emergency works be required to be undertaken by Council to make the site
                      safe due to inactivity on the development site for extended periods of time.
               3.     Should any changes or modifications to the approved plans be required as a result of
                      construction constraints, a “Request to change an existing approval” under the Planning Act
                      2016 must be made. Amended plans clearly indicating the changes must be lodged with this
                      application along with the appropriate fees.
               4.     Development obligations refers to all conditions of approval relative to the development
                      permit. This includes, but is not limited to, Civil Works, Park improvements, landscaping,
                      provision of “As Constructed” information, test certificates, revegetation, sediment and
                      erosion control.



                                                                                                  Page 14 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 15

                      Prestart and Inspections Request
               5.     Contact Council on 5329 6245 to arrange a prestart or an inspection giving a minimum of 5
                      business days’ notice of preferred inspection time.
               6.     If Council officers are required to undertake additional inspections of the same works, a
                      reinspection fee will be applicable in accordance with Council’s Fees and Charges register
                      applicable at the time.
                      Environmental Advisory Notes
               7.     The Environmental Protection Act 1994 states that a person must not carry out any activity
                      that causes, or is likely to cause, environmental harm unless the person takes all reasonable
                      and practicable measures to prevent or minimise the harm. Environmental harm includes
                      environmental nuisance. In this regard persons and entities, involved in the civil, earthworks,
                      construction and landscaping phases of this development are to adhere to their ‘general
                      environmental duty’ to minimise the risk of causing environmental harm.
                      Erosion and Sediment Control
               8.     Accepted best practice standards include:
                      a.      the Sunshine Coast Regional Council Manual for Erosion and Sediment Control V1.2
                              or other superseding document subsequently adopted by Council;
                      b.      Best Practice Erosion and Sediment Control, International Erosion Control Association
                              (2008).
               9.     As a general rule, a site is determined to have achieved effective short-term stabilisation if
                      at the time of the plan sealing inspection:
                      a.      Methods of stabilisation are:
                              •        appropriate for slopes and slope lengths; and
                              •        are consistent with best practice environmental management practices such as
                                       in the Manual for Erosion and Sediment Control or the IECA Manual; and
                      b.      Stormwater runoff from the site is not currently, and is not likely to result in visible
                              evidence of sedimentation or erosion, or lead to water contamination.
                              If at the time of request for plan sealing, the method of short-term stabilisation has not
                              achieved a level of stability that Council's Officers believe will have a high probability
                              of achieving long term stability (i.e. until house construction has occurred on all lots),
                              Council Officers may take the following matters into consideration in determining
                              whether the site is capable of achieving medium to long-term stability:
                              •        evidence that the site has been effectively stabilised in the short term;
                              •        evidence that soil has been adequately ameliorated;
                              •        evidence that seed of annual and perennial grass species has been applied at
                                       an adequate rate; and
                              •        that grass seed has germinated at a density that is likely to achieve an effective
                                       grass cover.
                      Landscaping
               10.    Qualified Person, for the purpose of:
                      a.      Supervising landscape works and preparing a landscape certification, is considered to
                              be a landscape architect, landscape designer or horticulturist with a minimum of three
                              years current experience in the field of landscape design.
                      b.      Undertaking Fauna site works and calculating compensatory habitat is considered to
                              be a Fauna Spotter Catcher with current certification under the Queensland Parks and
                              Wildlife Service.



                                                                                                           Page 15 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 16

                      c.      Supervising and for certifying compliance with the bushfire requirements of this
                              Decision Notice, is considered to be an ecologist with a minimum of 3 years current
                              experience in the field of bushfire assessment and management.
                      d.      Supervising and for certifying compliance with the Environmental Management Plan
                              requirements of this Decision Notice, is considered to be an ecologist with a minimum
                              of 3 years current experience in the field of environmental management on construction
                              sites.
                      Removal of Existing Trees and Vegetation
               11.    Stockpiling mulch to the appropriate volume and separation is required for fire mitigation as
                      well as optimum weed seed sterilisation.
                      Works
               12.    The applicant must pay the re-inspection fee in accordance with Council's Fees and Charges
                      Register where:
                      a.      An inspection revealed that any constructed landscape works/bushfire
                              measures/environmental management actions/fauna works do not comply with the
                              conditions of the Decision Notice, Approved Plans and or Approved Documents
                      b.      Certification is submitted to Council falsely stating that works comply with the approved
                              plans, documents and or conditions of the Decision Notice.
               Infrastructure Charges
               13.    All developments and/or changes to existing developments may require payment of
                      “Infrastructure Charges” (as applicable) in accordance with Council’s “Charges Resolution”
                      made pursuant to the planning legislation and regulations current at the time of issue. For
                      further information, please refer to https://www.noosa.qld.gov.au/planning-
                      development/development-tools-guidelines/infrastructure-charges
               8.     PROPERTY NOTES

               The following property notes will be placed against the subject property in Council’s property record
               system:
               “This site is provided with stormwater quality treatment devices which capture and store pollutants
               from stormwater runoff generated on the site. These devices are required to be routinely checked
               and serviced/cleaned out as per Maintaining Vegetated Stormwater Assets, Version 1 (Water by
               Design, 2009). Records of maintenance activities undertaken are to be kept and made available
               to council officers upon request.”
               9.     VARIATION APPROVAL DETAILS

               Not applicable.
               10.    FURTHER DEVELOPMENT PERMITS REQUIRED

               Not applicable.
               11.    SUBMISSIONS

               Not applicable.
               12.    RIGHTS OF APPEAL

               You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
               Planning Act 2016 is attached.
               13.    OTHER DETAILS

               If you wish to obtain more information about the decision, electronic copies are available on line at
               www.noosa.qld.gov.au or at Council Offices.



                                                                                                        Page 16 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 17

               Yours faithfully,




               Will Lowe
               Senior Environment Officer
               Development Assessment



               Enc:     Appeal Rights
                        Approved Plans/Documents
               cc.      Unitywater




               DECISION NOTICE HISTORY
               •     Original Decision Notice – 13 October 2020.

               •     Decision Notice - Minor – OPW19/0266.02- 26 October 2022, with an amendment to conditions 1 and 38.

               •     Decision Notice - Minor – OPW19/0266.03- 27 October 2023, with an amendment to conditions 1.




                                                                                                                           Page 17 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Page 18

                                                                              Appeal Rights
                                                                              PLANNING ACT 2016 & PLANNING REGULATION 2017




               Chapter 6 Dispute resolution                                                   (3) The appellant or, for an appeal to a tribunal, the registrar must,
                                                                                                  within the service period, give a copy of the notice of appeal to –
               Part 1 Appeal rights
                                                                                                  (a) the respondent for the appeal; and
               229 Appeals to tribunal or P&E Court
                                                                                                  (b) each co-respondent for the appeal; and
               (1) Schedule 1 of the Planning Act 2016 states –
                                                                                                  (c) for an appeal about a development application under schedule
                   (a) Matters that may be appealed to –
                                                                                                      1, table 1, item 1 – each principal submitter for the
                         (i)   either a tribunal or the P&E Court; or                                 development application; and
                         (ii) only a tribunal; or                                                 (d) for and appeal about a change application under schedule 1,
                                                                                                      table 1, item 2 – each principal submitter for the change
                         (iii) only the P&E Court; and
                                                                                                      application; and
                   (b) The person-
                                                                                                  (e) each person who may elect to become a co-respondent for the
                         (i)   who may appeal a matter (the appellant); and                           appeal, other than an eligible submitter who is not a principal
                                                                                                      submitter in an appeal under paragraph (c) or (d); and
                         (ii) who is a respondent in an appeal of the matter; and
                                                                                                  (f)   for an appeal to the P&E Court – the chief executive; and
                         (iii) who is a co-respondent in an appeal of the matter; and
                                                                                                  (g) for an appeal to a tribunal under another Act – any other
                         (iv) who may elect to be a co-respondent in an appeal of the
                                                                                                      person who the registrar considers appropriate.
                              matter.
                                                                                              (4) The service period is –
               (2) An appellant may start an appeal within the appeal period.
                                                                                                  (a) if a submitter or advice agency started the appeal in the P&E
               (3) The appeal period is –
                                                                                                      Court – 2 business days after the appeal has started; or
                   (a) for an appeal by a building advisory agency – 10 business
                                                                                                  (b) otherwise – 10 business days after the appeal is started.
                       days after a decision notice for the decision is given to the
                       agency; or                                                             (5) A notice of appeal given to a person who may elect to be a co-
                                                                                                  respondent must state the effect of subsection (6).
                   (b) for an appeal against a deemed refusal – at any time after the
                       deemed refusal happens; or                                             (6) A person elects to be a co-respondent by filing a notice of election,
                                                                                                  in the approved form, within 10 business days after the notice of
                   (c) for an appeal against a decision of the Minister, under chapter
                                                                                                  appeal is given to the person.
                       7, part 4, to register premises or to renew the registration of
                       premises – 20 business days after a notice us published under          231 Other appeals
                       section 269(3)(a) or (4); or
                                                                                              (1) Subject to this chapter, schedule 1 and the P&E Court Act, unless
                   (d) for an appeal against an infrastructure charges notice – 20                the Supreme Court decides a decision or other matter under this
                       business days after the infrastructure charges notice is given             Act is affected by jurisdictional error, the decision or matter is non-
                       to the person; or                                                          appealable.
                   (e) for an appeal about a deemed approval of a development                 (2) The Judicial Review Act 1991, part 5 applies to the decision or
                       application for which a decision notice has not been given –               matter to the extent it is affected by jurisdictional error.
                       30 business days after the applicant gives the deemed
                                                                                              (3) A person who, but for subsection (1) could have made an
                       approval notice to the assessment manager; or
                                                                                                  application under the Judicial Review Act 1991 in relation to the
                   (f)   for any other appeal – 20 business days after a notice of the            decision or matter, may apply under part 4 of that Act for a
                         decision for the matter, including an enforcement notice, is             statement of reasons in relation to the decision or matter.
                         given to the person.
                                                                                              (4) In this section –
               Note –                                                                             decision includes-
                   See the P&E Court Act for the court’s power to extend the appeal
                                                                                                  (a) conduct engaged in for the purpose of making a decision; and
                   period.
                                                                                                  (b) other conduct that relates to the making of a decision; and
               (4) Each respondent and co-respondent for an appeal may be heard
                   in the appeal.                                                                 (c) the making of a decision or failure to make a decision; and
               (5) If an appeal is only about a referral agency’s response, the                   (d) a purported decision; and
                   assessment manager may apply to the tribunal or P&E Court to
                                                                                                  (e) a deemed refusal.
                   withdraw from the appeal.
                                                                                                  non-appealable, for a decision or matter, means the decision or
               (6) To remove any doubt. It is declared that an appeal against an
                                                                                                  matter-
                   infrastructure charges notice must not be about-
                                                                                                  (a) is final and conclusive; and
                   (a) the adopted charge itself; or
                                                                                                  (b) may not be challenged, appealed against, reviewed, quashed,
                   (b) for a decision about an offset or refund-
                                                                                                      set aside or called into question in any other way under the
                         (i)   the establishment cost of trunk infrastructure identified in           Judicial Review Act 1991 or otherwise, whether by the
                               a LGIP; or                                                             Supreme Court, another court, a tribunal or another entity; and
                         (ii) the cost of infrastructure decided using the method                 (c) is not subject to any declaratory, injunctive or other order of
                              included in the local government’s charges resolution.                  the Supreme Court, another court, a tribunal or another entity
                                                                                                      on any ground.
               230 Notice of appeal
                                                                                              232 Rules of the P&E Court
               (1) An appellant starts an appeal by lodging, with the registrar of the
                   tribunal or P&E Court, a notice of appeal that-                            (1) A person who is appealing to the P&E Court must comply with the
                                                                                                  rules of the court that apply to the appeal.
                   (a) is in the approved form; and
                   (b) succinctly states the grounds of the appeal.                           (2) However, the P&E Court may hear and decide an appeal even if
                                                                                                  the person has not complied with the rules of the P&E Court
               (2) The notice of appeal must be accompanied by the required fee.




                                                                                                                                                 Page 18 of 18
Document Set ID: 22642068
Version: 2, Version Date: 31/10/2023

Used in these records

About this file

File size
245 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Minor Change Existing Approval OPW19 0266 03.pdf · 245 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.