Skip to the record
Noosa’s premier civic archive.

Council archive · source document

2ND RFI - Attachment 4A - Stormwater Management Plan (2) · MCU22/0118

of 82

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (35.2 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA        Page 1
Full text of the other 81 pages

Page 2

                                                                   RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                            ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                             July 2023

 Document Verification

 Job Title           RACV Noosa Resort – Proposed Eco Resort Extension

 Job Number          22366

 Document Title      Site Based Stormwater Management Plan

 Document Control

                                                                    Revision
      Date                         Document                                           Author          Reviewer
                                                                      No.

    04.06.2019       Site Based Stormwater Management Plan             00            B Plunkett       M Van Itallie

    11.09.2019       Site Based Stormwater Management Plan             01              J Hewitt       M Van Itallie

    15.06.2022       Site Based Stormwater Management Plan             02             T Mathew        M Van Itallie

    04.07.2022       Site Based Stormwater Management Plan             03             T Mathew        M Van Itallie

                                                                                     T Mathew /
    14.12.2022       Site Based Stormwater Management Plan             04                             M Van Itallie
                                                                                      A Mallard

    13.07.2023       Site Based Stormwater Management Plan             05             T Mathew         R Stanford

    17.07.2023       Site Based Stormwater Management Plan             06             T Mathew         R Stanford

    21.07.2023       Site Based Stormwater Management Plan             07             T Mathew         R Stanford


 Approval for Issue

                     Name                                         Signature                              Date


                 Theres Mathew
                                                                                                      21.07.2023




                 Rawdon Stanford                                                                      21.07.2023




 © Document copyright of ADG Engineers (Aust) Pty Ltd

 This document is and shall remain in the property of ADG. The document may only be used for the purpose
 for which it was commissioned and in accordance with the Terms of Engagement for the commission.
 Unauthorised use of this document in any form whatsoever is prohibited.

 To the extent permitted by law, ADG expressly disclaims and excludes liability for any loss, damage, cost or
 expenses suffered by any third party relating to or resulting from the use of, or reliance on, any information
 contained in this report. ADG does not admit that any action, liability or claim exist or be available to any third
 party.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA               Page 2

Page 3

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023


 Contents
 EXECUTIVE SUMMARY                                                                                            5
 1     INTRODUCTION                                                                                           7
       1.1   Background                                                                                       7
       1.2   Background Information                                                                           7
       1.3   Property Detail                                                                                  7
 2     EXISTING SITE                                                                                          8
       2.1   Existing Site Features                                                                           8
 3     FLOODING                                                                                               9
       3.1   Flooding Considerations                                                                          9
 4     STORMWATER INFRASTRUCTURE                                                                             11
       4.1   Existing Infrastructure                                                                         11
       4.2   Lawful Point of Discharge (LPD)                                                                 11
             4.2.1     Existing LPD                                                                          11
             4.2.2     Proposed LPD                                                                          11
       4.3   External Catchment                                                                              11
 5     STORMWATER QUANTITY ASSESSMENT                                                                        12
       5.1   Proposed Development and Associated Issues                                                      12
 6     STORMWATER QUALITY ASSESSMENT                                                                         12
       6.1   Treatment Objectives                                                                            12
       6.2   Site Analysis and Design Strategy                                                               13
             6.2.1     Pre-Development Phase                                                                 13
             6.2.2     Bulk Earthworks Phase                                                                 14
             6.2.3     Construction Phase                                                                    14
             6.2.4     Maintenance                                                                           15
       6.3   Operational Phase Treatment                                                                     15
             6.3.1     Bio infiltration basin                                                                15
       6.4   Rainwater Harvesting – Reuse Minimum Sizing of Rainwater Tank                                   15
             6.4.1     Internal Demand                                                                       15
       6.5   MUSIC Model                                                                                     16
       6.6   On-site Treatment Lifecycle Costs                                                               18
       6.7   Water Quality Monitoring                                                                        19
       6.8   Maintenance                                                                                     19
 7     CONCLUSION                                                                                            20


 Figures
 Figure 1 - Site Location (as accessed from Noosa Interactive Maps 20.04.22)                                  8

BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA        Page 3

Page 4

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023

 Figure 2 - Site Layout (as accessed from Nearmaps 20.04.2022)                                                9

 Figure 3 – Development Flooding Data (1% AEP Flood Extent 2017)                                             10

 Figure 4 – Treatment Train for Pre-Development                                                              16

 Figure 5 - Results for the Pre-Development Model                                                            17

 Figure 6 - Treatment Train for Proposed Development                                                         17




 Tables
 Table 1 - Property Detail                                                                                    7
 Table 2 - South East Queensland (SEQ) Targets                                                               13



 Appendices
 Appendix A Site Survey
 Appendix B Architectural Drawings
 Appendix C ADG Preliminary Plans
 Appendix D Concept Rehabilitation Plan
 Appendix E Noosa Shire Council Code Responses
 Appendix F Noosa Shire Council Erosion Hazard Assessment
 Appendix G Noosa Shire Council (Interactive Mapping)
 Appendix H MUSIC Modelling Information
 Appendix I Geotechnical Report




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA        Page 4

Page 5

                                                                    RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                            ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                             July 2023


          EXECUTIVE SUMMARY
          ADG Engineers (Aust.) Pty Ltd has been engaged by Aspect Architects to prepare a Site Based
          Stormwater Management Plan (SBSMP) suitable for submission to Noosa Shire Council (NSC) as
          additional information in support of a Development Application for a Material Change of Use for a
          proposed Eco Resort Extension to the current RACV Noosa Resort located at 94-142 Noosa Drive,
          Noosa Heads QLD 4567.

          The proposed development as shown in Aspect Architects plans issued on 30.06.2023 is for eight
          (8) double storey eco resort style units, raised boardwalk footpath links and associated carparking.
          The proposed application to Council also includes works involving converting an existing pond
          internal to the RACV Noosa Resort site into a new pool. ADG make note that this existing pond does
          not form part of an existing site-based stormwater treatment train nor provides further stormwater
          detention management. The pool works is to form part of separate application submitted to Council
          for building approval.

          The report comprises of stormwater quantity and quality assessments. The quantity assessment is
          undertaken to confirm a ‘non-worsening’ of peak flow discharges from the site and the quality
          assessment is undertaken to determine the required stormwater treatment measures to be
          implemented on site.

          The stormwater quantity objective was to demonstrate that there are no impacts from storm events
          up to and including the 1% AEP storm event. The purpose is to ensure that the existing infrastructure
          and/or downstream properties are not adversely affected. Due to negligible increase in peak flows
          from the subject site and the subject site being located close to the downstream waterway hence in
          the lower portion of the regional catchment, it is considered unnecessary to include provision for
          stormwater quantity management as the proposed runoff is intended to infiltrate into the existing sub-
          surface utilising bio infiltration basin. The In-situ Constant Head Permeability Test using the Talsma-
          Hallam Test method (per AS1547) undertaken by Tectonics Geotechnical & Environmental
          Engineers has confirmed the hydraulic conductivity of the soil is capable to infiltrate the retained
          water with an exfiltration rate of 115 mm/hr.

          Currently no stormwater quality management measures are in place for the Eco Village subject site.
          Stormwater treatment measures are proposed to be implemented on site in accordance with Industry
          Best Practice, WSUD Engineering Guidelines and, Council’s Land Development Guidelines to
          provide stormwater treatment for this site. ADG recommends the use of the following devices to meet
          the water quality objectives identified within the SPP 2017 and Council’s WSUD Planning Scheme
          Policies:

             Combined 40kL Rainwater Tank (Reuse) and downpipes to convey the overflow to the bio
             infiltration basin area.

             60m2 bio infiltration basin that will permit flows to infiltrate into the subject sites sub-surface.

          The eMUSIC model compares the pre and post-development stormwater pollutant residual loads in
          Section 6.6 of this report. ADG advise the post-development pollutant residual loads are now below
          the pre-development stormwater pollutant residual loads and that water is intended to infiltrate into
          the sub-surface strata of the subject site through the drainage layer of the proposed bio infiltration
          basin. This results in no increase in gross pollutants, total suspended solids, total phosphorus, nor
          total nitrogen compared to the pre-development scenario.

          To address the Noosa Shire Council’s RFI dated 6th April 2023, the following has been added to this
          SBSMP:

            The originally proposed 30m2 bio infiltration basin area is upsized into 60m2 surface and filter
            area. Refer to Appendix C of this report for updated plans with bio basin details.

BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA               Page 5

Page 6

                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                        ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023

            An In-situ Constant Head Permeability Test using the Talsma-Hallam Test method (per AS1547)
            was undertaken by Tectonics Geotechnical & Environmental Engineers and confirmed that the
            site has 0.6m sand clay topped over silty sand which is up to 1.7m deep. Saturated soil
            permeability (Ksat) was assessed from the results and confirmed the rapid infiltration at the test
            location with an ex-filtration rate at 115mm/hr. There are no ground water investigated at the
            boreholes during the tests.

            The in-situ saturated hydraulic conductivity results have been updated in the MUSIC model to
            reflect the In-Situ Constant Head Permeability Test results. Refer Appendix H of this report for
            updated MUSIC model details.

            The overflow from rainwater tanks are proposed to be conveyed using down pipes and discharge
            into bio basin area through localised 200mm deep vegetated swales, where the natural
            topography falls away from the discharge point. The runoff from raised timber walkway will fall
            directly to the natural surface below, which as demonstrated has adequate exfiltration properties.
            In the post-developed MUSIC model, the timber walkway node is modelled using the parameters
            for existing vegetated surface as agreed by NSC Assessment Officer (Leon Rowland from
            Switchback Consulting on behalf of NSC). Further, it is not considered practical to capture water
            run-off from a raised timber walkway structure. The bio infiltration basin has been oversized to
            compensate for the water quality catchment area of the walkway structure.

            All relevant standards and guidelines are addressed in this Stormwater Management Plan
            including criteria from the Noosa Shire Council Planning Scheme Policies, Queensland Urban
            Drainage Manual (QUDM) 2016, State Planning Policy (SPP) 2017 Plumbing and Drainage Code
            AS3500.3 and Australian Rainfall and Runoff Guideline (ARR).




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA          Page 6

Page 7

                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                       ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023


 1       INTRODUCTION
 1.1      Background
          ADG Engineers (Aust.) Pty Ltd was engaged by Aspect Architects to carry out a Site Based
          Stormwater Management Plan (SBSMP) suitable for submission to Noosa Shire Council (NSC) and
          any required referral agencies for a proposed Eco Resort Extension to the current RACV Noosa
          Resort located at 94-142 Noosa Drive, Noosa Heads QLD 4567.

          The purpose of this Stormwater Management Plan is to provide advice on the proposed development
          about stormwater drainage, stormwater quality and quantity measures, and flooding. The required
          infrastructure will be subject to the conditions attached to the Development Approval to be provided
          by Noosa Shire Council and any nominated referral agencies.

 1.2      Background Information
          This report was compiled using information from the following sources:

            ‘Dial Before You Dig’ (DBYD) As-Constructed information;

            NSC interactive mapping (Refer to Appendix G);

            NSC flood and storm tide inundation mapping (Refer to Appendix G);

            Detailed survey plan prepared by Skyline Surveyors (Refer to Appendix A);

            Architectural drawings by Aspect Architects issued on 30.06.2023 (Refer to Appendix B);

            Geotechnical Tests Results commences & completed on 12.04.2023 by Tectonic and

            Google Maps Aerial Imagery.

 1.3      Property Detail
          The details of the property for the proposed development can be seen in Table 1 below.

                                   Table 1- Property Detail




           Title                     Lot 203 on SP267424, Lot 0 on SP203415 and Lot 3 on SP126203


           Street Address            94 - 142 Noosa Drive, Noosa Heads QLD 4567


           Total Site Area           63,839 m2


           Developable Site Area     6167.7 m2 (Lot 3 on SP126203)


          The location of the proposed development is demonstrated in Figure 1.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA          Page 7

Page 8

                                                                 RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                        ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                          July 2023




     N


                                    Subject Site




              Development Site Area




                  Figure 1 - Site Location (as accessed from Noosa Interactive Maps 20.04.22)




 2       EXISTING SITE
 2.1     Existing Site Features
         The subject site is currently occupied by the RACV Noosa Resort.

            The site is bound by:

              Noosa Drive to the east

              Sanctuary Drive (internal road within RACV Noosa Resort) east of the development site area

              Weyba Creek Bushland Reserve North, west of the development

              Existing college buildings and ancillary structures internal to the site boundary to the east
               and south; and

              Existing college sporting ovals and Cooroy Creek internally to the west and south-west.

         The site generally slopes from the east to the west at a grade of approximately 6%. The existing site
         features can be seen in Figure 2.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA           Page 8

Page 9

                                                                   RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                          ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                            July 2023




     Location of existing
      pond converted to
          new pool.
      Submitted as part
     of separate building
           approval
                                                                                        Subject Site
         application to
           Council




                                                                        Development
                                                                         Site Area




                            Figure 2 - Site Layout (as accessed from Nearmaps 20.04.2022)

         The existing contours, surface levels and the location of the existing buildings are identified on the
         survey plan drawing as attached in Appendix A of this report.




 3       FLOODING
 3.1     Flooding Considerations
         Review of Councils interactive flood hazard overlay mapping has identified the subject site is located
         within an area subject to flooding as can be seen in Figure 3. Any habitable buildings are to ensure
         they are suspended above the existing surface with allowance for freeboard flood immunity reflective
         of the nominated Council defined flood level.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA             Page 9

Page 10

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                                                                  Developable
                                                                   Site Area




                      Figure 3 – Development Flooding Data (1% AEP Flood Extent 2017)


         Furthermore, review of Noosa Shire Council’s 2019 Draft Planning Scheme Policy Coastal Hazards
         mapping indicates the subject site is located within an area subject to Sea Level Rise HAT
         inundation and Stormtide inundation 1% AEP events. Refer to Appendix G for Council flood
         mapping plots regarding extents of the above-mentioned inundation events.


         In response to Council’s information request, ADG note the proposed cabin lodge’s will be
         suspended structures along with the walkways and carpark. The minimum habitable floor level for
         the suspended cabins is RL3.4m AHD. Appendix G which illustrates the council flood mapping,
         plots this defined flood event (DFE) extents at approx. RL2.4m AHD. Give the finished floor level
         (FFL) is at minimum RL3.4m AHD, there is a minimum of 1.0m between the assumed DFE and FFL.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA       Page 10

Page 11

                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                       ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023


 4       STORMWATER INFRASTRUCTURE
 4.1     Existing Infrastructure
         A Noosa Shire Council DBYD search and detailed survey identified the following stormwater
         infrastructure within the vicinity of the subject site:

            Existing 1050mm stormwater pipe and associated gully pit traversing the southern portion of 94
            Noosa Drive (Lot 203 on SP267424) and the existing Sanctuary Drive Road via kerb and channel
            adapters to the north-east of the proposed extension;

            Existing Council stormwater infrastructure consisting of 375-525mm stormwater pipes and gully
            pits external to 142 Noosa Drive (Lot 3 on SP126203) within the south-eastern roundabout.

         Refer to Appendix A for the detailed survey for further information regarding the existing stormwater
         infrastructure.

         Note: A diversion swale exists within existing RACV Noosa Resort along the development sites
         northern boundary internal to the resort development property. ADG refer reader to previous site
         reporting documents for details.

 4.2     Lawful Point of Discharge (LPD)
 4.2.1   Existing LPD

          Based on information gathered via survey and contour data, aerial imagery and site investigation it
          has been determined that the development site discharges stormwater flows via overland flow
          towards Weyba Creek.

 4.2.2   Proposed LPD

          It is proposed to maintain the existing ultimate lawful point of discharge being Weyba Creek to the
          west. Any increased runoff because of the proposed development is anticipated to be infiltrated
          onsite.

          Refer to Appendix C for the Preliminary Layout Plans prepared by this office.

 4.3      External Catchment
          No significant upstream catchment directly acts on the developable site area, other than the carpark
          extents beyond the boundary line. The area within Sanctuary Drive discharges to the existing council
          infrastructure within the road via kerb and channel adapters, this it to remain unchanged.

          Refer to Appendix A for the detailed survey for further information regarding the existing site
          features.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA         Page 11

Page 12

                                                                   RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                           ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                            July 2023


 5       STORMWATER QUANTITY ASSESSMENT
          The aim of the stormwater quantity assessment is to ensure that the development shall impose no
          adverse effects on downstream properties or receiving water bodies and that the conveyance of
          flows will be in a safe manner with minimal risk of human endangerment as well as the following
          objectives:

            Address the need for stormwater quantity control measures.

            Ensure there is no actional impacts from the subject site for events up to and including the 1% AEP
            event.

            Ensure proposed quantity control measures detain and convey flows in accordance with QUDM
            (2017) minimum freeboard recommendations.

 5.1     Proposed Development and Associated Issues
          In this development, the developable site area leads to negligible increase in peak flows downstream
          of the subject site and is located close to the downstream waterway being Weyba Creek, hence in
          the lower portion of the regional catchment. It is anticipated that the bio infiltration basin drainage
          system will allow for infiltration on-site of the additional flows which will permeate into the sub-surface
          strata, hence it is considered unnecessary to include provision for stormwater quantity management.


 6        STORMWATER QUALITY ASSESSMENT
 6.1      Treatment Objectives
          This assessment identifies issues relating to stormwater quality runoff and assesses possible
          methods of treatment if required. The aim of this section of the report is to determine practical
          approaches for achieving improvements in the quality of the stormwater run-off from the site that can
          be readily implemented.

          The SPP 2017 proposes criteria which apply to ‘high-risk’ development for stormwater. The criteria
          include one or more of the following:

             A Material Change of Use (MCU) for an urban purpose which involves greater than 2,500m2 of
             land that:

             will result in an impervious area greater than 25% of the net developable area; or

             will result in six (6) or more dwellings

             A Reconfiguration of a Lot (ROL) for urban purposes that involves a land area greater than
             2,500m2 and will result in six (6) or more lots; or

             Operational works for urban purposes that involve disturbing more than 2,500m2 of land.

          The proposal includes an MCU for a land area of 2,500m 2 that will result in impervious area greater
          than 25% of the developable area. Hence, the development is classed as ‘high risk’ for water quality
          and the SPP 2017 applies.

          The SPP 2017 suggests the development aims to:

             Avoid or otherwise minimises adverse impacts on the environmental values of receiving waters,
             arising from:

BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA            Page 12

Page 13

                                                                 RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                        ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                          July 2023

             altered stormwater quality or flows, and

             wastewater (other than contaminated stormwater and sewage), and

             the creation or expansion of non-tidal artificial waterways, and

             Demonstrate compliance with the SPP code - Water quality (Appendix 3).

          Appendix 2 (Table B) of SPP 2017 suggests ‘Post Construction Phase – Stormwater Management
          Design Objectives’ as:

                                     Table 2 - South East Queensland (SEQ) Targets

            Total Suspended Solids       Total Phosphorus         Total Nitrogen           Gross Pollutants
                     (TSS)                      (TP)                   (TN)                    >5mm

                 80% Removal               60% Removal             45% Removal               90% Removal


          Along with the SPP 2017, The Noosa Plan 2020 Water Quality and Drainage Code acceptable
          outcome AO6.1 states that;

          Stormwater runoff discharging into High Ecological Value waters as a result of development causes
          no increase in gross pollutants, total suspended solids, total phosphorous or total nitrogen compared
          to a pre-development scenario.

          Since the development site slopes toward and discharges to Weyba Creek, no pollutants compared
          to pre-development can be discharged from the site.

          The objective is to provide the following:

             Nitrogen and Phosphorous removal

             Gross Pollutant and Suspended Solids Removal

             All of the site’s impervious areas discharge to suitable treatment device/s

             Treatment device selection criteria are to be in accordance with Industry Best Practice and,
             WSUD Engineering Guidelines

 6.2      Site Analysis and Design Strategy
 6.2.1    Pre-Development Phase

          An Erosion Hazard Assessment has been carried out for the proposed development – refer to
          Appendix F for a copy of the completed Noosa Shire Council form. As a result of this assessment,
          it was determined that the overall site is a ‘low’ risk.

          Prior to construction commencing, the following erosion and sediment control measures will need to
          be installed around the subject site to minimise disturbance and ensure the quality of runoff
          discharging from the site is of an acceptable standard:

             Sediment barriers to be installed on all entrances to downstream stormwater infrastructure (i.e.
             gully pits);

             Designation of transport routes through the site to minimise vegetation disturbance;



BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA          Page 13

Page 14

                                                                  RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                         ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                           July 2023

             Maximise retention of existing vegetation to reduce soil disturbance and provide filter strip
             treatment for runoff;

             Install construction entry and exit shakedown areas;

             Sediment fences are to be installed on the downstream boundaries of the subject site; and

             Install dust control measures as required.

          All erosion and sediment control measures are to be designed and installed in accordance with IECA
          Guidelines. Further details regarding the proposed erosion and sediment control measures will be
          provided during the detailed design phase of the development.

          Further to the above considerations, it is the developments intent to limit ground disturbing activities
          to a minimum. Other than a portion of the carparking area, all structures and footpaths are proposed
          to be suspended over the existing surface.

 6.2.2    Bulk Earthworks Phase

          During the bulk earthworks phase, the following erosion and sediment control measures will need to
          be installed in addition to the aforementioned measures (Pre-Development Phase) to ensure there
          is minimal disturbance to downstream receiving water bodies:

             Construction chutes to control runoff over earthworks batters;

             Construction of temporary bunds at the top of all earthworks batters to ensure runoff is directed
             away from exposed batters;

             Sediment basins to be constructed at low points within each stage of the proposed development;

             Sediment fences to be installed on the downstream side of any stockpiles; and

             Stabilisation of all batters upon reaching the finished earthworks levels.

          All erosion and sediment control measures are to be designed and installed in accordance with IECA
          Guidelines. Further details regarding the proposed erosion and sediment control measures will be
          provided during the detailed design phase of the development.

 6.2.3    Construction Phase

          During the construction phase of the development, there is a risk of sedimentation transport due to
          disturbed land. The following erosion and sediment control measure will need to be installed in
          addition to the aforementioned measures (Pre-Development and Bulk Earthworks Phases) to ensure
          there is minimal disturbance and the quality of runoff is maintained to an acceptable standard:

             Construction of temporary diversion drains to divert water to sediment basins;
             Construction of temporary diversion drains to divert water to protect bio infiltration and treatment
             devices as required;
             Sediment barriers to be installed on all entrances to newly constructed stormwater infrastructure
             (i.e. gully pits);
             Sediment fences to be installed on the downstream side of any stockpiles and batters; and
             Re-vegetation of all disturbed areas within two (2) weeks of completion.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA           Page 14

Page 15

                                                                 RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                        ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                          July 2023

          All erosion and sediment control measures are to be designed and installed in accordance with IECA
          Guidelines. Further details regarding the proposed erosion and sediment control measures will be
          provided during the detailed design phase of the development.

 6.2.4    Maintenance

          All erosion and sediment control devices are to be maintained through the entire phase of the
          development leading up to the operational phase. Erosion and sediment control devices will need to
          be monitored closely throughout the entire project to ensure they are operating correctly and
          efficiently. No erosion and sediment control devices are to be removed unless otherwise authorized
          by a suitably qualified engineer or the site superintendent.

 6.3      Operational Phase Treatment
          Once directed to be commissioned by the superintendent and engineers, the Stormwater Quality
          Improvement Devices (SQIDs) will provide the required level of stormwater quality treatment to runoff
          from the site. It is expected that sediment laden runoff and the erosion potential at the subject site
          during the operational phase will be minimal. This is due to impervious developed areas in the form
          of roofs, driveways and carparking. It is understood that the footprint of these impervious areas has
          been reduced as much as practicable. The proposed landscaped areas will be maintained in a
          manner that will minimise erosion.

          Existing grassed and proposed landscaped areas will be maintained in a manner that will minimise
          erosion, some of which would be subject to erosion of topsoil from garden beds, erosion of soil from
          behind retaining walls, etc.

 6.3.1    Bio infiltration basin

             A minimum 60m2 surface area bio infiltration basin is proposed.

          The bio infiltration basin will remove contaminants and sedimentation from stormwater runoff via
          infiltration through layers of soil media. The basin is made of a 400mm filter media layer, a 100mm
          transition layer and a minimum 200mm drainage layer located above the silty sand sub-strata. The
          basin is to be vegetated, as per the Concept Rehabilitation Plan’s recommendations as attached to
          Appendix D or with suitable plants listed in Table 19 of the bio infiltration Technical Design
          Guidelines (Water by Design, 2014). These plants provide additional treatment and will prevent
          clogging of the basin. Runoff within the bio infiltration area gradually infiltrates the soil layers,
          assuming the in-situ soil of the area is sand. This assumption is based on the The In-situ Constant
          Head Permeability Test using the Talsma-Hallam Test method (per AS1547) undertaken by
          Tectonics Geotechnical & Environmental Engineers has confirmed the hydraulic conductivity of the
          soil is capable to infiltrate the retained water with an exfiltration rate of 115 mm/hr.

 6.4      Rainwater Harvesting – Reuse Minimum Sizing of Rainwater Tank
          To satisfy Council’s code performance outcomes by reducing the need for mains water, the roof area
          is to be connected to a rainwater tank with a minimum capacity of 5,000L in accordance with
          Department of Housing and Public Works MP4.2 – Rainwater Tanks and Other Supplementary Water
          Supply Systems. For the eight proposed cabins this equates to a total rainwater tank volume of 40
          kL. Each rainwater tank is to be plumbed to be available for outdoor cleaning, washing machines
          and toilet flushing in accordance with Council’s WSUD Planning Scheme Policies. Any overflow from
          the rain water will be directed to down pipes and suspended pipes clamped on the raised timber
          walkway leading into the bio-basin area.

 6.4.1    Internal Demand

          To calculate expected internal demand, the following assumptions were made:


BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA          Page 15

Page 16

                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                       ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023

             Toilet requires 25 L/day (per person) in accordance with Table 4.4 of the MUSIC Modelling
             Guidelines 2010;

             Laundry requires 21 L/day (per person) in accordance with Table 4.4 of the MUSIC Modelling
             Guidelines 2010;

             Peak occupancy of two (2) people per dwelling for the proposed 16x 2-bedroom units for the
             holiday accommodation in accordance with Table 4.3 of the MUSIC Modelling Guidelines 2010.

          Based on these assumptions the required volume for the internal demand component of the
          rainwater tank is calculated as;

              25 L/day (per person) + 21 L/day (per person) x 2 people per dwelling (peak) = 92 L/day

              Daily demand (representing indoor use) = 92 L/d * 16 units = 1,472 L / day = 1.472 kL / day

 6.5      MUSIC Model
          The sites stormwater run-off for both the pre and post development were modelled using MUSIC
          (version 6.3.0) and the water quality objectives for South East Queensland specified in the SPP 2017
          of 80% TSS reduction, 60% TP reduction, 45% TN reduction, and 90% Gross Pollutants reduction.
          Since the site slopes towards Weyba Creek which is a High Ecological Value waters, the post-
          development pollutant discharge cannot be more than that of the pre-development discharge
          according to The Noosa Plan 2020 Water Quality and Drainage Code.




                               Figure 4 – Treatment Train for Pre-Development

 The pre-developed site situation is modelled in MUSIC and the arrangement is as given in Figure 4. The
 Suspended Walkway node in the post development model has used the ewater parameters for the existing
 vegetated surface as agreed by Noosa Council (Leon Rowland from Switchback Consulting on behalf of NSC).




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA         Page 16

Page 17

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                      ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                              Figure 5 - Results for the Pre-Development Model




                                Figure 6 - Treatment Train for Proposed Development

 The treatment train effectiveness and residual loading of the post-development MUSIC model is presented in
 Figure 7.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA       Page 17

Page 18

                                                                  RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                         ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                           July 2023




                    Figure 7 - Results for Post-Development Model at Receiving Node


         As shown above in Figure 7, a significant pollutant reduction is shown at the receiving node.

         Based on the results from the In Situ Constant Head Permeability Test using the Talsma-Hallam Test
         method (per AS1547) undertaken by Tectonics Geotechnical & Environmental Engineers, the site has
         sand and sandy soil texture up to a minimum depth of 1.7m. Saturated soil permeability (Ksat) was
         assessed from the results of in situ constant head test. The test site was pre-soaked using a minimum
         15L of water prior to testing. It is noted that the pre-soak waters drained away rapidly, as would be
         expected of typically sandy media. Refer to Appendix I for the test results.

         Since the majority of the stormwater runoff from the roof will be re-used by the rainwater tanks and the
         rest of the runoff is intended to infiltrate onsite through the bio-basin, no discharge will be proposed
         from the site.

         Currently it is assumed that a silty sand sub-strata will have a hydraulic conductivity of approx. of
         3 .19 × 10−5 m/s, for a 60 m2 bio infiltration basin area, this equates to a yearly capacity of 60,356
         𝑚3 /yr which exceeds the infiltration rate of the receiving node being 2.93 ML/yr (2,930 𝑚3 /yr). It is
         therefore understood that the existing subgrade will have sufficient capacity to infiltrate all treatable
         flows with no additional stormwater infrastructure required to be implemented to the downstream
         waterway.

         Details of the MUSIC model are attached within Appendix H for further information.

         Refer to Appendix C for the Preliminary Layout Plans prepared by ADG.

 6.6      On-site Treatment Lifecycle Costs
         A lifecycle cost analysis is not a part of the scope of this report. All the recommended water quality
         treatment infrastructure lies within the development site and it shall be maintained and serviced by the
         owners of the development at no cost to Council.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA           Page 18

Page 19

                                                               RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                      ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                        July 2023


 6.7      Water Quality Monitoring
         No water quality monitoring is proposed for this development at this stage due to the nature of the
         development and the expected pollutant levels.

 6.8      Maintenance
         Maintenance of the SQIDs will be the responsibility of the owners of the development. The
         maintenance should be carried out in accordance with the manufacturer’s recommendations.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA        Page 19

Page 20

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023


 7        CONCLUSION
          In preparing this report, we have achieved all requirements for Site Based Stormwater Management
          Plans as described in the State Planning Policy (2017), Noosa Shire Council Planning Scheme
          Policies, Queensland Urban Drainage Manual (QUDM) 2016, Plumbing and Drainage Code
          AS3500.3 and Australian Rainfall and Runoff Guideline (ARR).




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA       Page 20

Page 21

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023



                                                                                         Appendix A
                                                                                         Site Survey




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 22

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 23

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 24

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 25

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 26

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 27

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 28

Skyline Surveyors
Suite 11C
Brightwater Corporate Centre   PHONE
                               07 5493 4877
69 Attenuata Drive
MOUNTAIN CREEK QLD 4557
E: [email protected]
W: www.skysurv.com.au

Page 29

Page 30

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023



                                                                              Appendix B
                                                                   Architectural Drawings




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 31

                                                                                                                                                                                                                            IMPORTANT:
                                                                                                                                                                                                                            ALL DRAWINGS MUST BE READ IN CONJUNCTION WITH
                                                                                                                                                                                                                            THE GENERAL NOTES SHEET

                                                                                                                                                                                                                                           AMENDMENT SCHEDULE

                                                                                                                                                                                                                           ISS        DATE              DESCRIPTION                  BY
                                                                                                                                                                                                                               A     20/06/22    CONSULTANTS REVIEW                     ZT
                                                                                                                                                                                                                               B     24/10/22    DA RFI                                 ZT
                                                                                                                                                                                                                               C     28/10/22    DA RFI                                 ZT
                                                                                                                                                                                                                               D     10/11/22    DA RFI                                 ZT
                                                                                                                                                                                                                               E     15/11/122   RFI                                    ZT
                                                                                                                                                                                                                               F     02/12/22    RFI                                    ZT
                                                                                                                                                                                                                               G     05/12/22    RFI                                    ZT
                                                                                                                                                                                                                               H     18/05/23    RFI RESPONSE                           TB
                                                                                                                                                                                                                               I     30/06/23    RESPONSE TO 2ND RFI                    ZT



                                                         1
                                                       A65-07




                  65 SQM BIO RETENTION
                  AREA

                                                                                                18 CARPARKS



                                                                      CABIN 1


10m WIDE BUSHFIRE ASSET                                                                                                                         EMT X
PROTECTION ZONE

                                                                                                                                                        EMT B
                                         1
                                       A65-09                                                                     RL 11.022




                                                                                                                             CABINS 14 & 15
                                                                                                   4
           2                                                                                     A65-09
         A65-09




                  RL 10.730     CABINS 2 & 3                                                    RL 11.022

                                                                                                                                              EMT A
                                                                                                           CABINS 12 & 13




                                                                                                              0
                                                                                                          60 0
                                     LOT 3




                                 0
                              400
                                                                                                  CABINS 10 & 11
                                                                                      3
                                                                                    A65-09




                                                      CABINS 4 & 5
                                          RL 11.640
                                                                                             CABINS 8 & 9




                                                                                                                                                                                                                                   TOOWOOMBA | BRISBANE | MOOLOOLABA
                                                                                                                                                                                                                                              www.aspectapm.net
                                                                                                                                                                                                                                     ABN 96 071 786 948 ACN 071 786 948
                                                                            CABINS 6 & 7                           60
                                                                                                                        00                                                                                                                       BOAQ 4487

                                                                RL 11.810


                                                                                                                                                                                                                                                                          BUILDING DESIGNERS
                                                                                                                                                                                                                                                                              ASSOCIATION


                                                                                                                                                                                                                           GENERAL NOTES
                                                                                                                                                                                                                            THIS PLAN HAS BEEN PREPARED IN ACCORDANCE WITH ALL
                                                                                                                                                                                                                            RELEVANT BUILDING CODES AND STANDARDS. NO AMENDMENTS
                                                                                                                                                                                                                            SHALL BE MADE WITHOUT THE APPROVAL FROM ASPECT AND/OR
                                                                                                                                                                                                                            RELEVANT LOCAL AUTHORITY.THESE DRAWINGS ARE SUPPLIED ON
                                                                                                                                                                                                                            THE CONDITION THAT, IN THE EVENT OF ERROR, ASPECTS' LIABILITY
                                                                                                                                                                                                                            IS LIMITED ONLY TO THE COST OF AMENDING THESE DRAWINGS.

                                                                                                                                                                                                                            CONTRACTORS ARE TO VERIFY ALL DIMENSIONS ON SITE BEFORE
                                                                                                                                                                                                                            COMMENCING ANY WORK OR PRODUCING SHOP DRAWINGS. THESE
                                                                                                                                                                                                                            DRAWINGS ARE PROTECTED BY THE LAWS OF COPYRIGHT AND MAY
                                                                                                                                                                                                                            NOT BE COPIED OR REPRODUCED WITHOUT THE WRITTEN
                                                                                                                                                                                                                            PERMISSION OF ASPECT .
                                                                                                                                                                                                                           PROJECT
                                                                                                                                                                                                                           RACV NOOSA RESORT - ECO
                                                                                                                                                                                                                           RESORT
                                                                                                                                                                                                                           FOR

                                                                                                                                                                                                                           ROYAL AUTOMOBILE CLUB OF
                                                                                                                                                                                                                           VICTORIA




                                                                                                                                                                                                          CONCEPT DESIGN
                                                                                                                                                                                                                           @

                                                                                                                                                                                                                           142 NOOSA DRIVE, NOOSA HEADS
                                                                                                                                                                                                                           QLD 4567
                                                                                                                                                                                                                           DRAWING TITLE




                                                                                                                                                                                                                           SITE PLAN
                                                                                                                                                                                                      N                    DATE                  SCALE @ A1       DRAWN         CHECKED

                                                                                                                                                                                                                           30/06/23              1 : 250                ZT              TB
                                                                                                                                                                                                                           DRAWING No.                                        ISSUE
                                                                                                                                                                1:250
                                                                                                                                                                        0   2   4   6   8   10   20                        21-0910_ A10-01                                          I

Page 32

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                                                                            Appendix C
                                                                  ADG Preliminary Plans




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 33

                                                                                                                                                                                             01
                                                                                                                                                                                              X
                                                                                                                                                                                              X
                                                                                                                                                                                             02
                                                                                                                                                                                                                        03
                                                                                                                                                                                                                                             04




               TM
                    CIVIL




       22366
                                                                                                                                                                                              X
                                                                                                                                                                                              X




SK01
                                                                                                                                                                                                                       17.05.23
                                                                                                                                                                                             15.06.22
                                                                                                                                                                                             03.06.19
                                                                                                                                                                                                                                             13.07.23




                                                                                                                                                                         T:1300 657 402
                                                                                                                                                                                                                                                                             All intellectual property rights (including, without limitation, all
                                                                                                                                                                                                                                                                             copyright and design rights) subsisting in the drawings and related
                                                                                                                                                                                                                                                                             information belongs to ADG Engineers (Aust) Pty Ltd ("ADG").




       TM
               AM
                                                                                                                                                                                                                                                                             Drawings or information are provided for general information
                                                                                                                                                                                                                                                                             purposes only and may not contain the full details required for




                                 CATCHMENT PLAN
                                                                                                                                                                                                                       ISSUED FOR APPROVAL
                                                                                                                                                                                                                                                                             construction. ADG makes no warranties, either express or implied,




                                 PRE DEVELOPMENT
                                                                                                                                                                                                                                             ISSUED FOR APPROVAL



                                                                                                                                                                                             XISSUED FOR INFORMATION
                                                                                                                                                                                             XISSUED FOR INFORMATION




                                                                                                                                                                         E: [email protected]
                                                                                                                                                                                                                                                                             of merchantability and fitness of the drawings or data for any




                                                                               ASPECT ARCHITECTS
                                                                                                                                                                                                                                                                             particular purpose.




               RS

       NTS
                                                                                                                                                                                                                                                                             ADG accepts no responsibility or liability for any loss or damage




                                                                                                                Env ironmental Management ISO 14001:2015
                                                                                                                                                                                                                                                                             caused to the recipient or any third party through use of the




                    Approval
                                                                                                                                                                                                                                                                                                                                                                                               NOT FOR CONSTRUCTION




                    PRELIINARY
                                                                                                                                                                                                                                                                             drawings or related information in any way.




                                                   94-142 NOOSA DR, NOOSA DR
                                                                                                                                                                                             X
                                                                                                                                                                                             X
                                                                                                                                                                                                                                                                                                                                                                                                                  PRELIMINARY




                                                                                                                                                                                                                         TM
                                                                                                                                                                                             TM
                                                                                                                                                                                                                                             TM




                                                                                                                                                                                             BP




                                                                                                                                                                         W: www.adgce.com
                                                                                                   Quality Assurance ISO 9001:2015 | Work Health Safety ISO 45001:2018




04
                                                                                                                                                                                             X
                                                                                                                                                                                             X
                                                                                                                                                                                                                                             RS

                                                                                                                                                                                                                       AM
                                                                                                                                                                                             MVI
                                                                                                                                                                                             MVI




                                                   RACV NOOSA ECO RESORT
                                                                                                                                                                                                                                                                                                                              A
                                                                                                                                                                                                                                                                                                                                                                                          Legend




                                                                                                                                                                                                                                                                                                                        Catchment ID
                                                                                                                                                                                                                                                                                                                                       Site Grade Direction
                                                                                                                                                                                                                                                                                                                                                              Stormwater Catchment B'dy




                                                                                                                                                                                                                                                                         A
                                                                                                                                                                                                                                                                   EX1

Page 34

                                                                                                                                                                                                                                                                                                          IMPORTANT:
                                                                                                                                                                                                                                                                                                          ALL DRAWINGS MUST BE READ IN CONJUNCTION WITH
                                                                                                                                                                                                                                                         ISSUED   FOR
                                                                                                                                                                                                                                                              THE GENERAL     APPROVAL
                                                                                                                                                                                                                                                                          NOTES SHEET

                                                                                                                                                                                                                                                              NOT FOR CONSTRUCTION
                                                                                                                                                                                                                                                                       AMENDMENT SCHEDULE

                                                                                                                                                                                                                                                                                                        ISS                                      DATE                                            DESCRIPTION                                                                                       BY
                                                                                                                                                                                                                                                                                                               A                                20/06/22                CONSULTANTS REVIEW                                                                                                         ZT
                                                                                                                                                                                                                                                                                                               B                                24/10/22                DA RFI                                                                                                                     ZT
                                                                                                                                                                                                                                                                                                               C                                28/10/22                DA RFI                                                                                                                     ZT
                                                                                                                                                                                                                                                                                                               D                                10/11/22                DA RFI                                                                                                                     ZT




                                                                                                                                                                                                                                                                         copyright and design rights) subsisting in the drawings and related




                                                                                                                                                                                                                                                                                                                                                    construction. ADG makes no warranties, either express or implied,
                                                                                                                                                                                                                                                                                                               E                                15/11/122               RFI                                                                                                                        ZT




                                                                                                                                                                                                                                                                                                                                                                                                                          ADG accepts no responsibility or liability for any loss or damage
                                                                                                                                                                                                                                                                                                               F                                02/12/22                RFI                                                                                                                        ZT




                                                                                                                                                                                                                                                                                                                                                    purposes only and may not contain the full details required for
                                                                                                                                                                                                                                                                         All intellectual property rights (including, without limitation, all

                                                                                                                                                                                                                                                                         information belongs to ADG Engineers (Aust) Pty Ltd ("ADG").
                                                                                                                                                                                                                                                                                                               G                                05/12/22                RFI                                                                                                                        ZT




                                                                                                                                                                                                                                                                                                                                                    of merchantability and fitness of the drawings or data for any
                                                                                                                                                                                                                                                                                                                                                    Drawings or information are provided for general information
                                                                                                                                                                                                                                                                                                               H                                18/05/23                RFI RESPONSE                                                                                                               TB




                                                                                                                                                                                                                                                                                                                                                                                                                          caused to the recipient or any third party through use of the
                                                                                                                                                                                                                                                                                                               I                                30/06/23                RESPONSE TO 2ND RFI                                                                                                        ZT



                                                                                           1
                                                                                         A65-07




                                                                                                                                                                                                                                                                                                                                                                                                                          drawings or related information in any way.
                                                                                                                                  18 CARPARKS



                                                                                                        CABIN 1




                                                                                                                                                                                                                                                                                                                                                    particular purpose.
                                   10m WIDE BUSHFIRE ASSET                                                                                                                        EMT X
                                   PROTECTION ZONE

                                                                                                                                                                                                EMT B

                                                                                                                                                    RL 11.022




                                                                                                                                                               CABINS 14 & 15
                                                                                                                                     4
                                              2                                                                                    A65-09
                                            A65-09




                                                     RL 10.730     CABINS 2 & 3                                                   RL 11.022
LEGEND
                                                                                                                                                                                EMT A     Ex1
                                                                                                                                             CABINS 12 & 13
         Site Grade Direction
                                                                                                                    A




                                                                                                                                                0
                                                                                                                                            60 0
         200 mm deep Stormwater
         Swale (Vegetated)                                              LOT 3

         Existing Trees
          Bio-infiltration Basin
                                                                    0
                                                                 400
                                                                                                                                    CABINS 10 & 11
                                                                                                                        3
                                                                                                                      A65-09




                                                                                        CABINS 4 & 5
                                                                                                                                                                                                                                                 06      21.07.23             Issued For Approval                                                                                                                                                                                     TM             RS
                                                                            RL 11.640
                                                                                                                               CABINS 8 & 9                                                                                                      05      13.07.23
                                                                                                                                                                                                                                                         03.05.23
                                                                                                                                                                                                                                                                              Issued For Approval                                                                                                                                                                                     TM             RS
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     AM
                                                                                                                                                                                                                                                 04                              Preliminary                                                                                                                                                                                          TM
                                                                                                                                                                                                                                                 03      14.12.22               Preliminary                                                                                                                                                                                             TM           AM
                                                                                                                                                                                                                                                 02      29.09.2                 Preliminary                                                                                                                                                                                            TM MVI
                                                                                                                                                                                                                                                         2
                                                                                                                                                                                                                                                 01      03.06.19            Issued For Approval                                                                                                                                                                                              BP      MVI




                                                                                                                                                                                                                                                                                                                           TOOWOOMBA | BRISBANE | MOOLOOLABA
                                                                                                                                                                                                                                                                                                                                      www.aspectapm.net
                                                                                                                                                                                                                                                                                                                             ABN 96 071 786 948 ACN 071 786 948
                                                                                                              CABINS 6 & 7                           60
                                                                                                                                                          00                                                                                                                                                                             BOAQ 4487

                                                                                                  RL 11.810
                                                                                                                                                                                                                                                           T:1300 657 402                                                          E: [email protected]                                                    W: www.adgce.com
                                                                                                                                                                                                                                                                                                                           BUILDING DESIGNERS
                                                                                                                                                                                                                                                         Quality Assurance ISO 9001:2015 | Work Health Safety ISO 45001:2018
                                                                                                                                                                                                                                                                                                                               ASSOCIATION
                                                                                                                                                                                                                                                                      Env ironmental Management ISO 14001:2015
                                                                                                                                                                                                                                                                                                   GENERAL NOTES
                                                                                                                                                                                                                                                                                                    THIS PLAN HAS BEEN PREPARED IN ACCORDANCE WITH ALL
                                                                                                                                                                                                                                                                                                    RELEVANT BUILDING CODES AND STANDARDS. NO AMENDMENTS
                                                                                                                                                                                                                                                                                                    SHALL BE MADE WITHOUT THE APPROVAL FROM ASPECT AND/OR
                                                                                                                                                                                                                                                                                                    RELEVANT LOCAL AUTHORITY.THESE DRAWINGS ARE SUPPLIED ON


                                                                                                                                                                                                                                                      Aspect Architects
                                                                                                                                                                                                                                                                                                    THE CONDITION THAT, IN THE EVENT OF ERROR, ASPECTS' LIABILITY
                                                                                                                                                                                                                                                                                                    IS LIMITED ONLY TO THE COST OF AMENDING THESE DRAWINGS.

                                                                                                                                                                                                                                                                                                          CONTRACTORS ARE TO VERIFY ALL DIMENSIONS ON SITE BEFORE
                                                                                                                                                                                                                                                                                                          COMMENCING ANY WORK OR PRODUCING SHOP DRAWINGS. THESE


                                                                                                                                                                                                                                                      RACV NOOSA ECO RESORT
                                                                                                                                                                                                                                                                                                          DRAWINGS ARE PROTECTED BY THE LAWS OF COPYRIGHT AND MAY
                                                                                                                                                                                                                                                                                                          NOT BE COPIED OR REPRODUCED WITHOUT THE WRITTEN
                                                                                                                                                                                                                                                                                                          PERMISSION OF ASPECT .

                                                                                                                                                                                                                                                      94-142 RACV
                                                                                                                                                                                                                                                              NOOSA
                                                                                                                                                                                                                                                                  NOOSADR,  NOOSA
                                                                                                                                                                                                                                                                        RESORT - ECO
                                                                                                                                                                                                                                                                                                   PROJECT



                                                                                                                                                                                                                                                                                                   RESORT
                                                                                                                                                                                                                                                      POST DEVELOPMENT
                                                                                                                                                                                                                                                                                                   FOR

                                                                                                                                                                                                                                                             ROYAL AUTOMOBILE CLUB OF

                                                                                                                                                                                                                                                      CATCHMENT
                                                                                                                                                                                                                                                             VICTORIA
                                                                                                                                                                                                                                                                      PLAN




                                                                                                                                                                                                                                                                CONCEPT DESIGN
                                                                                                                                                                                                                                                                                                   @


                                                                                                                                                                                                                                                      94-142 142
                                                                                                                                                                                                                                                              NOOSA      DR,
                                                                                                                                                                                                                                                                 NOOSA DRIVE,
                                                                                                                                                                                                                                                             QLD 4567
                                                                                                                                                                                                                                                                                NOOSA
                                                                                                                                                                                                                                                                              NOOSA HEADS
                                                                                                                                                                                                                                                                                                   DRAWING TITLE
                                                                                                                                                                                                                                                 CIVIL                                                                                                                                                                  PRELIMINARY



                                                                                                                                                                                                                                                 TM                                                SITEAM
                                                                                                                                                                                                                                                                                                        PLAN                                                                                                             RS
                                                                                                                                                                                                                                                 N
                                                                                                                                                                                                                                                 22366
                                                                                                                                                                                                                                                                                                   DATE
                                                                                                                                                                                                                                                                                                       TM
                                                                                                                                                                                                                                                                                                                                                                          SCALE @ A1
                                                                                                                                                                                                                                                                                                                                                                                                                         NTS
                                                                                                                                                                                                                                                                                                                                                                                                                           DRAWN                                                              CHECKED
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   (at A1)


                                                                                                                                                                                                        Catchment T
                                                                                                                                                                                                           1:250
                                                                                                                                                                                                                   0   2   4   6   8   10   20        SK02
                                                                                                                                                                                                                                                                                                   30/06/23
                                                                                                                                                                                                                                                                                                   DRAWING No.

                                                                                                                                                                                                                                                                                                     21-0910_ A10-01
                                                                                                                                                                                                                                                                                                                                                                          1 : 250                                                                         ZT
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        ISSUE

                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               06I
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    TB

Page 35

                                                                                                        PROPERTY BOUNDARY




                                                                                                                                                                                                                                                             VEGETATED SWALE 'V' DRAIN.
                                                                                                                                                                                                                                                             NOMINAL 200MM DEEP, 1:4V BATTERS.
                                                                                                                                                                                                                                                             ARBORIST TO DETERMINE EXTENT OF
                                                                                                                                                                                                                                                             ROOT REMOVAL. HAND EXCAVATION AND
                                                                                                                                                                                                                                                             VACUUM SUCKER TRUCK REMOVAL OF
                                                                                                                                                                                                                                                             SOIL AROUND ANY STRUCTURAL TREE
                                                                                                                                                                                                                                                             ROOT ZONES.

                                                                                                                                                                                   DOWN PIPE CONNECTION PIT
                                                                                                                                                                                   AND SCOUR PROTECTION
                                                                                                                                                                                                                                                              DP
                                                                                                                                                                                                                                                                                                                     18 CARPARKS



                                                                                                                                60m2 INFILTRATION                                                                                                                     CABIN 1
                                                                                                                                IN-SITU
                                                                                                                                SUB-STRATA
                                                                                                                                                                                          10m WIDE BUSHFIRE ASSET
                                                                                                                                                                                                                                                       DP                                                                                                                    EMT X
                                                                                                                                                                                          PROTECTION ZONE
                                                                                                                            ABOVE GROUND RETAINING WALL
                                                                                                                                                                                                                                                                                                                                                        DP
                                                                                                                            TO AVOID GROUND DISTURBANCE                                                                                                                                                                                                                                                                         EMT B

                                                                                                                                                                                                                                                                                                                                  RL 11.022


                                                                                                                                                                                                                                            DP
                                                                                                                                                                                                                                                                                                                                         CABINS 14 & 15
                                                                                                                                  VEGETATED SWALE 'V' DRAIN.
                                                                                                                                  NOMINAL 200MM DEEP, 1:4V BATTERS.
                                                                                                                                  ARBORIST TO DETERMINE EXTENT OF ROOT
                                                                                                                                  REMOVAL. HAND EXCAVATION AND VACUUM                                         RL 10.730      CABINS 2 & 3                                                                             RL 11.022
                                                                                                                                  SUCKER TRUCK REMOVAL OF SOIL AROUND
                                                                                                                                  ANY STRUCTURAL TREE ROOT ZONES.                                                                                                                                                                                                     EMT A
                                                                                                                                                                                                                                                                                                                               CABINS 12 & 13



                                                                                                                                                                                                                                                                                                                                              DP
                                                                                                                                                                                                                                LOT 3


                                                                                                                                                                                                                                                                                                                                                   DP

                                TYPICAL BIO-INFILTERATION SECTION                                                                                                                                                                                                  DP                                                   CABINS 10 & 11




                                                                                                                                                                EXISTING SURFACE                                                                                                                                   DP
                          EXTENDED RETENTION
                                                                                                                                       0.2m 0.10m 0.40m 0.30m




                                                                                                                                                                                                                                                       CABINS 4 & 5
                                                                                                                                                                                                                                           RL 11.640

                                        FILTER MEDIA                                                                                                                                                                                                                                                            CABINS 8 & 9
                                 TRANSITION SAND
                                 DRAINAGE LAYER
                                                                                                                                                                                                                                                                                      DP




                 IN-SITU SANDY SUB-STRATA
               115MM/HR INFILTERATION RATE
                                                                                                                                                                                                                                                                              CABINS 6 & 7
                                                                                                                                                                                                                                                              RL 11.810




                                                                    INFILTRATE TO NATURAL SOIL (SAND)




                                                                                                                                                                                                                                                                          0              5                 10            15m                                                                                                                                               ISSUED FOR
                                                                                                                                                                                                                                                                                             SCALE 1:250
                                                                                                                                                                                                                                                                                    AT ORIGINAL SIZE (A1)
                                                                                                                                                                                                                                                                                                                                                                                                                                                                     APPROVAL
                                                                                                                                                                                                                                                                                                    Client                                                   Discipline                                                     Status                           Title
                                                                                                                                                                                                                                                                                                                ASPECT ARCHITECTS                             CIVIL                                                          APPROVAL                         BIO-INFILTERATION BASIN -
04   21.07.2023   Issued for Approval                                                      TM   RS                                                                                                                                                                                                  Project Name                                             Designed By                    Checked By                      Approved By
                                                                                                                                                                                                                                                                                                                                                                                                                                                              PRELIMINARY DETAILS
                                                                                                                                                                                                                                                                                                                                                              TM                             AM                              RS
03   13.07.2023   Issued for Approval                                                      TM   RS
                                                                                                                                                                                                                                                                                                                 RACV NOOSA RESORT                           Project No.                    Drawn By                        Scale at A1
02   03.05.2023   Issued for Information                                                   TM   AM
                                                                                                                                                                                                                                                                                                                 94-142 NOOSA DRIVE,                           22366                         TM                              1:250
01   14.12.2022   Issued for Information                                                   TM   AM                                                                                                                        T:1300 657 402          E: [email protected]           W: www.adgce.com
                                                                                                                                                                                                                          Quality Assurance ISO 9001:2015 | Work Health Safety ISO 45001:2018                    NOOSA HEADS QLD 4567                         The concepts and information contained in this document are the copyright of ADG               Drawing No.
00   28.09.2022 Issued for Information                                                     TM   SQ                                                                                                                                     Environmental Management ISO 14001:2015                                                                                Engineers (Aust) Pty Ltd. Use or copying of the document in whole or in part without the

        Date      Description                                                              By   Chk
                                                                                                                                                                                                                                                                                                                                                              written permission of ADG Engineers (Aust) Pty Ltd constitutes an infringement of copyright.    SK03                        04
                                                                                                                                                                                                                                                                                                                                                              Do not scale drawings. If in doubt, ask!

Page 36

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                                                                       Appendix D
                                                         Concept Rehabilitation Plan




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 37

                                                                                                                                                                                                                                        IMPORTANT:
DEVELOPMENT FOOTPRINT (LOT 3)                                                                                                                                                                                                           ALL DRAWINGS MUST BE READ IN CONJUNCTION WITH
                                                                                                                                                                                                                                        THE GENERAL NOTES SHEET
SITE AREA                                          5453m2
DEVELOPED AREA (LOT 3)                             1797m2                                                                                                                                                                                              AMENDMENT SCHEDULE
                                                   33%
REHABILITATION AREA:                                                                                                                                                                                                                   ISS        DATE             DESCRIPTION                   BY
TOTAL REHABILITATION AREA FOR LOT 3 & LOT 203      3141m2                                                                                                                                                                                  A     29/06/23   REHAB. ZONE                           ZT
TOTAL REHABILITATION AREA FOR LOT 3                3041m2                                                                                                                                                                                  B     30/06/23   RESPONSE TO 2ND RFI                   ZT


SPECIES FOR REHABILITATION ZONES



                                                                                                                                                                      AREA OF CARPARK
                                                                                                                                                                      (LOT 203) 171m2
                                                                                                                         AREA OF CARPARK
                                                                                                                         (LOT 3) 330m2




                                                                                                                                                                                              AREA OF BOARDWALK
                                                                                                                                                                                              (LOT 203) 17m2
                                                                                                                ZONE 1
                                                                                                                 781m2
                                                                                                                                                                                    ZONE 2
                                                                                                                                     ZONE 3                                         98m2 (Lot 203)
                                                                                                                                     68m2               CABIN 1




                                                                                                                            ZONE 4                                               CABINS
                                                                                                                             357m2                                               14 & 15


                                                                                                                                      CABINS
                                                                                                                                      2&3
                                                                                                                                                                          CABINS
                                                                                                                                                                          12 & 13



                                                                                                                                              ZONE 5
                                                                                                                                              1,295m2
                                                                                          AREA OF BOARDWALK
                                                                                          (LOT 3) 349m2                                                                CABINS
                                                                                                                                                                       10 & 11


NOTE ON SPECIES SELECTION

•     SPECIES SELECTION INCLUDES SPECIES FROM TECHNICAL DESCRIPTION FOR RE12.2.7 AND

•
      RECORDED ON SITE AND SURROUNDS.
      BUSHFIRE “SUITABLE” SPECIES CONSIDERED FOR ZONES WITH BUSHFIRE MANAGEMENT
                                                                                                                                                 CABINS
      CONSTRAINTS (^ SPECIES IDENTIFIED BY BUSHFIRE CONSULTANT FOR ZONE 4).               ROOF PLAN AREA OF CABINS                               4&5
•
•
      SPECIES WITH * DEFINED AS KOALA HABITAT/FEED TREE.
      FINAL SPECIES PLANTING AND SELECTION DETERMINED BY PLANTING SUITABILITY AND
                                                                                          (CABIN 1 EXCLUDED BEING OVER CARPARK)
      SPECIES AVAILABILITY.                                                               (LOT 3) 1118m2                                                            CABINS
•     INTENT IS TO MAXIMISE SPECIES DIVERSITY AND % GROUND/MID STOREY COVER AND
      SUPPLEMENT WITH CANOPY/KOALA TREES.                                                                                                                           8&9
•     DETENTION BASIN PLANTING SPECIES IN ACCORDANCE WITH WSUD GUIDELINES (ALSO
      SPECIES IN LOCALITY AND FROM RE12.2.7 TECHNICAL DESCRIPTION) AND TO BE MAINTAINED
      (BUSHFIRE CONSULTANT ADVICE) TO 1M WHERE NECESSARY.



LEGEND
                                                                                                                                                                    ZONE 2
                                                                                                                                                           CABINS   542m2 (Lot 3)
                  ZONE 1 – WETLAND/HEATHLAND REHABILITATION (NORTHWEST)
                  •     NO PLANTING RESTRICTIONS.                                                                                                          6&7
                  •     WEED CONTROL/MANAGEMENT.
                  •     PLANTING WITH SPECIES APPROPRIATE TO RE12.2.7 AND LOCALLY
                        OCCURRING.
                  •     INCLUDE KOALA FEED TREES.
                                                                                                                                                                                                                                               TOOWOOMBA | BRISBANE | MOOLOOLABA
                  ZONE 2 – REHABILITATED SCREEN (SOUTH AND EAST)                                                                                                                                                                                          www.aspectapm.net
                  •     DENSE PLANTING ALONG SOUTHERN AND EASTERN BOUNDARY WITH                                                                                                                                                                  ABN 96 071 786 948 ACN 071 786 948
                        SUITABLE NATIVE SPECIES.                                                                                                                                                                                                             BOAQ 4487
                  •     MID TO HIGH STRATA SCREENING TO BE ACHIEVED.
                  •     WEED CONTROL/MANAGEMENT.
                  •     INCLUDE SCATTERED KOALA FEED TREES.
                                                                                                                                                                                                                                                                                      BUILDING DESIGNERS
                                                                                                                                                                                                                                                                                          ASSOCIATION
                  ZONE 3 – DETENTION BASIN                                                                                                                                                                                             GENERAL NOTES
                  •     PLANTING WITH SPECIES RECOGNISED AS SUITABLE FOR DETENTION                                                                                                                                                      THIS PLAN HAS BEEN PREPARED IN ACCORDANCE WITH ALL
                        BASINS.                                                                                                                                                                                                         RELEVANT BUILDING CODES AND STANDARDS. NO AMENDMENTS
                  •     GRASS AND SEDGE SPECIES ABLE TO BE MANAGED (MAINTAINED AT                                                                                                                                                       SHALL BE MADE WITHOUT THE APPROVAL FROM ASPECT AND/OR
                                                                                                                                                                                                                                        RELEVANT LOCAL AUTHORITY.THESE DRAWINGS ARE SUPPLIED ON
                        APPROPRIATE HEIGHT 1M AS NEEDED).                                                                                                                                                                               THE CONDITION THAT, IN THE EVENT OF ERROR, ASPECTS' LIABILITY
                  •     PROVIDE HABITAT AND WATER MAINTENANCE FUNCTION.                                                                                                                                                                 IS LIMITED ONLY TO THE COST OF AMENDING THESE DRAWINGS.

                                                                                                                                                                                                                                        CONTRACTORS ARE TO VERIFY ALL DIMENSIONS ON SITE BEFORE
                  ZONE 4 – BUSHFIRE (APZ) MANAGEMENT                                                                                                                                                                                    COMMENCING ANY WORK OR PRODUCING SHOP DRAWINGS. THESE
                  •     WEED CONTROL.                                                                                                                                                                                                   DRAWINGS ARE PROTECTED BY THE LAWS OF COPYRIGHT AND MAY
                                                                                                                                                                                                                                        NOT BE COPIED OR REPRODUCED WITHOUT THE WRITTEN
                  •     GROUNDCOVERS AND LOW SHRUBS.                                                                                                                                                                                    PERMISSION OF ASPECT .
                  •     RETAIN INDIVIDUAL TREES AS IDENTIFIED.                                                                                                                                                                         PROJECT
                  •     NO FURTHER TREE PLANTING.                                                                                                                                                                                      RACV NOOSA RESORT - ECO
                  ZONE 5 – BALANCE REHABILITATION AMONGST CABINS                                                                                                                                                                       RESORT
                  •     AREA OF INTENSE WEED CONTROL/MANAGEMENT (ESSENTIALLY ALL                                                                                                                                                       FOR
                        UNDERSTOREY IS NON-NATIVE AND WEED VINE ON TREES TO BE
                        TREATED).
                                                                                                                                                                                                                                       ROYAL AUTOMOBILE CLUB OF
                  •     DENSE PLANTING OF GROUNDCOVERS AND LOW SHRUB/MIDSTOREY                                                                                                                                                         VICTORIA




                                                                                                                                                                                                                      CONCEPT DESIGN
                        (I.E. COVER GROUND AND CONTROL WEED ESTABLISHMENT AND                                                                                                                                                          @
                        CREATE A FULLY VEGETATED GREENSPACE ADJACENT AND AMONGST
                        ELEVATED CABINS AND BOARDWALKS).
                                                                                                                                                                                                                                       142 NOOSA DRIVE, NOOSA HEADS
                  •     INTER-PLANTING WITH SMOOTH-BARK KOALA AND OTHER TREE                                                                                                                                                           QLD 4567
                        SPECIES.                                                                                                                                                                                                       DRAWING TITLE




                                                                                                                                                                                                                                       CONCEPT REHABILITATION PLAN
                                                                                                                                                                                                                  N                    DATE                 SCALE @ A1        DRAWN         CHECKED

                                                                                                                                                                                                                                       30/06/23             1 : 300                 ZT             TB
                                                                                                                                                                                                                                       DRAWING No.                                        ISSUE

                                                                                                                                                                                                                                       21-0910_ A10-13                                         B

Page 38

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                                                                Appendix E
                                       Noosa Shire Council Code Responses




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 39

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                              ACCEPTABLE OUTCOMES                                        COMMENTS
 Floodplain protection, immunity and safety - for                  AO1
 development areas                                                 The finished flood level is not less than the minimum      Development will comply
 PO1                                                               design levels specified in Table 8.2.6.4
 Development provides that for all flood events up to and
 including the DFE:
      1. the safety of people on the site is protected; and
      2. the risk of damage to property on the site is avoided
           or minimised as far as practicable.
 PO2                                                               AO2                                                        Development will comply
 All lots have sufficient area that is above the DFE flood level   The minimum area above flood level (flood free area) for
 or where modelling is not available, the highest                  each lot, is in accordance with Table 8.2.6.5.
 recorded flood level, to safely and adequately accommodate
 the intended use.




Page 1 of 9
June 2021

Page 40

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                              ACCEPTABLE OUTCOMES                                          COMMENTS
 PO3                                                               AO3
 For reconfiguring a lot or operational works, development is      Development areas are not filled to reduce flood risk.       Development will comply
 undertaken in a manner that ensures:

              1. natural hydrological systems are protected from
                 erosion, scour or flood damage on the premises
                 or other premises;
              2. natural landforms and drainage lines are
                 maintained to protect the hydraulic performance
                 of waterways and flood plain; and
              3. development integrates with the natural
                 landform rather than modifying the landform to
                 suit the development as far as practicable.

 PO4                                                               AO4.1                                                        N/A
 For reconfiguring a lot, development does not compromise          Development provides an effective evacuation route that
 the safety of people resulting from the flood risk associated     remains passable, with sufficient flood warning time, to
 with events exceeding the DFE.                                    enable people to progressively evacuate to safe areas
                                                                   above the PMF in the face of advancing flood or waters for
                                                                   events that exceed the DFE.

                                                                   OR
                                                                   AO4.2                                                        N/A
                                                                   Development provides for an area of sufficient size and
                                                                   dimensions on site above the PMF that allows for safe
                                                                   congregation and refuge.




Page 2 of 9
June 2021

Page 41

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                           ACCEPTABLE OUTCOMES                                      COMMENTS
                                                AO4.3                                                    N/A
                                                Where the existing roads servicing a development
                                                provide a specific flood immunity (as determined by
                                                the Qld Transport Road and Drainage Design Manual,
                                                Queensland Urban Drainage Manual and the
                                                Australian Rainfall and Runoff Guide), all lots
                                                have access to the flood free area identified in Table
                                                8.2.6.5 that matches the road immunity.




Page 3 of 9
June 2021

Page 42

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                             ACCEPTABLE OUTCOMES                                          COMMENTS
 PO5                                                              AO5                                                          Development will comply
 For reconfiguring a lot or operational works, development        In the Flood Hazard Overlay, or in areas otherwise
 does not directly, indirectly or cumulatively alter the flood    determined to be subject to the DFE or DSTE,
 characteristics external to the development site for all         development ensures:
 flooding and inundation events up to and including                        1. there is no loss of on-site flood storage
 the DFE or DSTE based on:
                                                                              capacity;
              1. current climate conditions; and                           2. all changes to level, depth, duration and
              2. incorporating an appropriate allowance for the               velocity of floodwaters are contained
                 predicted impacts of climate change.                         within the site for all flood events up to
                                                                              and including the DFE based on current
                                                                              climate and predicted impacts of climate
                                                                              change at 2100;
                                                                           3. there is no acceleration or retardation of
                                                                              flows, or any retardation in flood warning
                                                                              times, elsewhere on the floodplain and to
                                                                              any overland flow paths; and
                                                                           4. there is no increased stormwater ponding
                                                                              on sites upstream, downstream or in the
                                                                              general vicinity of the site.

 Resilient building design and form                               AO6.1                                                        Development will comply
 PO6                                                              Buildings are designed to integrate well with the street
 Development ensures that building design and building form:      level and the levels of adjoining properties to facilitate
          1. accounts for potential flood risk;                   pedestrian flows and visual and physical connectivity
          2. is resilient to flood events; and                    between the footpath and ground floors.




Page 4 of 9
June 2021

Page 43

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                           ACCEPTABLE OUTCOMES                                      COMMENTS
              3. maintains a functional and attractive street   AO6.2                                                    N/A.No under-storey proposed.
                 address appropriate to the intended use.       Buildings incorporate appropriate screening to ensure
                                                                that any under-storey is not visible from the street,
                                                                where such screening does not impede flood water
                                                                flows.
                                                                AO6.3                                                    Development will comply
                                                                Residential buildings minimise risk from flooding by
                                                                providing parking and other low intensive, non-
                                                                habitable uses at ground level, rather than habitable
                                                                uses.
                                                                AO6.4                                                    Development will comply
                                                                Non-residential buildings and structures are oriented
                                                                to the street by activating the street frontage with
                                                                appropriate uses and urban design treatments such
                                                                as recessed wall treatments, screening or
                                                                landscaping, whilst allowing for flow through of flood
                                                                waters on the ground floor.
                                                                AO6.5                                                    N/A. No basement or underground
                                                                Basements and underground car parking areas are          parking areas are proposed.
                                                                designed to drain and function safely during a flood
                                                                event and power failure.
 PO7                                                            AO7.1                                                    To be complied with at detailed
 Water quality treatment systems use natural processes and      Water quality treatment systems are designed to be
 materials, whenever possible, and are integrated into                                                                   design / construction stages.
                                                                integrated into the landscape consistent with the
 development to enhance biodiversity and landscape benefits .   technical design guideline published by Healthy Land
                                                                and Water Water by Design for the feature. (eg. For
                                                                Bioretention Basins: Bioretention Technical Design




Page 5 of 9
June 2021

Page 44

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                         ACCEPTABLE OUTCOMES                                          COMMENTS
                                                              Guidelines (October 2014) and for Wetland Systems
                                                              the Wetland Technical Design Guideline (May 2017).


 Essential network infrastructure                             AO8                                                          To be complied with at detailed
 PO8                                                          Essential network infrastructure that is likely to fail to   design / construction stages.
 Essential network infrastructure maintains effective         function or may result in contamination when
 function during and immediately after flood and storm tide   inundated by flood water (e.g. water supply pipeline
 inundation events.                                           air valves and the like) is located above the DFE level
                                                              (or where the DFE has not been modelled for the
                                                              area, above the highest recorded flood level for the
                                                              area).




 Essential community infrastructure                           AO9.1                                                        N/A
 PO9                                                          Essential community infrastructure is sited and
 Essential community infrastructure is able to function       constructed to ensure that flood levels comply with
 effectively during and immediately after flood events.       flood immunity requirements specified in Table
                                                              8.2.6.4.




Page 6 of 9
June 2021

Page 45

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                           ACCEPTABLE OUTCOMES                                   COMMENTS
                                                AO9.2
                                                Essential community infrastructure which is located
                                                below the specified flood immunity requirements:
                                                                                                      N/A
                                                        1. is designed and constructed to function
                                                           effectively during and immediately after
                                                           the recommended flood level event;
                                                           and
                                                        2. has direct access to low hazard
                                                           evacuation routes or an emergency
                                                           rescue area above the PMF, if it is
                                                           for emergency services (including
                                                           emergency shelters, police facilities,
                                                           hospitals and associated facilities).




Page 7 of 9
June 2021

Page 46

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions



 Earthworks                                                            AO10                                                        To be complied with at detailed design /
 PO10                                                                  Filling, other than accessways:                             construction stages.
 Excavation and filling for operational works only occur where
 they:                                                                          1. does not extend more than the equivalent of 3
                                                                                   metres around the main building, measured
              1. result in the protection, rehabilitation and repair               from the outer walls of the building;
                 of ecologically important areas, watercourses,                 2. is limited to a maximum of 500m2 and
                 drainage lines and wetlands;                                   3. does not impact on the local drainage of
              2. do not adversely impact on the overall                            adjoining properties.
                 hydrology, hydraulics and flood capacity of
                 a waterway;
              3. do not directly, indirectly or cumulatively cause
                 adverse impacts external to the site;
              4. do not cause increased flooding, which
                 adversely affects the safety or use of any land
                 upstream or downstream;
              5. do not cause ponding of water on the site or
                 nearby land;
              6. do not result in a reduction in flood storage
                 capacity;
              7. do not adversely affect the flow of water in any
                 overland flow path; and
              8. do not adversely affect the privacy or visual
                 amenity of surrounding property.




Page 8 of 9
June 2021

Page 47

Noosa Shire Council – The Noosa Plan 2020
Flood Hazard Overlay Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                       ACCEPTABLE OUTCOMES                                           COMMENTS
 Hazardous materials                                        AO11.1                                                        To be complied with at detailed
 PO11                                                       Materials manufactured or stored on site are not
 Development ensures that public safety and the                                                                           design / construction stages.
                                                            hazardous or noxious, or do not comprise materials that
 environment are not adversely affected by avoiding the     may cause a detrimental effect on the environment if
 release of hazardous materials into flood waters and the   discharged in a flood event.
 environment.
                                                            OR
                                                            AO11.2                                                        N/A no essential community
                                                            If a DFE is adopted, structures used for the manufacture or   infrastructure is proposed as part
                                                            storage of hazardous material are located above               of the development.
                                                            the DFE level.




Page 9 of 9
June 2021

Page 48

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                              ACCEPTABLE OUTCOMES                                      COMMENTS
 Stormwater drainage design                                        AO1
 PO1                                                               A stormwater management plan is prepared consistent      Development will comply. Refer to
 The development and its stormwater management system is           with PSP6 Engineering Design Standards - Roads,          Stormwater Management Plan, in
 planned and designed having regard to:                            drainage and earthworks.                                 specific stormwater quality and
     1. the natural features of the site;
                                                                                                                            quantity section prepared by this
     2. the need to avoid impacts and potential risks
                                                                                                                            office.
        to ecologically important areas;
     3. the likely effectiveness of erosion and sediment
        control and stormwater drainage measures during
        rainfall events during and post construction; and
     4. the need to protect environmental values and water
        quality of receiving waters both during and post
        construction.
 PO2                                                               AO2.1                                                    To be complied with at detailed
 Stormwater drainage infrastructure is planned, designed and       Stormwater drainage planning, design and construction    design / construction stages in
 constructed to:                                                   is in accordance with PSP6 Engineering Design            conjunction with the Stormwater
                                                                   Standards - Roads, drainage and earthworks and the       Management Plan, prepared by
               1. incorporate allowance for increased flood risk   latest version of the Queensland Urban Drainage Design
                  and tidal inundation through pipework as a                                                                this office.
                                                                   Manual.
                  result of climate change and sea level rise;     AO2.2                                                    Rainwater captured in Bio
               2. ensure the development is adequately drained;    The stormwater drainage system connects to a lawful      Infiltration Basin will gradually
                  and                                              point of discharge in accordance with PSP6 Engineering
               3. ensure stormwater is managed and lawfully
                                                                                                                            infiltrate to soil layers and freely
                                                                   Design Standards - Roads, drainage and earthworks.       discharges subsoil to an outfall to
                  discharged without altering stormwater
                  drainage characteristics external to the site.                                                            Weyba Creek
                                                                   AO2.3                                                    Development will comply, refer to
                                                                   Stormwater flows discharging from the development are    Stormwater Management Plan, in
                                                                   demonstrated to be consistent with pre-development       specific stormwater quantity
                                                                   characteristics.                                         section prepared by this office.




Page 1 of 12
June 2021

Page 49

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                          ACCEPTABLE OUTCOMES                                            COMMENTS
                                                                AO2.4                                                         Development will comply, refer to
                                                                Development provides for the management of                    Stormwater Management Plan
                                                                stormwater to incorporate appropriate allowance for           prepared by this office.
                                                                climate change impacts (including rainfall intensity and
                                                                sea level rise), in accordance in accordance with PSP6
                                                                Engineering Design Standards – Roads, Drainage and
                                                                Earthworks.
 PO3                                                           AO3.1                                                          N/A. No stormwater from the site is
 Stormwater drainage infrastructure conveys run-off in a       Stormwater drainage infrastructure meets the desired           directed towards roads.
 manner that allows roads to deliver desired standards of      standards of service for roads functionality set out in PSP6
 service appropriate to the local conditions and local         Engineering Design Standards - Roads, Drainage and
 stormwater drainage characteristics.                          Earthworks.




 PO4                                                           AO4.1                                                          N/A. Rainwater captured in Bio
 Stormwater infrastructure is compatible with existing         The location, design and construction of stormwater            Infiltration Basin will gradually
 infrastructure, allows for easy access for the ongoing        drainage structures is in accordance with PSP6 Engineering     infiltrate to soil layers and freely
 maintenance by Council, is cost effective across its design   Design Standards - Roads, drainage and earthworks.             discharges subsoil to an outfall to
 life.
                                                                                                                              Weyba Creek. Refer to Stormwater
                                                                                                                              Management Plan prepared by this
                                                                                                                              office.




Page 2 of 12
June 2021

Page 50

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                           ACCEPTABLE OUTCOMES                                            COMMENTS
                                                AO4.2                                                          N/A. Rainwater captured in Bio
                                                Where infrastructure is located on private land an easement    Infiltration Basin will gradually
                                                is dedicated over the infrastructure in accordance with PSP6   infiltrate to soil layers and freely
                                                Engineering Design Standards - Roads, drainage and             discharges subsoil to an outfall to
                                                earthworks.                                                    Weyba Creek. Refer to Stormwater
                                                                                                               Management Plan prepared by this
                                                                                                               office.
                                                AO4.3                                                          N/A. Rainwater captured in Bio
                                                Any alterations or repairs to infrastructure as a result of    Infiltration Basin will gradually
                                                the development are made at no cost to Council.                infiltrate to soil layers and freely
                                                                                                               discharges subsoil to an outfall to
                                                                                                               Weyba Creek. Refer to Stormwater
                                                                                                               Management Plan prepared by this
                                                                                                               office.
                                                AO4.4                                                          Development will comply.
                                                Development avoids stormwater inflow and infiltration to
                                                the sewer infrastructure network.
                                                AO4.5                                                          N/A. Rainwater captured in Bio
                                                Stormwater infrastructure is designed to minimize              Infiltration Basin will gradually
                                                maintenance costs and the requirement for specialized          infiltrate to soil layers and freely
                                                equipment for maintenance techniques.                          discharges subsoil to an outfall to
                                                                                                               Weyba Creek. Refer to Stormwater
                                                                                                               Management Plan prepared by this
                                                                                                               office.




Page 3 of 12
June 2021

Page 51

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                           ACCEPTABLE OUTCOMES                                           COMMENTS
 PO5                                                            AO5.1                                                         N/A
 Stormwater drainage infrastructure is aligned to avoid         Stormwater drainage infrastructure avoids crossing
 crossing waterways, wetlands, drainage lines and               waterways, wetlands drainage lines and ecologically
 ecological important areas, or where it is demonstrated this
 is unavoidable, disturbed areas are reinstated and
                                                                important areas or follows the edge of existing disturbed
 revegetated upon completion of works.                          areas.
                                                                AO5.2                                                         N/A
                                                                Stormwater drainage infrastructure is co-located with
                                                                other infrastructure within a combined utility corridor
                                                                where appropriate.
                                                                AO5.3                                                         N/A
                                                                Temporary vehicular crossings of waterways must be
                                                                designed and constructed to be consistent with the
                                                                current International Erosion Control Association Best
                                                                Practice Book Series.
 Stormwater quality and protection of receiving waters          AO6.1                                                         Development will comply as
 PO6                                                            Stormwater runoff discharging into High Ecological Value      Noosa Shire Council interactive
 Development is located, designed, constructed and operated     waters as a result of development causes no increase in       mapping indicates the site is in an
 to protect and enhance environmental values and water
                                                                gross pollutants, total suspended solids, total phosphorous   environmentally significant area.
 quality of waterways, wetlands, lakes, ground waters and
 drainage systems.                                              or total nitrogen compared to a pre-development scenario.     Refer to Stormwater Management
                                                                                                                              Plan, in specific stormwater
                                                                AND                                                           quality section prepared by this
 Editor’s note: Environmental values of waters and water                                                                      office.
                                                                AO6.2
 quality objectives are prescribed in Schedule 1 of the
 Environmental Protection (Water) Policy 2009 and are
                                                                All stormwater runoff is treated to achieve maximum
 identified on the State Planning Policy Interactive Mapping    removal of nutrients, gross pollutants and suspended          Development will comply, Refer to
 System.                                                        solids as determined by cost to efficiency ratios. (e.g.      Stormwater Management Plan, in




Page 4 of 12
June 2021

Page 52

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                           ACCEPTABLE OUTCOMES                                           COMMENTS
                                                                bioretention basins must be sized to achieve at least 80%      specific stormwater quality section
                                                                reduction in total suspended solids, 60% reduction in total    prepared by this office.
                                                                phosphorous, 45% reduction in total nitrogen and 90%
                                                                reduction in gross pollutants >5mm).

                                                                OR                                                            N/A
                                                                AO6.3
                                                                Developments achieve a minimum 3 drop rating consistent
                                                                with the Water by Design Living Waterways Scoring Guide
                                                                (Healthy Land and Water).
 PO7                                                            AO7.1                                                         Development will comply, Refer to
 Water quality treatment systems use natural processes and      Water quality treatment systems are designed to be
 materials, whenever possible, and are integrated into                                                                        Stormwater Management Plan, in
                                                                integrated into the landscape consistent with the technical
 development to enhance biodiversity and landscape benefits .                                                                 specific stormwater quality section
                                                                design guideline published by Healthy Land and Water
                                                                Water by Design for the feature. (eg. For Bioretention        prepared by this office.
                                                                Basins: Bioretention Technical Design Guidelines (October
                                                                2014) and for Wetland Systems the Wetland Technical
                                                                Design Guideline (May 2017).

 PO8                                                            AO8.1                                                          N/A. Water quality treatment
 Water quality treatment infrastructure to be dedicated as      Detailed life cycle costing is provided for the entire         infrastructure will not be dedicated
 public assets are proven to be suitable for its use and of a   treatment train system including replacement costs of          to Council.
 cost effective and efficient standard.
                                                                asset parts.
                                                                AO8.2
                                                                Treatment systems dedicated as public assets are designed
                                                                to minimize maintenance, renewal and adaption costs and




Page 5 of 12
June 2021

Page 53

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                        ACCEPTABLE OUTCOMES                                            COMMENTS
                                                             the requirement for specialized equipment, material or
                                                             maintenance techniques
                                                             AO8.3
                                                             Vegetated stormwater management systems to be
                                                             dedicated as public assets are established and maintained
                                                             during the maintenance period to ensure optimal
                                                             vegetated growth and that the functional elements of the        N/A
                                                             system achieve the design function at the end of the
                                                             maintenance period.

 PO9                                                         AO9.1                                                          To be complied with at detailed
 Treatment systems are designed to eliminate or minimise     Free draining inlets and outlets are provided to ensure that   design / construction stages.
 health, safety and aesthetic hazards, including risks
 associated with insect breeding, odour and public safety.
                                                             waters do not pond for more than 24 hours.
                                                             AO9.2                                                          To be complied with at detailed
                                                             Developments are designed to eliminate retaining walls in      design / construction stages.
                                                             excess of 0.8m for any water quality treatment device.
 Hydrology and waterway stability                            AO10
                                                                                                                            Development will comply, Refer to
 PO10                                                        The development is designed to:                                Stormwater Management Plan.
 Development prevents increased bed and bank erosion and             1. limit the peak 1 year ARI event discharge
 sedimentation in receiving waterways by avoiding changes               within the receiving waterway to the pre-
 in low rate, peak flow run-off and flow duration.
                                                                        development peak 1 year discharge;
                                                                     2. maximise pervious areas by using pervious
                                                                        alternatives for otherwise impervious areas
                                                                        wherever possible;




Page 6 of 12
June 2021

Page 54

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                             ACCEPTABLE OUTCOMES                                          COMMENTS
                                                                           3. provide for capture and reuse of stormwater
                                                                              for non-potable purposes for gardening, toilet
                                                                              flushing, laundry and hot water supply uses;
                                                                           4. incorporate appropriate detention features;
                                                                              and
                                                                           5. incorporate natural channel design principles

 PO11                                                             AO11.1
                                                                                                                              N/A. No new channels natural
 Water sensitive urban design principles are applied to           The design and construction of a natural channel or natural
 achieve multifunctional design of waterways, wetlands and                                                                    channel or natural channel
                                                                  channel rehabilitation works are in accordance with the
 drainage lines that provide for:                                 Natural Channel Design Guidelines (Brisbane City            rehabilitation works are proposed.
          1. stormwater conveyance that uses natural
              channel design;
                                                                  Council) having regard to local topography, geology, and
          2. protection of landscape features and ecological      geomorphology.
              important areas including terrestrial and aquatic   AO11.2                                                      To be complied with at detailed
              habitat;                                            Landscape features, plant species and habitat types used    design / construction stages.
          3. aesthetic and passive recreation values;             in stormwater conveyance channels are complementary to
          4. flood management and conveyance of external          the local context and natural waterways.
              catchment stormwater through the                    AO11.3                                                      To be complied with at detailed
              development;                                        Bank and bed stability and planting densities result in a   design / construction stages.
          5. landscaping that incorporates local native           stable channel over the long term and minimal potential
              species; and                                        for pest plant species.
          6. bed and bank stability.                              AO11.4
                                                                                                                               Development Complies, Water
                                                                  Water Sensitive Design measures are incorporated into the
                                                                                                                               Sensitive Design measures were
                                                                  development, as detailed in the document Water Sensitive
                                                                  Designs small improvements, new ideas, concepts and          incorporated in the SBSMP.




Page 7 of 12
June 2021

Page 55

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                    ACCEPTABLE OUTCOMES                                           COMMENTS
                                                         sketch designs for stormwater filtration systems (Healthy
                                                         Waterways Water by Design).
                                                         AO11.5
                                                                                                                       Development will comply..
                                                         Floodplain management is designed in accordance with
                                                         the Framework for the Integration of Flood
                                                         and Stormwater Management into Open Space published
                                                         by Healthy Waterways Water by Design (version current at
                                                         the time of development application).
 PO12                                                    AO12.1                                                        Development will comply, pre-
 Development protects in-stream ecology by maintaining   Where run-off from or within the site passes through or       development low flows will be
 pre-development low flow discharge regimes and          drains to natural channels, waterways or wetlands,            maintained in accordance with the
 maintaining fish passages.                              development protects in-steam ecology by maintaining
                                                                                                                       frequent flow management
                                                         pre-development low flow discharge regimes in
                                                                                                                       objectives in PSP6 Engineering
                                                         accordance with the frequent flow management objectives
                                                         in PSP6 Engineering Design Standards - Roads, drainage        Design Standards - Roads,
                                                         and earthworks                                                drainage and earthworks
                                                         AO12.2                                                        N/A no instream structure are
                                                         Instream structures such as roads, bridges, culverts, and     proposed within this SBSMP
                                                         other stormwater infrastructure do not cause barriers to      prepared by this office.
                                                         fish passage and facilitate the movement of terrestrial and
                                                         aquatic fauna along waterway corridors.
                                                         AO12.3                                                        Development will comply.
                                                         Benthic substrate retains a continuous grade with the
                                                         direction of flow consistent with the natural bed profile.




Page 8 of 12
June 2021

Page 56

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                       ACCEPTABLE OUTCOMES                                       COMMENTS
 PO13                                                       AO13.1                                                    To be complied with at detailed
 Development is designed and constructed to maintain        The location and form of stormwater discharge points do   design / construction stages.
 surface and ground water balances that sustain the         not alter the pre-development hydrology of receiving
 environmental values of water dependent ecosystems,        surface water or groundwater.
 including downstream aquatic, riparian, wetland and
 terrestrial ecosystems.                                    AO13.2                                                     N/A Development is not located
                                                            Developments located on groundwater recharge or            on groundwater recharge or
                                                            discharge areas are designed and managed in accordance     discharge areas.
                                                            with a groundwater recharge and discharge management
                                                            plan prepared by a suitably experienced and qualified
                                                            groundwater hydrologist. The groundwater recharge or
                                                            discharge must demonstrate that the development does
                                                            not affect groundwater balances beyond the property
                                                            boundaries.
 Construction and establishment of stormwater               AO14.1                                                    To be complied with at detailed
 management systems                                         An erosion and sediment control plan prepared in          design / construction stages.
 PO14                                                       accordance with the International Erosion Control
 Construction methods provide for appropriate controls to   Association Best Practice Books demonstrates that the
 avoid entry and transport of litter, sediment, and         capture and release of stormwater achieves the design
 associated prescribed water contaminants into receiving    objectives listed in Table A: Construction phase –
 waters.                                                    stormwater management design objectives of the State
                                                            Planning Policy (Appendix 2).

                                                            AO14.2                                                    To be complied with at detailed
                                                            Construction works are designed and managed to restrict   design / construction stages.
                                                            the extent of clearing and soil exposure to the minimum




Page 9 of 12
June 2021

Page 57

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                           ACCEPTABLE OUTCOMES                                      COMMENTS
                                                necessary for access, and safe construction at any one
                                                time.
                                                AO14.3                                                    To be complied with at detailed
                                                For buildings:                                            design / construction stages.

                                                            1. upstream runoff is diverted around
                                                               the construction site;
                                                            2. sediment barriers are provided
                                                               downslope of disturbed areas to
                                                               prevent sediment washing into
                                                               gutters, drains and waterways ,
                                                               wetlands or drainage lines either on
                                                               or off the site; and
                                                            3. temporary or permanent downpipes
                                                               are connected to the stormwater
                                                               system before laying the roof; or
                                                            4. Localized erosion is avoided by
                                                               directing flow from downpipes over
                                                               non-erosive areas.
                                                AO14.4                                                   To be complied with at detailed
                                                Chemical flocculants used as part of an erosion and      design / construction stages.
                                                sediment control plan do not harm the environmental
                                                values within receiving waters.
                                                AO14.5                                                   To be complied with at detailed
                                                                                                         design / construction stages.




Page 10 of 12
June 2021

Page 58

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                                   ACCEPTABLE OUTCOMES                                           COMMENTS
                                                        Appropriately sized litter containment areas, with
                                                        provision for sorting recyclables are provided for the type
                                                        of litter expected to be generated onsite.
                                                        AO15                                                          N/A
 Wastewater management and effluent disposal            Wastewater (non-sewage) generated from the
 PO15
                                                        development is collected and contained on-site, and is:
 Development does not discharge wastewater unless it
 can be demonstrated to not compromise environmental
                                                                 1. lawfully disposed to sewer; or
 values of waters and water quality objectives
                                                                 2. transferred off-site for treatment/disposal to
                                                                    an appropriately licenced facility;
                                                                 3. reused on-site in a closed-cycle irrigation
                                                                    scheme, industrial processes, washing or
                                                                    cleaning or other purpose; or
                                                                 4. treated to meet the drinking water supply
                                                                    environmental values prior to release.
 PO16                                                   AO16                                                          N/A
 On-site effluent treatment and disposal systems are    An onsite effluent system and disposal area is:
 designed, constructed and managed to not compromise
 the environmental values of waters and water quality            1. not located on a slope greater than 1 in
 objectives.                                                        (10%);
                                                                 2. not located at or below the 1% annual
                                                                    exceedance probability (AEP flood event);
                                                                 3. not located within a riparian buffer
                                                                    area mapped on a Biodiversity, Waterways
                                                                    and Wetlands Overlay Map; and




Page 11 of 12
June 2021

Page 59

Noosa Shire Council – The Noosa Plan 2020
Water Quality and Drainage Code
Performance Criteria and Acceptable Solutions




 PERFORMANCE OUTCOMES                           ACCEPTABLE OUTCOMES                                  COMMENTS
                                                     4.   setback 400 metres minimum from the full
                                                          supply level of Lake Macdonald.




Page 12 of 12
June 2021

Page 60

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




                                                        Appendix F
                    Noosa Shire Council Erosion Hazard Assessment




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 61

        SCHEDULE 2—EROSION AND SEDIMENT CONTROL




                                                                                                                   Proposed Amendments August 2015
                     ASSESSMENT




                                                                                                  The Noosa Plan
1.            Preamble

Erosion and sediment control on building sites

Builders must not pollute the environment. The Environmental Protection Act provides for
penalties for persons or entities causing environmental harm.

Soil erosion on building sites can be a major source of sediment pollution (environmental
harm) in our watercourses. A single building site can lose up to four truckloads of soil in one
storm. Washed from the sites into stormwater drains, this sediment can cause flooding and
also affects the water quality and the fish stocks in our creeks, lakes and the Noosa River
system.

Preventing sediment run-off from building sites is one of a number of ways that Council and
industry are improving our watercourses.

Effective on-site erosion and sediment control provides the following benefits—


      A better looking, more marketable site;
      Improved wet weather working conditions;
      Reduced stockpile losses;
      Less mud and dust problems;
      Reduced clean-up costs;
      Fewer public complaints;
      Better public image;
      Cleaner watercourses; and
      Better fishing and swimming in our nearby watercourses.

2.            Erosion Hazard Assessment Form
Controlling Factors                                                   Points   Score   Checking
Predominant slope1 of the whole site, prior to
building works:
 0 - 3% slope                                                           0
 >3% - 5% slope                                                         1
 >5% - 10% slope                                                        2        1
 >10% - 15% slope                                                       4
 > 15% slope                                                            5
Soil type: (see 1 below)
 Sandy soil/gravel                                                      0
 Sandy loam                                                             1        1
1
    The term ‘predominant slope’ is defined in Part 2 Section 2.12.



                                                              S2.1

Page 62

                                                   Controlling Factors                                                 Points         Score         Checking
                                                    Clay loam                                                             2
                 Proposed Amendments August 2015
The Noosa Plan



                                                    Clay soil                                                             2
                                                   Anticipated duration of site disturbance: (see 2 below)
                                                    Duration < 2 weeks                                                      0
                                                    2 weeks  Duration < 3 months                                           2             5
                                                    3 months  Duration < 6 months                                          4
                                                    Duration > 6 months                                                     5
                                                   Month that works are undertaken: (see 3 below)
                                                    August, September                                                       0
                                                    April, May, June, July, November, October                               1              1
                                                    March December                                                          2
                                                    January February                                                        3
                                                   Offsite sediment control (i.e. down slope of the soil
                                                   disturbance):
                                                    Score 1 point if there is no purpose built, operational                 1
                                                       and well maintained sediment traps (eg. sediment                                     1
                                                       basin, gross pollutant trap or purpose built wetland)
                                                       to catch sediment before it enters a water body with
                                                       environmental values (eg. creek, natural wetland,
                                                       river or bay) (see 4 below)
                                                   Run-off entering the site:
                                                    Score 1 point if stormwater run off entering the site is                1              0
                                                       not diverted away from the soil disturbance
                                                   Extent of site disturbance:
                                                    Score 2 points if building work requires reshaping of
                                                       the ground surface (eg. ‘cut and fill’ works) (see 5                  2
                                                       below)                                                                               2
                                                     Score 5 points if the area to be disturbed is greater                  5
                                                      than 600m²
                                                   Works within environmentally sensitive areas:
                                                    Score 11 points if the disturbance is within the banks
                                                      of a watercourse (see 6 below)                                        11
                                                    Score 5 points if the disturbance is within 50m of the                                 2
                                                      top of bank of a watercourse                                           5
                                                    Score 2 points if the disturbance is between 50m
                                                      and 100m of the top of bank of a watercourse                           2

                                                   TOTAL SCORE (See 7 & 8 below)                                                           13           LOW
                                                   Notes:
                                                       1. Where there is more than one type of soil on the site, select the category with the highest point value.
                                                       2. The time, from when the building site will first become vulnerable to erosion, to the time the soil will
                                                          be fully stabilised (eg. grassing).
                                                       3. If this time span covers more than one category, select the category with the highest point value.
                                                          Note that if there is no grass/vegetation cover on the site before building work has started, the time
                                                          span starts from the time this form is completed.
                                                       4. If you are not sure, score 1 point.
                                                       5. For the purpose of this form, ‘cut and fill’ works are those that will result in a steep batter or retaining
                                                          wall above and/or below the building slab, greater than 1 metre in height. If the building slab has
                                                          already been fully cut and stabilised (eg. grassed) during the subdivision stage, score 0 points.
                                                       6. Watercourse means any clearly identifiable creek, stream or river, whether flowing permanently or
                                                          intermittently.
                                                       7. For a high risk site, the total score is  14 points.
                                                       8. For a low risk site, the total score is < 14 points.




                                                                                                            S2.2

Page 63

                                                                                                                  Proposed Amendments August 2015
3.        Erosion and Sediment Control Methods




                                                                                                 The Noosa Plan
                    Element                                    Solution

Minimise disturbance when excavating      Retain as much grassed area as possible on the
                                          site.
                                          These areas not only improve the appearance
                                          of the site they also filter much of the sediment
                                          from stormwater run-off before it reaches the
                                          drainage system.
Catch drains and perimeter banks          Allow for diversion of up slope stormwater
                                          around the work site and other disturbed
                                          surfaces.
Install a sediment barrier                Install sediment barriers down slope of the
                                          building site to filter coarse sediment before it
                                          can wash into gutters, drains and watercourses.
                                           Purpose designed geotextile sediment
                                               fabric (i.e. not shadecloth) attached to posts
                                               with the geotextile buried in an upstream
                                               trench; or
                                           Place turf of a minimum 600mm width along
                                               kerb line; or
                                           Straw bales, staked in a 100mm (min) deep
                                               trench.
Single gravelled entry-exit               Restrict vehicle access to one entry-exit point.
                                           Gravelling the access point will allow all
                                               weather access, will reduce the amount of
                                               soil carried off the site by vehicles, and will
                                               provide a permanent base for the driveway.
Early stormwater drainage connection      Connect a temporary or permanent downpipe/s
                                          to the stormwater system before laying the roof
                                          or slow and spread the flow from downpipe/s to
                                          avoid localised erosion. Downpipe/s may be
                                          temporarily removed during wall construction.
                                          All stormwater must discharge in a manner that
                                          does not cause soil erosion.
Concrete waste and washing                Waste concrete and household paint must not
                                          be allowed to wash into the gutters or the street.
Sand and soil stockpiles                  Stockpiles must be placed wholly on the
                                          construction site and behind a sediment barrier.




                                       S2.3

Page 64

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023


                                                               Appendix G
                                Noosa Shire Council (Interactive Mapping)




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 65

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:4514

Page 66

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:4514

Page 67

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:4514

Page 68

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:4514

Page 69

 

 

10}
r168CP8495 16)

0
148MCH4796

0
167CP849516

~
&

G latels

(S62 Road Labels
= Major
2 ga Intermediate
e | ——
S7REII0234 Property Label
620 SO .
— aN pe PlaceNames

9 “4
‘85RP94023) 5 Fs

28% D
poi PS.
pes
84RP94023 a
Foy FOOpegso1 RP94023}
42 2s

Y55'00)

1928)
ie
fie Peest A
BY he ef 81 RP94023)
isis 29 Ieee
3 eB i80RP94023) =
57RP94023)

24)
3}

‘
27
"i 9RP94023)

Se
78RP94023)
1

IS8RP940:

Q
Ai

10:
“

la =
20 05
M103RP94023)
Oe q
oS)
pace)
105RP94023) F oh

109RP94023) Bian 146RP94023)

Py
v3.
ae “yg87RP94023) :
rr abcae cS S “a ‘
2H 50, 7RP94023
‘ a Se OY, dopoeans 7, 4
ats

= 93RP94023) z
a SF iy 20s ee
Py i \
Bo ea reo
i94RP94023 me
ag

arias a

boS!00)

3. S Ope |
ot .

S 2235 4 De
"A118RP94023) u137RR94023
FS
16 vay

Site
24)
peeecanrs

“145RP94023 ms
nH
M'56RP94023¢_
fo)
_ ASSRP94023
M47RP94023)

74
6 y 1 54RP94023}

 

 

 

 

g Fire Management
g Brigade Areas
3) Rural Brigade Areas (DCS)
E29) Urban Brigade Areas (DCS)
BQA
D
AV FireBreaks Trails
ME Bushfire Hazard Area (Bushfire Prone Area)
Gm Very High Potential Bushfire Intensity
HB High Potential Bushfire Intensity
ME Medium Potential Bushfire Intensity
Potential Impact Buffer
& Contours
Az Contour Labels
/\/ Contours (1m)
g Transport and Facilities
Emergency Services Facilities
Evacuation Centres

 

/V/ Minor
QB Beach Access
On-Road Bike Routes
BAZ
/V/ Cycle bus lane
SV Cycle lane
Cycle parking lane
Green treatment
/V/ Greenlink
/\V/ Intersection
/V/ Intersection signalised
/V/ Mixed traffic street
/\/ Roundabout
/V/ Sealed shoulder
Shared zone
,>, Other
Noosa Trail
Trail 1
Trail 2
AN Trait3
f\¢ Trail 4
JN ¢ Trail 5
AN Trail
Trail 7
Trail 8
SV/ Pathways
Oe Railway
Water Skiing Areas
Permitted
Prohibited
@ On-Water Navigation Aids

 

 

 

21/04/2022

 

 

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying

 

OOSA COUNCIL upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability

  

 

 

 

whatsoever for any errors, faults, defects or omissions in the information. 1:2257

 

 

 

 

 

 

Page 70

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:2257

Page 71

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying   21/04/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                        1:4514

Page 72

Noosa Shire Council does not warrant the accuracy of information in this publication and any person using or relying                                1/12/2022
upon such information does so on the basis that Noosa Shire Council shall bear no responsibility or liability          NSC - Flood Hazard Overlay
whatsoever for any errors, faults, defects or omissions in the information.
                                                                                                                                                     1:2257

Page 73

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023


                                                                      Appendix H
                                                       MUSIC Modelling Information




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 74

                                                                RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                       ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                         July 2023




 MUSIC Model Information

 Introduction:

 The quality of stormwater runoff and the impact of the proposed stormwater quality improvement measures
 were analyzed using MUSIC Version 6.3.0 according to the MUSIC Modeling Guidelines Version 1.0, Water
 by Design 2010. The source nodes in the model are split into two types and a summary of the area breakdown
 is presented below:

 Meteorological Data:

 The MUSIC model was carried out using the following parameters:

 - Modeling period should be 10 years with a time step of 6 minutes

 - The nearest available 6 minute time step rainfall series to the subject site is Cooroy (Rainfall Station ID
 040059), with a mean annual rainfall of 1595 mm, and data from: 1/1/1973 to 31/12/1983. Evaporation was
 applied as monthly mean. The mean annual evaporation was 1201 mm.




 Source Nodes, Fractions Impervious:

 The areas of the source nodes were estimated from the Post Development Stormwater Catchment Plan as
 shown in Appendix C

 Source Nodes - Pollutant Exports:

 Rainfall runoff and pollutant export parameters were assigned per Tables 3.7 and 3.8 of the Water by Design
 MUSIC Modeling Guidelines Version 1.0 (2010).

 The rainfall runoff and pollutant export parameters for an Urban development were adopted.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 75

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




 Properties of Bio Infiltration Basin:




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 76

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




 Treatment Train for Prost Development:




 Results for Post-Development:




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 77

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023




 Treatment Train for Pre-Development:




 Results for Pre-Development:




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 78

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023

 MUSIC Parameters – Existing Vegetated Surface/Suspended Timber Walkway:




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 79

                                                              RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                     ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                       July 2023



                                                                               Appendix I
                                                                       Geotechnical Report




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA

Page 80

                                                             CONSTANT HEAD TEST
                                             Talsma Hallam Metod AS/NZ 1547:2000 Appendix 4.1F

     Client ADG                                                             Hole No           Permeability 1
    Project Bio-Basin                                                     Test Date            April 12, 2023
   Location RACV Noosa Resort                                            Project No.              23109
                                                                                                                                      dh
  Tested by MS                                                             Checked                  MT




                          Depth of Hole (Lh)                 40.00 cm   Vegetation
                     Tube below Surface (Lt)                 10.00 cm     Area may be occasionally inundatedwith
                      Length to Air Inlet (Ls)                 1.0 cm                  stormwater.
                             Test Section (H)                   30 cm   Soil moisture prior to test                                             Lt
                 Diameter of test section (Dh)               10.00 cm       Saturated for 5-10 min prior to test.                   Dt               Lh
                                                                                                                                           Ls
                        Diameter of tube (Dt)                5.000 cm         Continuously draining (>15L).
                       Static depth to gw (hs)                     cm   General comments (soil structure,              H
                                                                                                                                      Dh
                Depth Impermeable Layer (S)                        cm   macro pores, water logging etc)
                          Radius of Tube (R)                  2.50 cm
                                                                             SAND, Fine to Meduim Grained.             S
                    Radius of Test Section (r)                5.00 cm
                                                                                                                       Impermeable Layer
                                                                                       i = 1, 2, 3, ....n
                                                                   50                                       Level in   Difference
                                                                                          i     Time         Tube       in level
                                                                   45
                                                                                                  t            h           dh         K
                                                                   40                           (min)        (cm)         (cm)       (m/s)
                                                                                          1      0.0          0.0
                                                                   35
                                                                                          2      0.5          10.0         10.00    2.9E-05
                                                                   30                     3      1.0          21.0         11.00    3.2E-05
                                                                                          4      1.5          32.0         11.00    3.2E-05
                                                                   25
                                          y = 22x - 0.6                                   5      2.0          44.0         12.00    3.5E-05
                                           R² = 0.999              20                     6
                                                                                          7
                                                                   15
                                                                                          8
                                                                   10                     9
                                                                   5                     10
                                                                                         11
                                                                   0                     12
                                                                   -5                    13
       0.0      0.5        1.0      1.5         2.0          2.5                         14
                                                                                         15
                           Time t (min)                                                  16
                                                                                         17
                                                                                         18
                                                                                         19
      Calculation of Hydraulic Conductivity, K :                                         20
                                                                                         21
          π R 2 ∆h                                                                    22
                     0.5sinh-1  H  −      r             r 
      4.4                                      2  + 0.25 +                       23
             ∆t                 2r         H             H
                                                                                     24
K =
                                   2πH 2                                                 25
                                                                                         26
                                                                                         27
                                                                                         28
                                                                                         29
                                                                                         30
      Equilibrium Hydraulic Conductivity :                                               31
                                                                                         32
                                     Time                 Height                         33
              Start from     1        0.0                  0.0                           34
                End at       5        2.0                  44.0                          35
                      K = 3.2E-05 m/sec                                                  36

Page 81

                                                                                                                                                                                                                                                                                                                                                                                                                                               Borehole No.

                                                                                                                                                                                                                                                                                                                                                                                                                                                     HA1
                                                                                                                                                                                                                                                                                                                                                                                                                                               Page 1 of 1

                                                                                                                                                                                                            Engineering Log - Borehole                                                                                                                                      Project No.:                      23109

                                                                                                                                                                                                                 Client:                                        Aspect Architects                                                                                           Commenced:                        12/4/2023
                                                                                                                                                                                                                 Project Name:                                  Proposed Bio-Basin                                                                                          Completed:                        12/4/2023
                                                                                                                                                                                                                 Hole Location:                                 94 & 142 Noosa Drive, Noosa Heads                                                                           Logged By:                        MS
                                                                                                                                                                                                                 Hole Position:                                 508265.3 m E 7080053.1 m N MGA2020 Zone 56                                                                  Checked By:                       MT
                                                                                                                                                                                                                 Drill Model and Mounting:                                     Hand Auger                                                  Inclination: -90°                RL Surface:                No survey
                                                                                                                                                                                                                 Hole Diameter:                                                100 mm                                                      Bearing:     360°                Datum:                     AHD             Operator:          Tectonic

                                                                                                                                                                                                                                    Drilling Information                                                                                                  Material Description and Observations




                                                                                                                                                                                                                                                                                                                                                                                    Relative Density
                                                                                                                                                                                                                                                                                                            Classification
                                                                                                                                                                                                                                                                                                                                                                                                          Pocket                          DCP TEST
                                                                                                                                                                                                                     Penetration




                                                                                                                                                                                                                                                                                                                                                                                    Consistency
                                                                                                                                                                                                                                                                                              Graphic Log


                                                                                                                                                                                                                                                        Samples                                                                              Material Description
                                                                                                                                                                                                                                                                                                                                                                                                       Penetrometer
                                                                                                                                                                                                                                                                    Recovery




                                                                                                                                                                                                                                                                                                                                                                                    Condition
                                                                                                                                                                                                                                                         Tests                                                                 soil type: plasticity or particle characteristics,




                                                                                                                                                                                                                                                                                                                                                                                    Moisture
                                                                                                                                                                                                                                                                                                                                                                                                           UCS                        Blows per 100 mm
                                                                                                                                                                                                                                                                                                            Symbol
                                                                                                                                                                                                            Method




                                                                                                                                                                                                                                                        Remarks                                                                 secondary and minor components, colour
                                                                                                                                                                                                                                   Water




                                                                                                                                                                                                                                                                                RL    Depth                                                                                                               (kPa)
                                                                                                                                                                                                                                                                                (m)    (m)                                                                                                                             0        5        10     15     20    25




                                                                                                                                                                                                                                                                                                                                                                                                       100
                                                                                                                                                                                                                                                                                                                                                                                                       200
                                                                                                                                                                                                                                                                                                                                                                                                       300
                                                                                                                                                                                                                                                                                                                                                                                                       400
                                                                                                                                                                                                                                                                                                                                                                                                       500
                                                                                                                                                                                                                                                     DS                                                                      SAND, (FILL), fine grained, pale brown, with
                                                                                                                                                                                                                                                                                                                                                                                                                           HW
                                                                                                                                                                                                                                                     0.0-0.3m                                                                organics, trace cobbles, 70mm
                                                                                                                                                                                                                                                                                                                                                                                            VL to
                                                                                                                                                                                                                                                                                                                                                                                             L



                                                                                                                                                                                                                                                                                                                             without cobbles, trace organics
                                                                                                                                                                                                                                                                                                                                                                                             MD

                                                                                                                                                                                                                                                                                      0.5
                                                                                                                                                                                                                                                                                                                CI           Sandy CLAY, (FILL), medium plasticity, pale grey,                          120
                                                                                                                                                                                                                                                                                                                                                                                              St
                                                                                                                                                                                                                                                                                                                             red brown, orange
                                                                                                                                                                                                                                                                                                              SM             Silty SAND, (ALLUVIUM), fine to medium
                                                                                                                                                                                                                                                                                                                             grained, grey
                                                                                                                                                                                                                                   Not Encountered




                                                                                                                                                                                                                                                                                                                                                                                      M
TECTONIC 3.00.2 LIB.GLB Log 1 TECTONIC BOREHOLE 23109.GPJ <<DrawingFile>> 13/4/2023 11:54 10.02.00.04 Datgel Lab and In Situ Tool - DGD | Lib: Tectonic 3.00.2 2021-03-30 Prj: Tectonic 3.00.2 2021-03-30




                                                                                                                                                                                                                                                     DS
                                                                                                                                                                                                                                                     0.8-1.0m
                                                                                                                                                                                                                                                                                                                                                                                               L
                                                                                                                                                                                                            HA




                                                                                                                                                                                                                                                                                      1.0




                                                                                                                                                                                                                                                                                                                                                                                             MD



                                                                                                                                                                                                                                                                                      1.5
                                                                                                                                                                                                                                                     DS                                                                      becoming dark grey
                                                                                                                                                                                                                                                     1.5-1.7m
                                                                                                                                                                                                                                                                                                                                                                                    M to
                                                                                                                                                                                                                                                                                                                                                                                               D
                                                                                                                                                                                                                                                                                                                                                                                     W
                                                                                                                                                                                                                                                                                                              SM             Indurated SAND, (ALLUVIUM), fine to medium
                                                                                                                                                                                                                                                                                                                             grained, dark grey, weakly cemented
                                                                                                                                                                                                                                                                                                                             Hole Terminated at 1.80 m
                                                                                                                                                                                                                                                                                                                             Hand auger refusal on indurated sand


                                                                                                                                                                                                                                                                                      2.0




                                                                                                                                                                                                                      Method                                             Penetration                                         Water                    Samples and Tests                         Moisture Condition                  Consistency/Relative Density
                                                                                                                                                                                                                 AD/T-Auger Drilling TC Bit                                       VE - Very Easy         Level (Date)                          U## - Undisturbed Sample (## mm)                     D - Dry                            VS - Very Soft
                                                                                                                                                                                                                 AD/V-Auger Drilling V Bit                                        E - Easy                                                     DS - Disturbed Sample                                M - Moist                          S - Soft
                                                                                                                                                                                                                 RT - Rotary Tri-cone Bit                                                                Inflow                                BDS - Bulk Disturbed Sample                          W - Wet                            F    - Firm
                                                                                                                                                                                                                 RD - Rotary Drilling                                             F - Firm                                                     SPT - Standard Penetration Test                                                         VSt - Very Stiff
                                                                                                                                                                                                                                                                                                         Partial Loss
                                                                                                                                                                                                                 NMLC -Rock Core                                                  H - Hard                                                                                                                                             H - Hard
                                                                                                                                                                                                                                                                                  VH - Very hard        Complete Loss
                                                                                                                                                                                                                 HA - Hand Auger                                                                                                                                                                       Plastic Limit                   VL - Very Loose
                                                                                                                                                                                                                                                                                Graphic Log/Core Loss                                                                                                                                  L    - Loose
                                                                                                                                                                                                                                                                                                                                                    Classification Symbols and                            < PL                         MD - Medium Dense
                                                                                                                                                                                                                                                                                   Core recovered (hatching                                              Soil Descriptions
                                                                                                                                                                                                                                                                                   indicates material)                                                                                                    = PL                         D - Dense
                                                                                                                                                                                                                                                                                                                                                       Based on Unified Soil                              < PL                         VD - Very Dense
                                                                                                                                                                                                                                                                                   Core loss                                                                                                                                           Fr - Friable
                                                                                                                                                                                                                                                                                                                                                       Classification System

Page 82

  Adelaide                                Brisbane
  Level 6, 19 Grenfell Street             596 Milton Road
  Adelaide SA 5000                        Toowong, QLD 4066
  Phone:     1300 657 402                 Postal:    PO Box 1492 Toowong
  Email:     [email protected]                          BC QLD 4066
                                          Phone:     1300 657 402
                                          Email:     [email protected]
  Darwin                                  Gold Coast
  Suite G01, Manunda Place                Suite 201, Level 1, 1 Short Street
  38 Cavenagh Street                      Southport, QLD 4215
  Darwin, NT 0800                         Postal:    PO Box 208
  Phone:     1300 657 402                            Southport, QLD 4215
  Email:     [email protected]               Phone:     1300 657 402
                                          Email:     [email protected]
  Hobart                                  Melbourne
  Tenancy 1B, Level 1,                    321 / 838 Collins Street
  199 Collins Street                      Docklands, VIC 3008
  Hobart TAS 7000                         Phone:     1300 657 402
  Phone:     1300 657 402                 Email:     [email protected]
  Email:     [email protected]
  Perth                                   Sunshine Coast
  Suite 9, Level 2, 23 Railway Road,      Level 3, 2 Emporio Place
  Subiaco WA 6008                         Maroochydore, QLD 4558
  Phone:     1300 657 402                 Postal:    PO Box 5014
  Email:     [email protected]                          Maroochydore BC, QLD 4558
                                          Phone:     1300 657 402
                                          Email:     [email protected]
  Sydney                                  Toowoomba
  Suite 22.02, Level 22,                  Tenancy 8, 158 Margaret Street
  111 Pacific Highway,                    Toowoomba QLD 4350, Australia
  North Sydney, NSW, 2060                 Phone:     1300 657 402
  Phone: 1300 657 402                     Email:
  Email: [email protected]




Driven by passion and vision, courage, and optimism, we truly believe that no
project or challenge is beyond us. At ADG, we design with purpose, to make a
difference.



ADG Engineers

www.adgce.com

Used in these records

About this file

File size
35.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdf · 35.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.