2ND RFI - Attachment 4A - Stormwater Management Plan (2) · MCU22/0118

of 82

Check the original when the exact wording matters.

Plans and drawings: the text below has words only, no drawings.

Very large file (35.2 MB): may take a few minutes to open.

Log in to see the plans as drawn
                                                                  RACV Noosa Resort: 94-142 Noosa Drive, Noosa Heads

                                                                         ADG Ref: 22366 C R10 Rev07 21.07.2023.docx

                                                                                                           July 2023




                    Figure 7 - Results for Post-Development Model at Receiving Node


         As shown above in Figure 7, a significant pollutant reduction is shown at the receiving node.

         Based on the results from the In Situ Constant Head Permeability Test using the Talsma-Hallam Test
         method (per AS1547) undertaken by Tectonics Geotechnical & Environmental Engineers, the site has
         sand and sandy soil texture up to a minimum depth of 1.7m. Saturated soil permeability (Ksat) was
         assessed from the results of in situ constant head test. The test site was pre-soaked using a minimum
         15L of water prior to testing. It is noted that the pre-soak waters drained away rapidly, as would be
         expected of typically sandy media. Refer to Appendix I for the test results.

         Since the majority of the stormwater runoff from the roof will be re-used by the rainwater tanks and the
         rest of the runoff is intended to infiltrate onsite through the bio-basin, no discharge will be proposed
         from the site.

         Currently it is assumed that a silty sand sub-strata will have a hydraulic conductivity of approx. of
         3 .19 × 10−5 m/s, for a 60 m2 bio infiltration basin area, this equates to a yearly capacity of 60,356
         𝑚3 /yr which exceeds the infiltration rate of the receiving node being 2.93 ML/yr (2,930 𝑚3 /yr). It is
         therefore understood that the existing subgrade will have sufficient capacity to infiltrate all treatable
         flows with no additional stormwater infrastructure required to be implemented to the downstream
         waterway.

         Details of the MUSIC model are attached within Appendix H for further information.

         Refer to Appendix C for the Preliminary Layout Plans prepared by ADG.

 6.6      On-site Treatment Lifecycle Costs
         A lifecycle cost analysis is not a part of the scope of this report. All the recommended water quality
         treatment infrastructure lies within the development site and it shall be maintained and serviced by the
         owners of the development at no cost to Council.




BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA           Page 18

Used in these records

About this file

File size
35.2 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdf · 35.2 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.