Figure 7 - Results for Post-Development Model at Receiving Node
As shown above in Figure 7, a significant pollutant reduction is shown at the receiving node.
Based on the results from the In Situ Constant Head Permeability Test using the Talsma-Hallam Test
method (per AS1547) undertaken by Tectonics Geotechnical & Environmental Engineers, the site has
sand and sandy soil texture up to a minimum depth of 1.7m. Saturated soil permeability (Ksat) was
assessed from the results of in situ constant head test. The test site was pre-soaked using a minimum
15L of water prior to testing. It is noted that the pre-soak waters drained away rapidly, as would be
expected of typically sandy media. Refer to Appendix I for the test results.
Since the majority of the stormwater runoff from the roof will be re-used by the rainwater tanks and the
rest of the runoff is intended to infiltrate onsite through the bio-basin, no discharge will be proposed
from the site.
Currently it is assumed that a silty sand sub-strata will have a hydraulic conductivity of approx. of
3 .19 × 10−5 m/s, for a 60 m2 bio infiltration basin area, this equates to a yearly capacity of 60,356
𝑚3 /yr which exceeds the infiltration rate of the receiving node being 2.93 ML/yr (2,930 𝑚3 /yr). It is
therefore understood that the existing subgrade will have sufficient capacity to infiltrate all treatable
flows with no additional stormwater infrastructure required to be implemented to the downstream
waterway.
Details of the MUSIC model are attached within Appendix H for further information.
Refer to Appendix C for the Preliminary Layout Plans prepared by ADG.
6.6 On-site Treatment Lifecycle Costs
A lifecycle cost analysis is not a part of the scope of this report. All the recommended water quality
treatment infrastructure lies within the development site and it shall be maintained and serviced by the
owners of the development at no cost to Council.
BRISBANE / DARWIN / GOLD COAST / HOBART / MELBOURNE / PERTH / SUNSHINE COAST / SYDNEY / TOOWOOMBA Page 18
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
2ND RFI - Attachment 4A - Stormwater Management Plan (2).pdfRelated documentApplication case desk ↗
About this file
- File size
- 35.2 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.