Appeal judgement 30-32 Doonella St Tewantin - MCU21-0013 OPW21-0013
Original PDF page 1, section 1. The text section number identifies this passage in the reader.
In the Planning and Environment Court No. BD2677 of 2021
Held at: Brisbane
Between: DOONELLA STREET PTY LTD ACN 611 394 793 ATF
THE DOONELLA STREET UNIT TRUST Appellant
And: NOOSA COUNCIL Respondent
JUDGMENT
Before her Honour Judge Kefford
Date of Hearing: 23 February 2022
Date of Judgment: 23 February 2022
THIS MATTER HAVING come on for hearing by way of an appeal against the decision of the
Respondent to refuse a development application for Development Permit for Material Change of Use -
Multiple Dwelling Units (19 x Small Dwelling Units), Food and Drink Outlet, Indoor Sport and
Recreation, Health Care Service, and Office and Development Permit for Operational Works –
Stormwater Management, Access, Parking, Earth Works and Frontage Works (Application) on land
located at 30 - 32 Doonella Street, Tewantin and more particularly described as Lot 32 on RP 893427
and Lot 903 on T1631,
AND UPON HEARING solicitor for the Appellant and solicitor for the Respondent,
IT IS ORDERED, WITH THE CONSENT OF THE PARTIES, THAT:-
1. the appeal be allowed;
2. the Respondent's decision be set aside;
3. the Application be approved, subject to the development approval package attached hereto,
paginated 1 to 51 and marked "A"; and
4. each of the parties bear their own costs of the proceeding.
JUDGMENT HWL Ebsworth Lawyers
Filed on behalf of the Appellant Level 19, 480 Queen Street
Form PEC-7 Brisbane QLD 4000
Tel: +61 7 3169 4700 Fax: 1300 368 717
Ref: PJB:CJV:1083546
Planning Act 2016 Version 1 July 2017
Doc ID 924222943/v1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of sections 2 to 22 (of 105)
Section 2
-2-
Filed on: 23 February 2022
Filed by: HWL Ebsworth Lawyers
Service Address: Level 19, 480 Queen Street
Brisbane QLD 4000
Phone: +61 7 3169 4700
Fax: 1300 368 717
Email: [email protected]
..................................................................................
Registrar
Doc ID 924222943/v1
Section 3
"A"
1. APPLICATION DETAILS
Application No: MCU21/0013 & OPW21/0013
Street address: 30 & 32 Doonella St, Tewantin
Real property description: Lot 32 RP 893427 & Lot 903 T1631
Planning Scheme: The Noosa Plan 2020 (25 September 2020)
2. DECISION DETAILS
The following type of approval was issued:
• Development Permit for Material Change of Use - Multiple dwelling units (Small Dwelling
units x 19), Food and Drink outlet, Indoor Sport and Recreation, Health Care Service,
Office
• Development Permit for Operational Works -Stormwater Management, Access, Parking,
Earth Works & Frontage works
3. CURRENCY PERIOD OF APPROVAL
The currency period for this development approval is stated in the conditions below.
4. CONDITIONS OF APPROVAL
MATERIAL CHANGE OF USE - MCU21/0013
PLANNING
When Conditions must be Complied With
1. Unless otherwise stated, all conditions of this Decision Notice must be complied with
prior to the use commencing, and then compliance maintained at all times while the use
continues.
Approved Plans
2. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
SD01 13 Site Plan, prepared by Archicology P/L 08/07/21
SD02 12 Ground / Carpark Plan, prepared by 08/07/21
Archicology P/L
SD03 10 Level 1 Plan, prepared by Archicology P/L 31/05/21
SD3A 2 LHA-SDA Compliance Plan, prepared by 14/05/21
Archicology P/L
SD04 6 Level 2 Plan, prepared by Archicology P/L 23/04/21
SD06 6 Roof Plan, prepared by Archicology P/L 23/04/21
SD10 10 Elevations, prepared by Archicology P/L 08/07/21
1
Section 4
SD11 10 Elevations, prepared by Archicology P/L 08/07/21
SD12 7 Sections A, B, prepared by Archicology P/L 23/04/21
SD13 7 Sections C, D, prepared by Archicology P/L 14/05/21
SD14 10 3D Impression 01, 02, prepared by 08/07/21
Archicology P/L
SD15 9 3D Impression 03, 04, prepared by 08/07/21
Archicology P/L
SD16 6 3D Impression 05, 06, prepared by 23/04/21
Archicology P/L
SD17 6 3D Impression 07, prepared by Archicology 23/04/21
P/L
Nature and Extent of Approved Use
3. No more than one Food and drink outlet is approved to operate at any one time and
must be located in one tenancy only as identified on the approved plans of development.
The Food and drink outlet must only operate between the hours of 7am and 9pm, 7 days
per week.
4. Class sizes for the Indoor Recreation use are not to exceed 5 persons at any one time
between the hours of 9am and 5pm.
5. All dwelling units must have a gross floor area of no more than 100m2 pursuant to the
definition of a ‘small dwelling’ under the Noosa Plan 2020.
6. Service vehicle movements associated with non-residential uses on the premises
(including loading and unloading) must not occur outside the hours of 7am to 6pm
Monday to Saturday and not at all on Sundays or public holidays. The requirements of
this condition must be included in the Community Management Statement for any body
corporate for the subject site.
Currency Period
7. This development approval lapses if the use has not happened by 17 February 2028,
unless an application to extend the currency period is approved by Council.
Building Height
8. The maximum height of the development must not exceed the building height and
storeys shown on the approved plans.
9. Certification must be submitted to Council from a Licensed Surveyor which certifies that
the buildings do not exceed the maximum height requirement of this Decision Notice.
Performance Bond
10. Security in the form of a cash bond or trading bank guarantee to the sum of $30,000
must be submitted to Council, to secure performance of all conditions of this approval,
prior to pre-start meeting. The cash bond or trading bank guarantee will be returned on
performance of the conditions of approval less any costs incurred by Council in respect
of enforcing performance of this permit. Council reserves the right to call upon the bond
or guaranteed sum to effect compliance with conditions.
2
Section 5
Built form
11. All air conditioning units or other mechanical equipment must be fully enclosed or
screened such that they are not visible from the street frontages nor adjoining properties.
12. All deck and balcony areas above ground floor must not be enclosed by permanent
fixtures such as shutters, louvres, glass panelling or the like, except where required to
satisfy any privacy condition of this Decision Notice.
13. External finishes must be as per the approved plans of development.
14. External colours must be muted environmental tones that blend with the natural
environment.
15. The Energex PMT and the Fire hydrant booster must be finished in a colour that blends
with the natural environment and the development.
Communal Recreation Areas
16. Communal recreation area/s must be provided as shown on the approved plans of
development.
Street Identification
17. The street address of the development must be clearly visible and discernible from the
primary frontage of the site by the provision of a street number and, where appropriate,
the building name.
Water & Sewer Connections
18. An underground connection to reticulated water and sewerage must be provided to the
development site in accordance with the standards and requirements of Northern SEQ
Distributor–Retailer Authority (Unitywater).
19. A Certificate of Completion from the Northern SEQ Distributor–Retailer Authority
(Unitywater) must be submitted to Council that certifies an underground connection to
reticulated water and sewerage has been provided to the development site.
ENGINEERING
Site Access and Driveways
20. Sealed access driveways must be provided from Doonella Street to all parking and
manoeuvring areas of the development. The works must be undertaken in accordance
with the conditions of this Decision Notice and must include in particular:
a. driveway crossovers generally in accordance with Council’s standard drawing RS-
051;
b. suitable safety measures, including warning signage, to improve driver awareness
of pedestrians and enhance pedestrian safety. Warning signage must be provided
near the exit ramp from the parking area to warn motorists of pedestrian movement
along the frontage street.
Car Parking
21. Thirty three (33) car parking spaces must be provided and marked on the site and made
available and accessible at all times. The works must be undertaken in accordance with
the conditions of this Decision Notice and must include in particular:
a. for the residential development, a maximum of 20 parking spaces within the total,
which are clearly marked for that purpose and accessible at all times; and
b. the balance of carparking for the commercial uses; and
c. 12 motorcycle spaces; and
3
Section 6
d. disabled parking spaces as shown on the approved plans; and
e. dimensions, crossfalls and gradients in accordance with Australian Standard
AS2890: Parking Facilities.
22. All car parking areas and access driveways must be maintained exclusively for vehicle
parking and manoeuvring and kept in a tidy and safe condition at all times.
23. Directional signage must be provided to direct visitors and customers to the car parking
spaces provided on site.
Pedestrian and Bicycle Facilities
24. Pedestrian and bicycle facilities must be provided for the development. The works must
be undertaken in accordance with the conditions of this Decision Notice and must
include in particular:
a. a 2 metre wide concrete footpath within the road verge, the same colour as the
existing (dark), for the entire length of the site’s frontage to Doonella Street;
b. a 2m wide concrete pathway for the full length of the ‘public thoroughfare’
easement, along the full length of the easement located along the northern
boundary
a. pedestrian pathways between the proposed car parking area and the building/s;
b. adequate separation of all specific pedestrian routes from vehicle access and
manoeuvring areas, and clear demarcation by pavement marking, signposts or
changes in surface materials or levels;
c. signage and lighting at strategic locations to direct people to building entries and
public toilet facilities;
d. bicycle parking spaces and lockers as shown on the approved Ground / Carpark
Plan (Plan SD02, Iss.12).
Stormwater Drainage
25. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must be undertaken in accordance with the conditions of
this Decision Notice.
Services
26. Unless otherwise stipulated by telecommunications legislation at the time of
construction, the development must be provided with all necessary conduits, pits and
pipes to accommodate the future connection of optic fibre technology
telecommunications.
27. Certification must be submitted to Council from all relevant service providers (Energex,
NBN and Unitywater) which certifies that the development has met the requirements of
this Decision Notice and all applicable legislation at the time of construction.
Easements
28. A 3 metre wide easement for “Public Thoroughfare” must be registered against the title
of the property in favour of Council. The easement must be located as shown, in red, on
Drawing No. SD03, titled “Level 1 Plan”, Issue 10, dated 31/05/2021 and prepared by
Archicology P/L.
29. Unless otherwise agreed in writing by the relevant service provider, any public or third
party infrastructure located on the subject site must be placed within an easement
registered against the title of the property.
4
Section 7
30. All easements must be designed in accordance with the planning scheme and granted
at no cost to the Grantee. Where the Grantee is Council or a service authority, the
easement documentation must be in accordance with the Grantee’s standard easement
terms. Draft easement documentation must be submitted to Council for endorsement.
31. All works must be kept clear of any existing or proposed easements on the subject land,
unless agreed otherwise in writing by the Grantee.
Geotechnical Stability
32. All works must be carried out generally in accordance with geotechnical investigation
report 18151-001-Rev0, titled: “Proposed Commercial & Residential Development 30-
32 Doonella St Tewantin”, dated 22 June 2018 and prepared by Tectonic Geotechnical
and Environmental Engineers.
33. Certification must be submitted to Council from a qualified person* which certifies that
the development has been constructed in accordance with the recommendations
contained in geotechnical investigation report 18151-001-Rev0, titled: “Proposed
Commercial & Residential Development 30-32 Doonella St Tewantin”, dated 22 June
2018 and prepared by Tectonic Geotechnical and Environmental Engineers, and that
the development has a minimum factor of safety against landslip of 1.5 in the long term.
*(Refer to advisory Note)
Earthworks and Retaining Walls
34. All fill and associated batters must be undertaken in accordance with the conditions of
this Decision notice, and must be contained entirely within the subject site unless written
permission from the respective landowner(s) is provided to Council. All earthworks must
be undertaken in accordance with the provisions of Australian Standard AS3798:
Guidelines on Earthworks for Commercial and Residential Developments.
35. Where the development involves excavation or filling over, or adjacent to, drainage,
water supply or sewerage infrastructure, all access chamber surface levels must be
adjusted to provide a freeboard of 100mm above the finished ground surface level.
36. All retaining walls must be designed and constructed in accordance with the planning
scheme and must be certified by an RPEQ where exceeding 1.0m in height. All retaining
walls that are publicly accessible and exceed 1.0m in height must be fitted with a
commercial grade safety fence.
37. The retaining wall located to the north of the bio basin (shown on section D of
A6035/21/D1, E with a TOW of RL8.4) must be amended to not exceed 0.8m above the
NGL. The area between this retaining wall and the footpath further north can either be
tiered (retaining walls no greater than 0.8m above NGL) or battered (1:4) to the footpath
to the north.
Damage to Services and Assets
38. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Water quality
39. The site must be provided with a stormwater drainage system connecting to a lawful
point of discharge. The works must include in particular:
5
Section 8
a. Water quality treatment features that achieve the following pollutant reduction
targets as measured by a MUSIC model developed in accordance with the Water
by Design MUSIC modelling guidelines;
b. the use of gravity stormwater drainage and not surcharge pits;
c. A stormwater quality treatment system must be provided for the development that
achieved 80% reduction in Total Suspended Solids, 60% reduction in Total
Phosphorous, 45% reduction in Total Nitrogen compared to an unmitigated
scenario. The works must be undertaken in accordance with an Operational Works
approval and the Water by Design Guidelines.
40. All stormwater quality treatment devices must be maintained in accordance with the
Water by Design (2009) - Maintaining Vegetated Stormwater Assets (Version 1). A copy
of this document must be retained on the site together with the approved Operational
Works drawings for the stormwater quality treatment system and a detailed life cycle
costing of the system attached as an addendum. Records of all maintenance activities
undertaken must be kept and made available to Council upon request.
41. Any proposed Community Management Statement required for the development must
include the Water by Design (2009) – Maintaining Vegetated Stormwater Assets
(Version 1) document and must include the full cost of maintaining the system in
accordance with that document.
42. Operating rainwater collection and stormwater harvesting tanks must be provided as
shown identified in section 6.2 of the Engineering Report & Stormwater Management
Plan report For Proposed Residential and Commercial Tenancies at 30-32 Doonella St
(A6035/21/ENG/RevB). The tanks must be provided in accordance with an Operational
Works approval.
43. Certification must be submitted to Council from a qualified person* which certifies that
the rainwater collection tank/s and associated reticulation has/have been installed in
accordance with the requirements of this Decision Notice.
*(Refer to Advisory Note)
Acid Sulfate Soils
44. All waters, including stormwater runoff, groundwater seepage and leachate must
achieve the following quality prior to release from the site at all times:
a. a pH range of 6.5-8.5 pH units;
b. 50mg/L maximum total suspended solids concentration;
c. 0.3mg/L maximum total iron concentration;
d. 0.2mg/L maximum total aluminium concentration; and
e. no visible plume at either the point of release from the site or within a waterway.
ENVIRONMENTAL HEALTH
Waste Storage
45. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9, Waste Management, including an external imperviously
paved area correctly sized for all refuse and recycling containers and suitably screened
from public places and neighbouring properties.
6
Section 9
46. A bin wash area is required with a cold-water tap, hose and drain outlet connected to
sewer, via a bucket trap. The drain outlet is to be designed to prevent storm water entry
to the sewerage system which can be achieved by a bunded area, with a nib wall height
of 100mm maximum, enclosing a wash area of 700mm x 700mm minimum (max 0.7m²).
Alternatively, the waste area can be roofed, or any other appropriate design approved
by Council.
Noise
47. Written certification is required from a suitably qualified person confirming that sound
pressure levels from all mechanical plant and equipment comply with the following:
a. Air-conditioning and Refrigeration
• 7am to 10pm: Maximum level allowable = background + 5dB(A)
• 10pm to 7am: Maximum level allowable = background + 3dB(A)
b. Pumps
• 7am to 7pm: Maximum level allowable = background + 5dB(A)
• 7pm to 10pm: Maximum level allowable = background + 3dB(A)
• 10pm to 7am: No audible noise.
48. The certification must be submitted to Council, which certifies that operational noise from
any fixed plant and equipment complies with the requirements of this Decision Notice.
Kitchen Exhaust (Food and drink outlet)
49. Kitchen exhaust points for the Food and drink outlet must be located and operated in
accordance with Australian Standard AS1668.2-2002 “The use of ventilation and air-
conditioning in buildings” (specifically Section 5.10 – Air Discharges).
50. The development must be constructed with reticulated ducting inside the building to
transfer kitchen exhaust fumes to a discharge point on the roof.
51. Submission of written certification must be provided from a suitably qualified person
confirming that the kitchen exhaust is constructed, installed and is operating in
accordance with Australian Standard AS1668.2-2002.
52. The assessment and certification is required immediately after installation of the
equipment and prior to any occupation of the building, and in a format approved by
Council.
Outdoor Lighting Devices
53. Lighting associated with the use must be designed, sited, installed and tested to comply
with Table 2.1 & 2.2 of Australian Standard AS4282-1997 “Control of the obtrusive
effects of outdoor lighting” using a control level of 1.
54. Certification must be submitted to Council from a qualified person which certifies that all
outdoor lighting devices comply with the requirements of this Decision Notice at the time
of commissioning.
For the purpose of certifying outdoor lighting devices for the development, a qualified
person is:
a. a Registered Professional Engineer of Queensland;
b. an environmental or electrical design consultant with a minimum of 3 years current
experience in the field of outdoor lighting.
7
Section 10
LANDSCAPING
55. The development site must be landscaped. The works must be undertaken in
accordance Noosa Plan PSP 2 – Landscaping and generally in accordance with the
approved Landscaping Plans and in particular:
a. A 1m wide garden along the south side of the ‘public thoroughfare’ easement must
be provided which includes native species that effectively screen the development
and grow to a minimum mature height of 4m.
b. Plantings along the eastern side of the bio basin must grow to a minimum height
of 3-4m and provide screening to the car parking area.
c. Landscaping works to provide a suitable visual screening buffer between the
building and the easement with a minimum garden bed width of 800mm.
d. The proposed 25 litre pot size feature trees within the front setback (facing
Doonella Street) must be replaced with 45 litre pot size plants (the SYZ hem, CUP
ana, ELA ret, ACR imp species)
e. The existing street trees in the road reserve may be removed. If removed they
must be replaced with 4 x ex-ground Delonix regia (poinciana’s) as shown on the
approved operational works landscape plans.
56. All landscape works must be established and maintained in accordance with the
approved design for the life of the development, and in a manner that ensures healthy,
sustained and vigorous plant growth. All plant material must be allowed to grow to full
form and be refurbished when its life expectancy is reached.
Signage
57. Advertising devices must comply with Council’s signage policy.
OPERATIONAL WORKS - OPW21/0031
Approved Plans
58. Development undertaken in accordance with this approval must generally comply with
the approved plans of development. The approved plans are listed in the following table
unless otherwise amended by these conditions.
Plan No. Rev. Plan/Document Name Date
SD02 12 Ground / Carpark Plan, prepared by 08/07/2021
Archicology P/L
A6035/21/EW01 F Earthworks Layout Plan, prepared by Alta 25/05/2021
Engineering
A6035/21/R01 F Roadworks Layout Plan, prepared by Alta 25/05/2021
Engineering
A6035/21/R03 E Roadworks Doonella Street – Cross 25/05/2021
Sections, prepared by Alta Engineering
A6035/21/R04 B Roadworks Setout Plan, prepared by Alta 25/05/2021
Engineering
A6035/21/R08 A Roadworks Boundary Cross Sections, 25/05/2021
prepared by Alta Engineering
8
Section 11
A6035/21/D01 E Stormwater Layout Plan, prepared by Alta 25/05/2021
Engineering
A6035/21/D02 E Stormwater Drainage Details, prepared by 25/05/2021
Alta Engineering
A6035/21/D03 B Stormwater Drainage Setout Plan, prepared 25/05/2021
by Alta Engineering
A6035/21/WQ01 E Stormwater Treatment Catchment Plan, 25/05/2021
prepared by Alta Engineering
A6035/21/WQ02 E Stormwater Quality Layout Plan and Notes, 25/05/2021
prepared by Alta Engineering
A6035/21/WQ03 E Stormwater Quality Bio Basin Calculations 25/05/2021
and Details, prepared by Alta Engineering
CD-001 J Vegetation Management Plan, prepared by 2021.05.28
Project Urban
CD-002 L Landscape Plan – In Ground, prepared by 2021.05.28
Project Urban
CD-003 K Landscape Plan – In Ground, prepared by 2021.01.25
Project Urban
CD-004 I Landscape Plan – On Podium, prepared by 2021.01.25
Project Urban
CD-005 I Landscape Plan – Boundary Fences, 2021.01.25
prepared by Project Urban
CD-200 L Construction Details, prepared by Project 2021.01.25
Urban
CD-201 C Planting Schedule, prepared by Project 2021.01.28
Urban
CD-202 B Planting Schedule, prepared by Project 2021.07.07
Urban
CURRENCY PERIOD
59. The Currency Period for this development approval lapses if the development has not
substantially started by 17 February 2024, unless an application to extend the currency
period is approved by Council.
PRIOR TO COMMENCEMENT OF WORKS
Engineering
60. All necessary approvals from external service providers (e.g. Unitywater) and external
parties on which the development works are proposed have been obtained and a copy
supplied to Council.
61. A condition report of the drainage system must be completed for agreement prior to the
prestart meeting. The condition report is to include a CCTV inspection of the existing
pipe and must include at least 50m upstream and downstream of all works.
9
Section 12
62. A condition report including photographs of the frontage of the site must be completed
and submitted to council prior to the prestart meeting.
63. Certificates demonstrating currency of public liability insurance and works insurance
covering the works must be submitted to Council prior to the prestart meeting.
64. Council must be contacted at least 5 working days prior to any works commencing to
organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500.
The pre-start meeting must include the relevant parties for the following aspects of the
works:
a. Civil engineering works;
b. Landscape works;
c. Erosion and sediment control works;
d. Other relevant parties.
65. A Construction Management Plan must be submitted to Council prior to the pre-start
meeting and must specifically address the following:
a. Traffic Management during all aspects of the construct phase including:
i. A Traffic Management Control Plan in accordance with Manual of Uniform
Traffic Control Devices (MUTCD) detailing all temporary signage and traffic
control measures prior to construction;
ii. Maintenance of safe pedestrian access across the frontage of the site both
during daily construction and after daily construction has ceased;
iii. Proposed fencing to the site during the construction phase of the
development;
iv. Adequate parking arrangements for construction workers;
v. No queuing of trucks is permitted on residential streets, especially prior to
7.00am. Further parked trucks must have engines turned off.
b. Maintenance and protection of water quality and existing drainage lines through
the construction site through the implementation of appropriate erosion and
sediment control measures;
c. Provision for safe pedestrian access across the frontage of the site both during
daily construction and after daily construction has ceased;
d. Works programme identifying key components of the works and their respective
durations;
e. Establishment of a communication protocol with the general public, adjoining
owners, emergency services and local businesses to advise of agreed
construction times, impacts on traffic and services and other relevant issues;
f. Include a post out to the local residents and businesses advising of the proposed
development, the expected time frames and the site contact details.
g. Include signage in prominent locations on the boundaries of the site advising of
the proposed development, the expected time frames and the site contact details;
h. identification of complaint management procedures including:
i. contact details for the on-site manager;
ii. dispute resolution procedures;
10
Section 13
i. For haulage operations involving significant volumes of excavated material being
transported off the site: details on the location of external site, the haulage route,
type of vehicle to be utilised during excavation operations and frequency of usage.
NB any damage to the existing road system as a result of haulage operations must
be fully repaired at the applicant’s expense.
66. Any changes to the details associated with the supervising RPEQ or Principal Contractor
during construction, must be notified to council in writing within five business days of the
change occurring.
67. Any conflict between the development and an existing or proposed service must be
referred to the relevant service authority for determination prior to commencement of
works.
DURING CONSTRUCTION
Engineering
68. All works must be supervised by a Registered Professional Engineer of Queensland
(RPEQ) who is independent of the Developer and Principal Contractor, and they must
certify that all works conform to the Operational Works permit. Where municipal works
are involved, such confirmation must be submitted for the respective hold points prior to
any site inspection by Council Officers.
69. All works must be constructed and work procedure undertaken in accordance with:
a. The approved plans/documents and conditions detailed in this Decision Notice;
b. All relevant Noosa Council Planning Scheme Policies, standard drawings,
standard specifications and guidelines;
c. The latest version of the Healthy Waterways document “Water Sensitive Urban
Design Technical Design Guidelines for South East Queensland” for all water
quality devices to be constructed on site.
Roadworks
70. The installation and/or modification of any traffic signs, street signs, line marking and
Raised Reflective Pavement Markings (RRPMs) must be in accordance with the Manual
of Uniform Traffic Control Devices (MUTCD). New or relocated signage must be
installed using the VLok installation system. All new signage must be Class 1
retroreflective material in accordance with AS 1906.1, Retroreflective materials and
devices for road traffic control purposes – Part 1: Retroreflective sheeting.
71. The developer must notify Council’s Traffic Engineer for any works involving the removal
or modification of existing council traffic signs and/or parking bays prior to such works
commencing.
Pavement Design and Construction
72. Pavement design for privately owned works must be undertaken in accordance with the
relevant standards. Structural integrity of the driveway and car park areas will remain
the responsibility of the property owner/developer and must be certified by an RPEQ.
Works within Road Reserve/Reinstatement
73. Safe pedestrian access on all streets in the vicinity of the development must be
maintained at all times. Should footpath/road closures be necessary to carry out
construction works, Council’s Engineering Officer must be notified prior to the proposed
closure and all requirements complied with.
74. All frontage works must match neatly with existing road and verge/footpath features.
Additional works beyond the frontage may be required to provide an acceptable
transition to existing road and verge/footpath profiles.
11
Section 14
75. Electrical conduits or other services proposed to be installed within existing and
proposed road reserves under existing sealed carriageways, concrete pathways,
concrete/sealed driveways or significant vegetation must be installed by boring.
Trenching is not permitted, unless specifically approved by Council.
Pathways
76. All pathways must be constructed in accordance with the following requirements:
a. All footpath/cycleway must comply with Council’s Standard Drawing SEQ R-065;
b. Provision must be made for disabled access at all kerb crossings associated with
pathways, in accordance with Council's current standards;
c. All paths must have a slip resistant surface, with a colour to match the existing
(dark);
d. Expansion and contraction joints must provide a flush finish. Installation of joints
by saw cutting is preferred to ensure a smooth ride for cyclists;
e. Pram ramps where required.
f. The required work includes any modifications to ensure the footpath finishes flush
with all existing service covers and the like, or alternatively these services are
raised or altered, so as not to create a pedestrian safety hazard.
77. Pathways must:
a. terminate in a manner that ensures smooth transition to existing surfaces for public
safety;
b. be designed and constructed to comply with the Disability Discrimination Act
(DDA), Access to Premises Standard, Austroads and relevant sections of AS1428
Design for access and mobility.
Site Access and Driveways
78. Driveway crossovers must be constructed generally in accordance with Council’s
Standard Drawing RS-051.
79. Any existing unnecessary or redundant property accesses must be removed, and the
kerb, footpath and verge area reinstated to match the existing footpath and/or verge
treatments. Grassed verge areas to be reinstated must be provided with 100 mm topsoil
and grass seed or turf, and must be maintained by the developer until established.
80. The following must be complied with during the construction of the required
crossover/driveway:
a. The driveway surfacing must consist of either an approved hot mixed asphaltic
concrete or patterned/plain concrete;
b. The driveway must be constructed so as not to concentrate stormwater runoff onto
neighbouring properties;
c. Where there is an existing pedestrian path, a matching crossfall must be provided
for the driveway on the alignment of the path, for the full width of the path;
d. The property accesses must be located a minimum of 1m clear of existing power
poles, streetlights or other signage. The developer is responsible for any
necessary relocation of existing services to provide this clearance and must
contact the relevant service authorities and comply with their requirements in
relation to these works.
12
Section 15
Earthworks and Retaining Walls
81. All earthworks must be undertaken in accordance with the provisions of AS 3798
Guidelines on Earthworks for Commercial and Residential Development, with
geotechnical testing undertaken in accordance with Section 8 of the Standard, and to a
minimum of ‘Level 2’ as defined in Appendix B. Test results as required by AS 3798,
and a certificate of quality and uniformity of fill must be provided by a RPEQ and
submitted to Council prior to Council undertaking the On-Maintenance inspection.
82. Fall protection must be provided to retaining walls that are over 1m high.
83. Slope and batters are a maximum grade of:
a. 1 in 6 where in proximity to waterbodies;
b. 1 in 4 for grassed areas;
c. 1 in 3 for planted areas;
d. 1 in 2 for combined structural engineering and planting solutions.
Stormwater Drainage
84. Appropriate scour protection must be provided at the outlet of all stormwater pipes
including temporary outlets.
85. Works associated with this permit must not adversely impact on the existing drainage
conditions on other properties (e.g. by blocking or interfering with natural overland
flows).
86. Construction of all internal stormwater drainage works must comply with the relevant
section/s of Australian Standard AS/NZS 3500.3.
Landscaping
87. The development site must be landscaped. The works must be undertaken in
accordance Noosa Plan PSP 2 – Landscaping and generally in accordance with the
approved Landscaping Plans and in particular:
a. The along the south side of the easement must include native species that
effectively screen the development and grow to a minimum mature height of 8m.
b. Plantings along the eastern side of the bio basin must grow to a minimum height
of 4m and provide screening to the car parking area.
c. The proposed 25 litre pot size feature trees within the front setback (facing
Doonella Street) must be replaced with 45 litre pot size plants
d. The existing street trees in the road reserve may be removed. If removed they
must be replaced with 4 x ex-ground Delonix regia (Poinciana’s) 400L trees as
shown on the approved landscape plans.
88. The finished level of all mulch in garden beds and landscaped medians is to be a
minimum of 50mm below the level of the adjacent top of kerb. All landscaping is to be
constructed in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
89. Suitable root barriers must be installed where proposed trees are adjacent to paths,
pavement etc in accordance with Council’s Planning Scheme Policy PSP2 Landscaping.
Damage to Services and Assets
90. Any damage caused to existing services and assets as a result of the development
works must be repaired at no cost to the asset owner at the following times:
a. where the damage would cause a hazard to pedestrian or vehicle safety,
immediately; or
13
Section 16
b. where otherwise, upon completion of the works associated with the development.
Any repair work which proposes to alter the alignment or level of existing services and
assets must first be referred to the relevant service authority for approval.
Erosion & Sediment Control - Works adjacent to High Ecological Significance
Water
91. Prior to the requesting the pre-start meeting the applicant must engage a Certified
Professional and Erosion Control to prepare and provide to Council scheduling plans for
the development which demonstrate that construction can be undertaken in a manner
consistent with Accepted best practice standards and all relevant conditions of this
approval. * (Refer to Advisory Note).
92. The applicant must engage a CPESC, or other suitably trained professional, (i.e. who
has completed the CPESC training, and has a minimum of 5 years site experience
supervising Erosion and Sediment Control management) to undertake weekly site visits
to inspect and certify whether or not required Erosion and Sediment controls are properly
installed and maintained to achieve the requirements on this approval.
93. Construction must be managed such that less than 2,500m2 of soil is exposed at any
time.
94. Exposed soil is only permitted between the months of May to October, and all
catchments with these soils must drain to sediment treatment features to achieve
50mg/L TSS prior to release of waters from the site. Outside these months the site must
achieve a C factor of 0.05 at all times.
95. A construction hold point with a council delegate and supervising RPEQ must be
established prior to commencement of cut to fill earthworks for each stage of the
development. The hold point must be held as soon as reasonably practical and prior to
the first rain event forecast following initial tree clearing or removal of soil stabilising
material for each stage. At the hold point inspection, all required sediment basins, drains
and bunds to divert waters away from disturbed soil or soils about to become exposed
through cut to fill activities must be installed. All areas that will not require earthworks in
the imminent cut to fill operation must be stabilised to prevent entrainment of sediments
into receiving waters.
96. Cut to fill earthworks must not commence until after the Supervising CPESC has certified
that all installed erosion and sediment controls required by this approval are sized in
accordance with conditions of the approval and the written acceptance of the certification
is provided to the supervising RPEQ by Council officers.
97. Prescribed Water Contaminants (as defined in Schedule 10 of Environmental Protection
Regulation 2019) must not be released from the site or to waters within the site, or be
likely to be released should rainfall occur, unless all reasonable and practicable
measures are taken to prevent or minimise the release and concentration of
contamination.
98. Sediment and erosion control measures must be in place prior to works commencing. If
such measures are not in place or are not satisfactory, “on the spot” fines may be issued.
Such fines can be issued if sediments from the site are found to enter or have the
potential to enter Council’s stormwater system, natural waterways, any downstream
stormwater filtration system or adversely impacting on other properties. The sediment
and erosion control design and measures have NOT been approved, it is the site's
Supervising Engineer who is responsible for ensuring that the sediment and erosion
control measures have:
a. Been duly designed by an RPEQ or CPESC and constructed in accordance with
"best practise" methods;
14
Section 17
b. Been revised by an RPEQ or CPESC to address the issues raised by changes in
the projected construction schedule and/or methods;
c. Been revised to address predicted rainfall events, and
d. Achieve the desired environmental outcomes.
99. Council may request further controls to be installed should the implemented measures
be found inefficient.
100. The erosion and sediment control measures must be designed, installed and maintained
in accordance with the supervising engineer instructions and the current best practice
standards * (Refer to Advisory Note).
101. The developer must ensure non-essential exposure of soil is prevented by restricting the
extent of disturbance and minimising the duration of soil exposure to adverse weather
conditions and effectively turf, cover or stabilise any disturbed area without delay and
prior to rainfall occurring.
102. The developer in conjunction with the engaged CPESC must ensure measures installed
to divert the upstream water are designed and certified by the supervising RPEQ and
installed prior to commencement of bulk earthworks.
103. The developer must ensure sediment does not leave the site or enter onto adjoining
properties or Council’s drainage system due to surface runoff or on tyres of vehicles
and/or machinery. It is essential to implement appropriate approved erosion and
sediment control measures throughout the site during all phases of construction
including vehicle shakedown pad/grid (or similar) at the access to the construction site.
Where sediments or other contaminants are deposited on a road, they must be removed
so as not to enter Council’s drainage system or waterways.
104. Prior to the completion of the development, all site surfaces must be effectively
stabilised. For the purpose of this condition, an effectively stabilised surface is defined
as one that does not, or is not likely to result in visible evidence of soil loss caused by
sheet, rill or gully erosion or lead to sedimentation, or lead to water contamination.
Water Sensitive Design
105. The active filter media of the bioretention device must be 27m². Active filter media area
is the area of the bioretention basin surface that is not covered by any impermeable
structure such as a sediment forebay, riser, etc.
106. During construction and establishment of the bioretention devices, the supervising
RPEQ must certify forms contained in section 3.15 of the Construction and
Establishment Guidelines: Swales, Bioretention Systems and Wetlands (Water by
Design, 2009). These forms and certification must be submitted to council prior to the
sealing of the survey plan.
107. A construction hold point with a council delegate must be established once the
bioretention device underdrainage pipe work is installed. At the time of inspection, a
sample of the drainage layer, transition layer, and filtration media materials must be
stockpiled onsite accompanied by laboratory results that demonstrate that the media
complies with the specifications contained in the latest version of the Guidelines for Soil
Filter Media in Bioretention Systems (Facility for Advancing Water Biofiltration) and that
the minimum hydraulic conductivity of 180mm/hr or as specified on the approved
engineering plans will be achieved. The drainage layer, transition layer, and filtration
media materials shall not be installed until the catchment draining to the bioretention
device has 80% groundcover as determined by council’s delegate.
108. Eighty percent (80%) of the catchment flowing to the bioretention basin must be
effectively stabilised prior to the construction holdpoint for the Bioretention device.
15
Section 18
109. Prior to the release of the plan of survey, the supervising RPEQ must certify must certify
that all hardstand areas of the development drain to a bioretention device designed and
constructed in accordance with all relevant conditions of this approval, the Water by
Design Bioretention Technical Design Guidelines, relevant aspects of the IPWEAQ
Standard Drawing WSUD-drawing series and Construction and Establishment
Guidelines: Swales, Bioretention Systems and Wetlands (Water by Design, 2009).
Bioretention Devices - Landscaping
110. Landscape plans must include a mixture of at least five of the following species for
planting in the bioretention basin extended detention surface at a minimum density of 8
plants/m2:
e. Carex appressa
f. Carex fascicularis
g. Ficinia nodosa
h. Juncus usitatis
i. Lomandra longifolia
j. Ghania sieberiana
111. Landscape plans for the areas surrounding the bioretention basin filter media footprint
must be arranged to minimise shading to the filter media footprint are. Suitable plants
include the following:
k. Carex appressa
l. Carex fascicularis
m. Ficinia nodosa
n. Juncus usitatis
o. Lomandra longifolia
p. Ghania sieberiana
q. Banksia robur
r. Dianella brevipendunculata
s. Themada triandra
t. Cymbopogan refractus
u. Melaleuca thymifolia
112. Where landscaping/garden beds are proposed adjacent to the bioretention basin, or
where the basin is located adjacent to naturally forested areas, a 900mm deep root
barrier must be installed to the interface between the landscape/garden/forest area and
the bioretention basin to prevent root intrusion to the biobasin infrastructure.
113. Landscaping to the surface of the bioretention basin filter media area must not
commence until 80% of building work within each contributing catchment is complete or
after 3 years, whichever occurs first. An uncompleted works bond of 150% of the value
of the planting to the surface of the bioretention basin filter media area must be provided
to Council prior to the release of the Plan of Survey.
114. Where required, mulch within the batters of bioretention basins must be installed in a
manner that it will not escape into receiving stormwater drainage infrastructure or water
courses.
16
Section 19
Bioretention Devices - Education
115. The development shall be provided with approved permanent signage that is
deigned in accordance with Noosa’s Look and Feel document to educate the
public on the function of the bioretention basin. The wording for the signage for
each bioretention basin is to include: “BIORETENTION BASIN - This bioretention
basin reduces the pollution of our waterways by reducing the amount of heavy
metals, litter, suspended solids, and nutrients discharged to Lake Doonella”.
FOLLOWING CONSTRUCTION / PRIOR TO THE ON-MAINTENANCE INSPECTION
Certification
116. Upon completion of the work a certificate must be issued by an RPEQ certifying
that the works have been constructed in accordance with the Operational Works
permit.
117. A condition report of the drainage system must be completed for agreement prior
to requesting the works to be accepted On-Maintenance. The condition report is
to include a CCTV inspection of the existing pipe and must include at least 50m
upstream and downstream of all works.
As Constructed Plans and ADAC XML Files (Council)
118. Prior to acceptance of civil works to become Council assets “On Maintenance”,
satisfactory “As-Constructed” records must be submitted to Council. The bundle
of “As Constructed” information must include:
v. As-Constructed Engineering Drawings. Data is to be submitted in an
electronic drawing file format (.dwg), with all plans clearly endorsed “As-
Constructed”, along with the accompanying hardcopies (PDFs of the As-
Constructed .dwg drawing files), and;
c. ADAC XML Digital File. ADAC File format (ADAC - Asset Design As
Constructed) prepared in accordance with industry standards and recorded
in “MGA - UTM56 / GDA94” projection.
d. Please Note: Further information and advice relating to the as-constructed
drawing presentation, as-constructed survey capture and associated
guidelines for preparation of a compliant ADAC XML digital file are available
on the webpage titled “As-Constructed Guidelines” and accessible at the
Noosa Council Website: Planning & Development / Development Tools &
Guidelines / As-Constructed Guidelines.
e. The “As-Constructed” drawings will require certification by a:
i. Qualified experienced Civil Engineer (RPEQ) confirming design
intent and conformance with applicable standards and
specifications, along with the relevant descriptions of assets,
services and structures and;
ii. Licensed Surveyor in regard to the cadastral and locational
information, levels and applicable survey datum.
f. The data must be in accordance with Council’s “Planning Scheme Policy 6
– Engineering Design Standards”, and fully detail the levels for all
engineering works including but not limited to the drainage network and
structures, finished ground and pavement surface levels.
17
Section 20
On Maintenance
119. All municipal works must be accepted ‘On Maintenance’ by Council in accordance
with Council’s relevant Planning Scheme Policy prior to the On-Maintenance
inspection. To achieve ‘On Maintenance’, the supervising RPEQ must submit to
Council:
a. certification that all works have been undertaken and completed in
accordance with the requirements of this Permit;
b. as Constructed details in accordance with Council’s Planning Scheme
Policy;
c. maintenance and operational manuals for all proprietary or site specific
devices.
Off Maintenance
120. Prior to requesting an Off Maintenance inspection the developer must provide a
written request for the Off Maintenance inspection.
121. A re-inspection fee in accordance with Council’s Fees and Charge Register will be
charged where:
a. a Council inspection reveals works do not comply with approval
requirements;
b. submitted certification falsely states works comply with approval
requirements.
5. ADVISORY NOTES
The following notes are included for guidance and information purposes only and do not form
part of the assessment manager conditions:
1. All developments and/or changes to existing developments may require payment of
“Infrastructure Charges” (as applicable) in accordance with Council’s “Charges
Resolution” made pursuant to the planning legislation and regulations current at the time
of issue.
6. REFERRAL AGENCIES
Not Applicable.
7. SUBMISSIONS
Not Applicable
8. FURTHER DEVELOPMENT PERMITS REQUIRED
Type of Development Permit Required Subject of the required Development Permit
Development Permit for Building Works All building works
18
Section 21
C:\Users\User\Archicology Pty Ltd\Archicology - Projects
\Archicology Projects\20531 Tewantin 40 x 40\20531 SD model
\20531 SD MODEL scheme B.pln
SD ISSUE
DRAFT A by NF on 27/07/20 for Review
ISSUE 1 by NF on 31/07/20 for Consultation
ISSUE 2 by NF on 14/10/20 for SCHEME B
ISSUE 3 by NF on 27/11/20 for Consultants
ISSUE 4 by NF on 18/12/20 for Approval
ISSUE 5 by NF on 22/12/20 for ISSUE
ISSUE 6 by NF on 12/01/21 for rev. data
ISSUE 7 by NF on 21/01/21 for DA Submission
ISSUE 8 by NF on 01/02/21 for Bins + SW Pathway
ISSUE 9 by NF on 23/04/21 for NC RFI
ISSUE 10 by NF on 14/05/21 for NC RFI
ISSUE 11 by NF on 31/05/21 for NC RFI
ISSUE 12 by NF on 06/07/21 for drawing index
90° 00' 15" 8
40·532 N
359° 39' 40"
Proposed
Proposed 3m3m Access Easement
25·146
Access Easement
8,510
5,510
8,506
N
3,093
1.520
0.190
0.250
Tread width:
Riser:
Total rise:
24 25 25 24
2,788
Tread width:
Riser:
Total rise:
1.450
0.181
0.250
23 26 26 23
22 27 27 22
21 21
20 13 13 20
Tread width:
19 19
Total rise:
14 14
18 18
Riser:
0.250
0.181
1.450
15 15
17 16 16 17
Tread width:
Total rise:
Riser:
0.250
0.180
0.181
1.440
1.450
awning above
Proposed
Residential Units
16
15
14
13
12
11
10
9
8
7
6
5
4
7
8
2,495
Site Location Plan
1
NTS
90° 00' 15" 3,496
20·519
DEVELOPMENT SUMMARY
3,260
17,990 3,000 15,550 3,350 14,900
PROPERTY DESCRIPTION
RPD Lot 903 on T1631 &
LOT 32 LOT 903
179° 39' 40"
Lot 32 on RP893427
Drawing Index
25·160
SITE AREA TOTAL 2,539m2 BIO-RETENTION
BASIN
PARISH Noosa DWG # Drawing Name Issue Date
359° 39' 40"
COUNTY March 6
25·160
SD01
DD19 Site Plan
Notes 13 08/07/21
LOCAL AUTHORITY Noosa Shire Council
Proposed SD02 Ground / Carpark Plan 12 08/07/21
GROSS FLOOR AREA Proposed Proposed SD03 Level 1 Plan 10 31/05/21
Residential Units
Residential Residential Units Residential Units SD3A LHA - SDA COMPLIANC... 2 14/05/21
Proposed No. of Units 19 SD04 Level 2 Plan 6 23/04/21
Proposed Total GFA Residential 1514.00m2
7 SD06 Roof Plan 6 23/04/21
Commercial SD07 Areas - Ground / Carpark 12 08/07/21
Proposed Total GFA Commercial 188.00m2
FIRE SD08 Areas - Level 1 8 14/05/21
LANDSCAPING Proposed Commercial Proposed Commercial Proposed Commercial SD09 Areas - Level 2 6 23/04/21
3,500
Required 10% of Site Area 254.00m2 5 SD10 Elevations 10 08/07/21
9,410
9,390
9,240
5,000
Proposed 808.22m2 SD11 Elevations 10 08/07/21
Carpark
Carpark
FIRE
Entry
6,150
6,150
6,150
6,150
Exit
SD12 Sections A, B 7 23/04/21
5,150
5,000
PARKING
SD13 Sections C, D 7 14/05/21
Carparking Spaces Required 30 Cars
1,900
Carparking Spaces Proposed 33 Cars 270° 00' 40" 270° 00' 40" 4,000
SD14 3D Impression 01, 02 10 08/07/21
20·519 6 40·234 5 SD15 3D Impression 03, 04 9 08/07/21
Motorcycle Spaces Required 12 Motorbikes
SD16 3D Impressions 05, 06 6 23/04/21
Motorcycle Spaces Proposed 12 Motorbikes stree tree to be stree tree to be
removed. replace with stree tree to be
removed. replace with removed. replace with SD17 3D Impression 07 6 23/04/21
Bicycle Spaces Required 14 Bicycles new street tree new street tree new street tree
stree tree to be
Bicycle Spaces Proposed 7 Bicycles removed. new street
NOTE: this drawing set is documented with survey plans from in 2011.
There may be very minor anomalies when compared against a more
tree in SE corner
accurate and recent survey.
WASTE MANAGEMENT Pedestrian Crossing
General Waste
ARCHICOLOGY P/L
2.28 (Residential) + 0.13 (Commercial) = 2.41m3 Required
1.1m3 + 1.1m3 + 1.1m3 (Bulk Bins) = 3.3m3 Provided
architecture
Recycle Waste
2.28 (Residential) + 0.14 (Commercial) = 2.42m3 Required
about people
1.1m3 + 1.1m3 + 1.1m3 (Bulk Bins) = 3.3m3 Provided Site Plan
2 ph 5446 3113
1:200 Po Box 579 Coolum Beach 4573
PRIVATE OPEN SPACE
Unit / Tennancy GFA The builder shall check and verify all dimensions and
Balcony Garden Courtyard Beds Bath Carparks Tot living Carparks Storage Total verify any errors and omissions to the architect. Do not
Unit 1 81 22 10 15 2 2 1 128 30 5 163 scale off drawings. Drawings shall not be issued for
2 81 20 13 17 2 2 1 131 20 5 156 construction purposes until issued by the Architect for
3 81 20 13 17 2 2 1 131 13 5 149 construction. In the first instance contact :
4 81 20 13 17 2 2 1 131 15 5 151 Mr Adrian Just on 0412 117772
5 81 22 10 18 2 2 1 131 27 5 163
6 81 22 10 0 2 2 1 113 32 5 150
7 81 20 13 0 2 2 1 114 18 5 137 Client Name
8 81 20 13 0 2 2 1 114 13 5 132
9 81 20 13 0 2 2 1 114 14 5 133
Project Name
10 81 22 10 0 2 2 1 113 35 5 153
11
12
79
74
16
16
3
0
0
0
2
2
2
2
1
1
98
90
15
15
5
5
118
110
Tewantin 40 x 40
SCHEME B : 2 LEVELS : 19 UNITS
13 71 12 0 0 2 1 1 83 15 5 103
14 80 16 0 0 2 2 1 96 15 5 116 30 & 32 Doonella St, Tewantin QLD, 4566
15 75 12 0 0 2 1 1 87 15 5 107
16 70 16 10 0 2 2 1 96 15 5 116
17 69 16 6 0 2 1 1 91 15 5 111
Drawing Title:
18 89 12 8 0 2 2 1 109 15 5 129
19 98 14 0 0 3 2 2 112 30 17 159 Site Plan
Unit Total 1515
Commercial 1 51 3 45 96
Commercial 2 40 2 30 70 Scale: As shown Date: 2020
Commercial 3 55 3 45 100
Commercial 4 42 2 45 87 Status: SD Checked By: ACJ
Commercial Total 188
Commercial Project No: Drawing No.:
12
Amenities
Site Total 1715 338 145 84 39 35 30 2082 532 107 2909 20531 SD01
19 Plot Date: 8/07/2021
Section 22
C:\Users\User\Archicology Pty Ltd\Archicology - Projects
2,000
13,250 1,000
35,800
7,200 1,000
8
12,550 200
\Archicology Projects\20531 Tewantin 40 x 40\20531 SD model
C
\20531 SD MODEL scheme B.pln
D
200 1,800 200
200
2,500
1,900 200
200
4,300 5,900 5,000
30,000
150
500
150 5,000 5,900 5,400
200 2,500
200
200
N SD ISSUE
34,600 DRAFT A by NF on 27/07/20 for Review
ISSUE 1 by NF on 31/07/20 for Consultation
ISSUE 2 by NF on 14/10/20 for SCHEME B
ISSUE 3 by NF on 27/11/20 for Consultants
ISSUE 4 by NF on 18/12/20 for Approval
ISSUE 5 by NF on 22/12/20 for Stormwater DT
ISSUE 6 by NF on 12/01/21 for rev. motorbikes
ISSUE 7 by NF on 21/01/21 for DA Submission
ISSUE 8 by NF on 01/02/21 for Bins + SW Pathway
ISSUE 9 by NF on 23/04/21 for NC RFI
200 1,660
D.P
D.P
ISSUE 10 by NF on 14/05/21 for NC RFI
ISSUE 11 by NF on 06/07/21 for NC RFI
Residential Building Above
Residential Building Above
ISSUE 12 by NF on 08/07/21 for NC RFI
200
200
200
200
200
200
200
STORE STORE STORE STORE STORE STORE STORE STORE STORE STORE STORE STORE
Walkway Above
540
Unit 12 Unit 11 Unit 10 Unit 9 Unit 8 Unit 7 Unit 6 Unit 5 Unit 4 Unit 3 Unit 2 Unit 1
1,800
2,800
13.3m3 13.3m3 13.3m3 13.3m3 13.3m3 13.3m3 13.3m3 13.3m3 13.3m3 13.11m3 13.3m3 13.3m3
2,800
spoon drain spoon drain
A RL 5.7 RL 5.7 A
1,000
13,450
5,290
exit path from fire stair
Carpark Signage Key
5,100
BLIND ISLE BLIND ISLE
at ground level
user Class 1A
user Class 1A
user Class 1A
user Class 1A
AS2890.1
AS2890.1
AS2890.1
AS2890.1
UNIT 19
UNIT 3
UNIT 7
UNIT 1
2,400
2,400
P23
P15
P7
2,840
P1
9,700
Class 1A - Residential
9,500
9,500
UNIT 15
P22
user Class 1A
user Class 1A
user Class 1A
user Class 1A
60
AS2890.1
AS2890.1
AS2890.1
AS2890.1
UNIT 19
300 1,960
UNIT 4
UNIT 8
UNIT 2
2,400
2,400
P24
P16
2,550
P8
P2
spoon drain
13,850
Class 1A - Residential
2,950
VISITOR
VISITOR SMALL CAR 3,095
140
300
300
P22 P22
1,100
user Class 1A
user Class 1A
AS2890.1
AS2890.1
UNIT 5
UNIT 9
WATER SUB-METER WATER SUB-METER
P17
Class 3 - Commercial
P9
2,400
2,140 ASSEMBLY
MBP 8
ASSEMBLY D.P
'LOGO' MBP 1
7