Appendix F - Bushfire Hazard Assessment and Managment Report
Bushfire Hazard Assessment
Bushfire Management Report
Project No: B6138
220 Black Mountain Range Rd Black Mountain
Address:
QLD 4563
Lot Plan: Lot 3 SP 258991
Local Government Area: Noosa Shire Council
Proposed Development: Reconfiguring a lot (one (1) lot into five (5) lots)
Maximum Radiant Heat Flux: Less than 29 kW/m2
Compliance with Bushfire Hazard
Complies
Overlay Code:
Max Bushfire Protection Consulting / ABN 81 671 088 887
Suite 1605 17 Gould Rd Herston QLD 4006 / PO BOX 186 Toowong DC QLD 4066
Mobile: 0432 89 82 82 / Email: [email protected]
www.maxbp.com.au
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take up to a minute.
Full text of the other 62 pages
Page 2
Bushfire Report Document History Version Description Date Author Approved by 1.0 Report - Draft 26/2/2026 LL, HL HL 2.0 Report - Final 28/4/2026 LL, HL HL 2.1 Report - Final 22/6/2026 LL, HL HL Report Expiry Please be aware that the bushfire hazard assessment and BAL rating provided in this report are valid for 12 months from the date of issuance. It is advisable to consult with a qualified professional to confirm the accuracy of the assessment if this report is more than 12 months old. If any discrepancies are identified or if an update is necessary, a new report should be obtained. Copyright Statement The contents of this document are the exclusive property of Max Bushfire Protection Consulting and are protected by copyright and other intellectual property laws. This document is intended solely for the use of the client and regulatory agencies involved in the project. Any reproduction or distribution, in whole or in part, without the prior written consent of the copyright holder, is strictly prohibited and may constitute a violation of copyright law. This report is provided for the specific purpose of the project at hand and may not be used for any other purpose without the express written consent of the author. Individuals are required to maintain all copyright and other notices contained within the materials. Unauthorized distribution of copies, whether in electronic or physical form, is prohibited without the prior written consent of the copyright holder. Disclaimer This report has been prepared based on information provided by the client and is intended solely for the client's exclusive use for the stated purpose for which it was provided. Any inaccuracies or amendments to the report or development application will require revision. Please note that, despite our best efforts, there is no guarantee that desirable outcomes are achievable during extreme bushfire weather episodes, which may result in unpredictable bushfire behavior and detrimental consequences to life, property, and the environment. Any representation, statement, opinion, or advice expressed or implied in this report is made in good faith. Max Bushfire Protection Consulting and its employees will not be liable (whether by reason of negligence, lack of care, or otherwise) to any person for any damage or loss whatsoever that may occur in relation to that person taking or not taking action in respect of any representation, statement, or advice referred to in this report. Legislation may impact vegetation clearing activities. It is strongly recommended that clients contact the relevant agencies to determine if their proposed vegetation clearing activity complies with local, state, and federal laws. Max Bushfire Protection Consulting 2
Page 3
Bushfire Report
Practitioner Declaration
Name: Henry (Hongxi) Liang
Position: Senior Bushfire Consultant
I hereby certify that I have undertaken the assessment of the above-mentioned
site and determined the Bushfire Attack Level stated above in accordance with the
requirements of AS 3959:2018 and/or the Bushfire Resilient Communities -
Technical Reference Guide published by Queensland Fire and Emergency
Services.
I hereby declare that I am a suitably qualified bushfire consultant, holding AQF
Level 8 qualifications and tertiary degrees below:
▪ Graduate Diploma in Bushfire Protection
▪ Graduate Certificate in Bushfire Protection
▪ Master of Business Administration
▪ Bachelor in Engineering
Signature:
Email: [email protected] Max Bushfire Protection Consulting
Mobile: 0432898282 ABN: 81 671 088 887
Max Bushfire Protection Consulting 3
Page 4
Bushfire Report
Table of Contents
Executive Summary .............................................................................................................. 7
1. Introduction .................................................................................................................... 8
1.1 Purpose ...................................................................................................................... 8
1.2 Subject site................................................................................................................. 8
1.3 The proposed development ........................................................................................ 8
1.4 Bushfire Prone Land ................................................................................................... 9
1.5 Scope and objectives ................................................................................................. 9
2. Assessment Methodology ............................................................................................ 11
2.1 Desktop Assessment and Legislative ....................................................................... 11
2.2 Bushfire Hazard Assessment ................................................................................... 11
2.3 Bushfire Attack Level Assessment............................................................................ 12
3. Legislative Context....................................................................................................... 13
3.1 State Planning Policy (July 2017) ............................................................................. 13
3.2 National Construction Code 2022: Building Code of Australia .................................. 13
3.3 AS 3959:2018 Construction of Buildings in Bushfire-Prone Area .............................. 14
3.4 Noosa Shire Council Planning Scheme .................................................................... 14
4. Bushfire Hazard Assessment ....................................................................................... 15
4.1 Current Bushfire Hazard Mapping ............................................................................ 15
4.2 Local FFDI................................................................................................................ 15
4.3 Fire History ............................................................................................................... 16
4.4 Site-Specific Hazard Assessment ............................................................................. 16
4.4.1 Ground Truthed VHC ....................................................................................... 18
4.4.2 Vegetation Conditions within the proposed development ................................. 21
4.5 Probable Direction of Bushfire Attack ....................................................................... 29
4.6 Radiant Heat Flux Modelling..................................................................................... 29
4.7 Building Envelope and Asset Protection Zone .......................................................... 30
4.8 Bushfire Attack Level and Construction Requirements ............................................. 30
5. Bushfire Management Plan .......................................................................................... 34
5.1 Bushfire Behaviours ................................................................................................. 34
5.1.1 Topography ..................................................................................................... 34
5.1.2 Weather Conditions ......................................................................................... 34
5.1.3 Vegetation ....................................................................................................... 35
5.2 Potential Bushfire Impacts and Attack Mechanisms ................................................. 35
5.2.1 Direct Flame Contact ....................................................................................... 36
5.2.2 Radiant Heat Exposure .................................................................................... 36
Max Bushfire Protection Consulting 4
Page 5
Bushfire Report
5.2.3 Ember Attack ................................................................................................... 37
5.2.4 Wind and Smoke Attack................................................................................... 37
5.2.5 Convection and Conduction ............................................................................. 37
5.3 Bushfire Protection Measures................................................................................... 37
5.3.1 Asset Protection Zone (APZ) ........................................................................... 38
5.3.2 Building Construction, Siting and Design ......................................................... 41
5.3.3 Access and Evacuation Arrangement .............................................................. 42
5.3.4 Water Supply ................................................................................................... 42
5.3.5 Landscaping Management Plan ....................................................................... 43
5.3.6 Reducing Fuel load and Weed Management ................................................... 43
6. Conclusion ................................................................................................................... 45
7. References .................................................................................................................. 46
8. Appendix...................................................................................................................... 46
Max Bushfire Protection Consulting 5
Page 6
Bushfire Report
Acronyms and Abbreviations
APZ Asset Protection Zone
AEP Annual Exceedance Probability
Australian Standard 3959:2018 Construction of Buildings in Bushfire-
AS 3959:2018 Prone Areas (This Standard incorporates Amendment No. 1 (June
2019) and Amendment No. 2 (December 2020))
BCA Building Code of Australia
BPA Bushfire Prone Area
BMP Bushfire Management Plan
BVG Broad Vegetation Group
FDI Fire Danger Index
FFDI Forest Fire Danger Index
FWS Fire Weather Severity
IMS Interactive Mapping System
LMP Landscape Management Plan
MCU Material Change of Use
NCC National Construction Code
QFES Queensland Fire and Emergency Services
RH Relative Humidity
RAL/ROL Reconfigure A Lot/Reconfiguration of Lot
SPP State Planning Policy 2017
SPP map input Statewide Map of Bushfire Prone Areas Input Data E.G. FFDI (5%
data AEP), Maximum Landscape and Vegetation Hazard Class
VHC Vegetation Hazard Class
VMP Vegetation Management Plan
Max Bushfire Protection Consulting 6
Page 7
Bushfire Report
Executive Summary
Project No: B6138
Site-specific bushfire hazard assessment
Type of bushfire
Bushfire attack level assessment
assessment:
Bushfire management plan
220 Black Mountain Range Rd Black Mountain QLD 4563
Location:
Lot 3 SP 258991
Site area: 228,500 sqm
Local Government
Noosa Shire Council
Area:
Threedom Nominees Pty Ltd ACN 670 892 994 atf The
Client(s):
SCB NO 2 Trust
Proposed
Reconfiguring a lot (one (1) lot into five (5) lots)
Development:
Site plan by: The Client(s)
Asset Protection
Designed APZ as Bushfire Management Area
Zone:
Maximum Radiant
Less than 29 kW/m2
Heat Flux:
Compliance with
Bushfire Hazard Complies
Overlay Code:
Max Bushfire Protection Consulting 7
Page 8
Bushfire Report
1. Introduction
1.1 Purpose
Max Bushfire Protection Consulting was engaged by the client(s) to conduct a site-
specific bushfire hazard assessment for the proposed development on the subject
site.
The objective of this report is to assess the potential bushfire hazard and related
risks concerning the proposed development, aligning with several regulatory
frameworks such as the Queensland State Government State Planning Policy - Part
E (SPP 2017), the Bushfire Resilient Communities Technical Reference Guide
(QFES, 2019), the local council planning scheme - bushfire hazard overlay code,
and the Australian Standard – Construction in Bushfire Prone Areas (AS 3959:2018).
These guidelines delineate the State and Council's concerns regarding bushfire
hazard within the context of evaluating development applications.
The development shall be carried out on the lot referred to as the ‘Subject Site,’ and
the dwelling shall be situated within the proposed building location envelope.
1.2 Subject site
• Site Address: 220 Black Mountain Range Rd Black Mountain QLD 4563
• Lot Plan: Lot 3 SP 258991
• Site Area: 228,500 sqm
1.3 The proposed development
The proposed development seeks a Development Permit for Reconfiguring a Lot,
involving the subdivision of one (1) lot into five (5) lots.
The existing dwelling will remain on the proposed Lot 3. The proposed Lot 1, Lot 2,
Lot 4 and Lot 5 will provide a suitable building area for the future construction of a
new Class 1a dwelling.
Suitable access driveways will be provided for all lots from Black Mountain Range
Road.
Max Bushfire Protection Consulting 8
Page 9
Bushfire Report
Figure 1-1: Subject Site
1.4 Bushfire Prone Land
The Council's designation of land as "bushfire prone" carries two primary
consequences:
• It mandates the formulation of a Bushfire Management Plan that conforms to
the specifications delineated in the Planning Scheme. This includes strict
adherence to the Bushfire Overlay Code stipulated within the planning
scheme.
• It activates the application of the Building Code of Australia (BCA) and the
National Construction Code (NCC), necessitating compliance with their
performance objectives pertaining to bushfire mitigation. Furthermore,
adherence to AS 3959:2018, which governs the construction of buildings in
bushfire-prone regions, is imperative.
1.5 Scope and objectives
The scope and objectives of this assessment are to:
• Identify bushfire-related risk factors linked to the positioning of the
development footprint. This includes the probable direction of bushfire attack,
hazard ratings associated with existing and proposed vegetation on and
around the subject site, and planning separation from potential hazards.
• Recommend suitable protective measures to alleviate the risk posed by the
assessed BAL in alignment with the State Planning Policy (SPP 2017), AS
Max Bushfire Protection Consulting 9
Page 10
Bushfire Report
3959:2018, and the Bushfire Hazard Overlay Code of the Council Planning
Scheme.
• Prepare a comprehensive site-specific bushfire management plan and
conduct an assessment of compliance with the Bushfire Hazard Overlay Code
to illustrate how adherence can be attained.
Max Bushfire Protection Consulting 10
Page 11
Bushfire Report
2. Assessment Methodology
2.1 Desktop Assessment and Legislative
A desktop assessment and legislative review was conducted to identify overlay
mapping and requirements under the SPP 2017 and Noosa Shire Council planning
scheme. The review included:
▪ Planning Act 2016 (Planning Act)
o Planning Regulation 2017 (Planning Regulation)
o State Planning Policy (SPP 2017) mapping
o State Assessment and Referral Agency (SARA) mapping (Department
of Infrastructure, Local Government and Planning)
▪ Noosa Shire Council Planning Scheme
o Bushfire Hazard Overlay Code
o Planning Scheme interactive mapping
▪ Queensland FIRE and Emergency Services
o Catalyst interactive mapping
▪ Building Act 1975 (Building Act)
▪ National Construction Code 2022: Building Code of Australia (NCC 2022)
▪ AS 3959:2018 Construction of Buildings in Bushfire-Prone Areas
2.2 Bushfire Hazard Assessment
A site-specific bushfire hazard assessment aims to identify and understand the
bushfire hazards on the site. The site's vegetation and terrain characteristics were
surveyed using a complete site examination, aerial photography, accessible
databases, and relevant mapping. The site-specific assessment included:
• Recording the structure, composition, and condition of vegetation
communities located in the development footprint and all land within 100m of
the development footprint, extending to 150m-300m where necessary.
• Assessing site slope and effective slope.
• Determining the aspect of the site.
• Identifying waterway and wetland features within the assessment area.
• Calculating potential fire line intensity and Radiant Heat Flux.
Utilizing the recorded outcomes of the field survey, a Bushfire Hazard Assessment
and subsequent BAL review were conducted in accordance with the Bushfire
Resilient Communities Technical Reference Guide for the State Planning Policy
State Interest ‘Natural Hazards, Risk and Resilience – Bushfire’ (QFES 2019), which
was prepared by the Queensland Fire and Emergency Services to provide technical
guidance for the SPP 2017 guidance material. The method involves a quantitative
assessment of the vegetation communities, fuel loads, slope, and other relevant
factors.
Max Bushfire Protection Consulting 11
Page 12
Bushfire Report
2.3 Bushfire Attack Level Assessment
The determination of the site-specific Bushfire Attack Level (BAL) for the
development footprint and classified vegetation was undertaken in accordance with
the Bushfire Resilient Communities – SPP Technical Reference Guide and AS
3959:2018. This includes the identification of the following input values:
• FFDI (5% AEP fire weather event)
• Vegetation hazard class, surface and overall fuel load
• Site slope, effective slope, and whether the effective slope is upslope or
downslope of the development
• Distance of the development footprint from classified vegetation
Radiant heat exposure was calculated using the Bushfire Asset Protection Zone
calculator provided by the Sustainable Development Unit of Queensland Fire and
Emergency Services and/or the AS 3959:2018 Method 2 Calculator.
AS 3959:2018 defines the Bushfire Attack Level as a method for measuring the
severity of a building's potential exposure to ember attack, radiant heat, and direct
flame contact, using increments of radiant heat expressed in kilowatts per square
meter. This method serves as the basis for establishing construction requirements to
improve the protection of building elements from bushfire attack. Consequently, the
assessment results and accompanying BAL construction requirements only apply to
proposed buildings or structures, not the entire development area.
Max Bushfire Protection Consulting 12
Page 13
Bushfire Report
3. Legislative Context
The following key legislation, policies and guidelines are relevant to the preparation
of bushfire assessment:
• State Planning Policy (July 2017, QLD)
• National Construction Code 2022
• AS 3959:2018 Construction of Buildings in Bushfire-Prone Areas
• Local Council Planning Scheme
• Planning Act 2016 (Planning Act) and Building Act 1975 (Building Act)
3.1 State Planning Policy (July 2017)
Supporting the Planning Act 2016 (Planning Act) (Qld), the purpose of the SPP is to
guide State and Local government in land-use planning and development by defining
the Queensland Government’s polices about matters of state interest, to which there
are 17 state interests arranged under five broad themes:
• liveable communities and housing
• Economic growth
• Environment and heritage
• Safety and resilience to hazards
• Infrastructure
The SPP Interactive Mapping System includes bushfire hazard area (bushfire prone
area) mapping based on the methodologies outlined in Leonard et al. (2014). Under
the safety and resilience to hazards theme, the state's interest is to ensure that
natural hazards are properly considered in all levels of the planning system. This
includes the avoidance of natural hazard areas or the mitigation of risks to an
acceptable or tolerable level. The SPP is supported by the SPP – State Interest
Guideline – Natural Hazards, Risk and Resilience (April 2016), Technical Manual –
Evaluation Report: Bushfire Hazards (April 2016), and Technical Manual – A 'Fit for
Purpose' Approach in Undertaking Natural Hazard Studies and Risk Assessments
(April 2016) by the Department of Infrastructure, Local Government and Planning.
These documents identify the outcomes sought by the state and their application
when planning development within a bushfire hazard area (bushfire prone area).
3.2 National Construction Code 2022: Building Code of Australia
The National Construction Code 2022: Building Code of Australia (NCC 2022) sets
out technical requirements for the design and construction of buildings and other
structures in Australia (The Australian Building Codes Board). NCC 2022 defines ten
core building classes, along with various subclasses. It mandates that buildings
constructed within designated bushfire prone areas must be designed and
constructed to minimize the risk of ignition from bushfires.
Max Bushfire Protection Consulting 13
Page 14
Bushfire Report
3.3 AS 3959:2018 Construction of Buildings in Bushfire-Prone Area
Where development is proposed in designated bushfire prone areas, AS 3959:2018
provides construction requirements designed to enhance resistance against bushfire
attack. These construction specifications are determined by specific heat flux
exposure thresholds and are categorized into six Bushfire Attack Levels (BAL):
Radiant Heat
Bushfire Attack Level Description of Predicted
Exposure
(BAL) Bushfire Attack and Levels of exposures
(AS3959:2018)
Minimal attack from radiant heat and flame due to
the distance of the building from the vegetation,
BAL – Low Insignificant
although some attack by burning debris is possible.
There is insufficient threat to warrant specific
construction requirements
Attack by burning debris is significant with radiant
heat (not greater than 12.5kW/m²). Radiant heat is
BAL - 12.5 0 to 12.5kW/m2 unlikely to threaten building elements (such as
unscreened glass). Specific construction
requirements for ember protection and accumulation
of debris are warranted.
Attack by burning debris is significant with radiant
heat flux (not greater than 19kW/m²) threatening
BAL - 19 12.5 to 19kW/m2
some building elements (such as screened glass).
Specific construction requirements for embers and
radiant heat are warranted.
Attack by burning debris is significant and radiant
2 heat flux (not greater than 29kW/m²) threatens
BAL – 29 19 to 29kW/m
building integrity. Specific construction requirements
for ember and higher levels of radiant heat are
warranted. Some flame contact is possible.
BAL – 40 29 to 40kW/m2 Radiant heat flux and potential flame contact could
threaten building integrity.
40kW/m2 plus Significant radiant heat and significantly higher
BAL - FZ likelihood of flame contact from the fire front will
(Flame Contact) threaten building integrity and result in significant
risk to residents.
Table 1: AS3959:2018 Using BAL to determine construction requirements
3.4 Noosa Shire Council Planning Scheme
The Bushfire Hazard Overlay, under the Council’s Planning Scheme reflects SPP
State and Local level interests by identifying designated bushfire prone areas. Where
assessable development is proposed on land mapped as containing bushfire hazard
areas, a site-specific bushfire hazard assessment prepared in accordance with the
planning scheme is required.
Max Bushfire Protection Consulting 14
Page 15
Bushfire Report
4. Bushfire Hazard Assessment
Several factors determine the likelihood and severity of bushfires in a landscape.
Key factors include the type of vegetation and the amount of available fuel. Other
considerations are topography and land use patterns around potentially hazardous
vegetation. Additionally, connectivity between vegetation communities can influence
the development and persistence of bushfires.
4.1 Current Bushfire Hazard Mapping
A review of the Bushfire Hazard Overlay Mapping indicates that the site contains
bushfire hazard areas, as shown in Figure 4-1.
Figure 4-1: Bushfire Hazard Overlay Mapping
4.2 Local FFDI
The fire season in Queensland typically begins in the far north in July, advancing
southward by spring and occasionally lasting until February in southern and far
south-western regions. These timeframes vary annually due to fuel loads, long-term
climate patterns, and short-term weather conditions, differing from other Australian
states. In the far north and the northwest, warm, dry winters and springs, with dead
grasses and dry fuels, heighten bushfire risks. In the south, the greatest danger
follows dry winters and springs, with severe conditions arising when low-pressure
systems bring strong, hot, dry westerly winds to coastal areas. The season ends with
the arrival of moist conditions, often influenced by tropical cyclones near the coast.
Max Bushfire Protection Consulting 15
Page 16
Bushfire Report
The Forest Fire Danger Index (FFDI) evaluates the likelihood of fire ignition, its
propagation rate, intensity, and the difficulties encountered during suppression,
amalgamating factors like air temperature, relative humidity, wind speed, and
drought effects. This assessment is accessible through state mappings, revealing an
annual exceedance probability FFDI of 47 at a 5% probability level for the subject
site. Fire Danger Ratings (FDR) are determined by forecasted weather conditions,
particularly the FFDI, offering insight into the level of bushfire threat on a given day.
This FFDI corresponds to a high FDR, indicating hot, dry, and windy conditions.
Under such circumstances, the ignition and spread of fires may present significant
challenges for containment, especially in areas with extensive bushland vegetation.
For grassland, a Fire Danger Index (GFDI) of 130 is applied in the calculation of the
specific Bushfire Attack Level (BAL).
4.3 Fire History
Fire history information from QFES reveals that between 2015 and 2025, there were
no recorded fires within a 1-kilometer radius of the site. It has been a substantial
amount of time since the site was last exposed to a large-scale fire event. However,
it is important to note that while this information does not guarantee the site will
remain free from future fires, the likelihood of such events occurring appears to be
decreasing due to the surrounding residential and commercial land development
patterns.
4.4 Site-Specific Hazard Assessment
This Site-Specific Bushfire Hazard Assessment draws upon several key references
and sources, including:
• Vegetation Hazard Classification and Potential Fire-line Intensity for
Queensland, as outlined in "A new methodology for state-wide mapping of
bushfire-prone areas in Queensland" by CSIRO, Australia (2014).
• The Bushfire Resilient Communities Technical Reference Guide (QFES,
2019).
• The Bushfire Attack Level (BAL), Building setback requirements, and
Construction Standards as specified in the Australian Standard AS3959:2018
Construction of buildings in bushfire-prone areas.
• Bushfire Risk Mitigation Measures aligned with current industry best-practice
assessment methodologies and compliance with Council's Planning Scheme.
This assessment will utilize factors such as vegetation composition and extent,
slope, and industry-standard fuel load calculations to determine the potential bushfire
hazard affecting the proposed development. Furthermore, this Bushfire Management
Plan (BMP) will ensure compliance with the Council's Bushfire Overlay Code in
relation to the proposed development.
Max Bushfire Protection Consulting 16
Page 17
Bushfire Report
The assessment involved an analysis of the site and its immediate 100 m radius
surroundings to determine the typical bushfire risk characteristics. It included the
application of Vegetation Hazard Classifications to vegetation located within 100 m
of the site. Where necessary, it was expanded to cover an additional area ranging
from 150 to 300 m.
According to AS3959:2018, the following vegetation shall be excluded from a BAL
assessment, which is considered as low threat vegetation and/or non-vegetation
areas:
• Vegetation of any type that is more than 100m from the site.
• Single areas of vegetation less than 1 ha in area and not within 100 m of other
areas of vegetation being classified vegetation.
• Multiple areas of vegetation less than 0.25 ha in area and not within 20 m of
the site, or each other or of other areas of vegetation being classified
vegetation.
• Strips of vegetation less than 20 m in width (measured perpendicular to the
elevation exposed to the strip of vegetation) regardless of length and not
within 20 m of the site or each other, or other areas of vegetation being
classified vegetation.
• Non-vegetated areas, that is, areas permanently cleared of vegetation,
including waterways, exposed beaches, roads, footpaths, buildings and rocky
outcrops.
• Vegetation regarded as low threat due to factors such as flammability,
moisture content or fuel load. This includes grassland managed in a minimal
fuel condition, mangroves and other saline wetlands, maintained lawns, golf
courses (such as playing areas and fairways), maintained public reserves and
parklands, sporting fields, vineyards, orchards, banana plantations, market
gardens (and other non-curing crops), cultivated gardens, commercial
nurseries, nature strips and windbreaks.
The assessment also takes into account the small and or isolated patches and
corridor filtering process of Bushfire Resilient Communities:
• Sub-hectare areas of continuous fuel (i.e. surrounded by either no fuel or non-
continuous fuel) those are further than 100 metres from any other continuous
fuel greater than two hectares.
• Downgrade the effective fuel load of continuous vegetation patches
measuring (a) 1 to 2 hectares (by 66 per cent), and (b) 2-3 hectares patches
(by 50 per cent) if the patch is surrounded by either non-continuous fuel or a
low-hazard vegetation or land use type, and if the patch is further than 100
metres from any other continuous-fuel vegetation patch greater than two
hectares.
• Remove narrow corridors and areas of continuous fuel < 50 m in width that
are not sufficiently wide to support a fully developed flame front.
Max Bushfire Protection Consulting 17
Page 18
Bushfire Report
• Small fragments are removed because of the varied quality of the vegetation
mapping inputs.
It is noted that the client is actively undertaking vegetation management activities on
the site, including the removal of invasive weeds, thinning of overgrown vegetation,
and general landscape and property maintenance.
4.4.1 Ground Truthed VHC
The locations of site assessment plots are shown on Figure 4-2. Table 2 presents a
summary of observations and the features of site assessment points.
Lot Mapped VHC Ground Truthed VHC
Lot 1 VHC 40.4 Continuous low grass or VHC 40.4 Continuous low grass or
tree cover tree cover
Potential hazard grassland
Lot 2 VHC 40.4 Continuous low grass or VHC 40.4 Continuous low grass or
tree cover tree cover
Potential hazard grassland
Lot 3 VHC 40.4 Continuous low grass or VHC 40.4 Continuous low grass or
tree cover tree cover
Potential hazard grassland
Lot 4 VHC 40.4 Continuous low grass or VHC 40.4 Continuous low grass or
tree cover tree cover
Potential hazard grassland
Lot 5 VHC 40.4 Continuous low grass or VHC 40.4 Continuous low grass or
tree cover tree cover
VHC 8.1 Wet eucalypt tall open Potential hazard grassland
forest VHC 8.1 Wet eucalypt tall open
forest
Table2: Ground truthed VHC
Max Bushfire Protection Consulting 18
Page 19
Bushfire Report
Figure 4-2: Ground truthed VHC and local Bushfire Prone Area map
Max Bushfire Protection Consulting 19
Page 20
Bushfire Report
▪ Classified vegetation surround BLE of Lot 1 – Lot 4
The proposed building envelopes on Lot 1, Lot 2 and Lot 4 are all located within
existing cleared areas. Unmanaged vegetation, such as unmanaged grassland and
grassy woodland, characterised by overgrowth typically exceeding 10cm in height,
dense ground cover, and the accumulation of dry or dead vegetation due to the
absence of mowing, slashing, or grazing would contribute to a build-up of fine fuels
that are easily ignitable and capable of sustaining rapid fire spread under dry and
windy conditions, thereby posing a potential bushfire risk.
▪ Classified vegetation surround BLE of Lot 5
Land at assessment plot F, a large continuous hazardous vegetation patch VHC 8.1
Wet eucalypt tall open forest was found along the eastern boudnary. This vegetation
patch may contain RE 12.11.2 Eucalyptus saligna or E. grandis, E. microcorys,
Lophostemon confertus tall open forest on metamorphics +/- interbedded volcanics.
Limited regular maintenance activities have been carried out in this area.
Trees ranging from 10m to 30m in height, characterized by foliage cover 30% to
70%, are typically dominated by eucalypts. The understorey is sclerophyllous,
comprising small trees, tall scrubs, or tall shrubs with hard leaves and short
internodes. A diverse range of weeds and invasive plant species, including weedy
grasses and Lantana, is widespread across the area, occurring under conditions
varying from sparse to moderately dense. The predominant tree canopy reaches a
height of approximately 25m.
The potential fuel load of the bushfire hazard vegetation patch is determined as
following:
Lot 5 Lot 5 Lot 1- Lot 4
Vegetation context VHC 8.1 Hazard grassland Hazard grassland
Vegetation structure Open Forest Grassland Grassland
AS3959:2018 Group A Forest – Group G-21 Group G-21
Classification of vegetation Open Forest 03 Closed Tussock Closed Tussock
Grassland Grassland
Effective slope under the Upslope. East Downslope 14° Downslope 14°
hazardous vegetation North North
Slope Between Site and Upslope. East Downslope 14° Downslope 14°
hazardous vegetation North North
Understorey fuel load 31.0 t/ha - -
Total fuel load 35.0 t/ha 14.9 t/ha 14.9 t/ha
Table 3: Potential fuel load
Max Bushfire Protection Consulting 20
Page 21
Bushfire Report
4.4.2 Vegetation Conditions within the proposed development
On all lots, within the building area and the designed Asset Protection Zone,
vegetation conditions will be consistently maintained in a low-fuel state, aligning with
the characteristics of VHC 40.4 Continuous low grass or tree cover.
Figure 4-3: Aerial view providing landscape context for the site (Sourced from QLD SPP mapping,
captured 03/2026)
Max Bushfire Protection Consulting 21
Page 22
Bushfire Report Figure 4-4: 1m interval contour map (Sourced from Queensland Globe mapping, captured 03/2026) Max Bushfire Protection Consulting 22
Page 23
Bushfire Report Figure 4-5: AS 3959:2018 Classification of vegetation – Open Forest A-03 and Grassland G-21 Max Bushfire Protection Consulting 23
Page 24
Bushfire Report
Figure 4-6: Ecological Condition Profile of RE 12.11.2
Max Bushfire Protection Consulting 24
Page 25
Bushfire Report
Figure 4-7: Regulated vegetation management map (sourced from Vegetation management report,
Department of Resources, 2026)
Max Bushfire Protection Consulting 25
Page 26
Bushfire Report
Figure 4-8: Vegetation Management Support Map providing RE context on the site (sourced from
Vegetation management report, Department of Resources, 2026)
Max Bushfire Protection Consulting 26
Page 27
Bushfire Report
Photo 1: The proposed development area
Max Bushfire Protection Consulting 27
Page 28
Bushfire Report
Photo 2: Bushfire hazard vegetation – unmanaged grassland
Max Bushfire Protection Consulting 28
Page 29
Bushfire Report
Photo 3: Bushfire Hazard Vegetation VHC 8.1 along eastern boundary
4.5 Probable Direction of Bushfire Attack
The anticipated directions of bushfire threat to the proposed development are
expected to originate from any direction, primarily in areas classified as having
medium, high and very high bushfire hazard levels from downslope vegetations.
4.6 Radiant Heat Flux Modelling
The radiant heat exposure outcome for residential development, as outlined in the
SPP Bushfire Prone Area Code under the Natural Hazards, Risk and Resilience –
State Planning Policy State Interest guidance material (DSDMIP 2019), requires that
radiant heat flux does not exceed 29 kW/m².
All proposed lots contain sufficient building area for a new Class 1a dwelling to
achieve a radiant heat flux of no more than 29 kW/m².
As illustrated in Figure 4-1, sufficient building area is available on proposed Lot 5 for
the construction of a Class 1a dwelling. Compliance with the ≤29 kW/m² radiant heat
flux criterion can be achieved through a setback of approximately 17.2 m from the
classified bushfire hazard vegetation to the east and 12.5 m from hazard grassland.
Max Bushfire Protection Consulting 29
Page 30
Bushfire Report
For Lot 1, Lot 2, Lot 3 and Lot 4, compliance with the ≤29 kW/m² radiant heat flux
criterion can be achieved through a minimum setback of 12.5 m from hazard
grassland.
4.7 Building Envelope and Asset Protection Zone
An Asset Protection Zone (APZ) will need to be established and maintained on each
lot to ensure adequate separation from hazardous vegetation.
For Lot 5, the designed APZ will have a radius of 25 m around the proposed
building(s) as minimum, consisting of a 10 m for the Inner Protection Area and a
further 15 m for the Outer Protection Area.
For Lot 1, Lot 2, Lot 3 and Lot 4, will be 10 m for the inner Protection Area and a
further 10m for the Outer Protection Area.
All distance measurements for the APZ should be taken as horizontal distances.
Management strategies within the APZ will ensure that vegetation or other structures
proposed do not increase the overall potential fuel load. The Bushfire Management
Plan will detail these requirements comprehensively.
In the remaining areas on each lot, the client should continue to maintain the current
vegetation management practices. Unmanaged vegetation will increase the bushfire
risk.
To assist in managing the impacts of bushfires in Queensland, the Queensland
Government has developed guidelines aimed at enhancing the resilience of both
new and existing homes. These guidelines provide practical, site-specific
recommendations on building design and landscaping measures to improve bushfire
resilience.
It is recommended that the client refer to and apply these guidelines to strengthen
the bushfire resilience of the dwelling.
• Queensland Reconstruction Authority (2024). Bushfire Resilient Building
Guidance for Queensland Homes.
https://www.qra.qld.gov.au/sites/default/files/2024-
02/0873_QRA%20CSIRO%20Bushfire%20Guideline%20(updated%20Februa
ry%202024).pdf
4.8 Bushfire Attack Level and Construction Requirements
For building approval on new lot, a bushfire report to determine the accurate BAL will
be requested where the location of the building location is decided.
It is recommended that the new building be located at the BAL-19 area or lower
where possible.
Max Bushfire Protection Consulting 30
Page 31
Bushfire Report Where considering the application of the designed Asset Protection Zone, the overall Bushfire Attack Level (BAL) for the proposed development has been assessed as being BAL-19. BAL-19 is primarily concerned with protection from ember attack and radiant heat greater than 12.5 kW/m² up to and including 19 kW/m². To meet the construction standards outlined in AS3959:2018, both Section 3 "Construction General" and Section 6 "Construction Requirements for BAL-19" should be adhered to. Max Bushfire Protection Consulting 31
Page 32
Bushfire Report
Figure 4-10: Separation Distance and Radiant Heat Flux Modelling
Max Bushfire Protection Consulting 32
Page 33
Bushfire Report
Figure 4-11: Asset Protect Zone – for new and existing Class 1a Dwelling
Max Bushfire Protection Consulting 33
Page 34
Bushfire Report
5. Bushfire Management Plan
This Bushfire Management Plan (BMP) identifies the bushfire protection measures
that should be implemented as part of the proposed development to manage and to
reduce the risk from bushfire to an acceptable level. It is important to understand the
processes that influence bushfire behaviour and the sources of damage that threaten
people and property.
5.1 Bushfire Behaviours
Understanding bushfire behavior is crucial when planning development on bushfire-
prone land to effectively mitigate the risks associated with bushfires. Three primary
elements significantly influence bushfire behavior, as follows:
5.1.1 Topography
The physical characteristics of the landscape significantly influence bushfire
behavior. It is well-established that fires tend to spread more rapidly when they move
uphill. This is because flames can easily access unburnt fuel ahead of the fire, which
is pre-heated by radiant heat, making it more combustible. Studies indicate that for
every 10-degree increase in slope, the fire's speed can double. For example, if a fire
is moving at a rate of 5 km per hour on flat ground, and it encounters a 10-degree
slope, its speed can double to 10 km per hour uphill. As the fire gains momentum, it
also increases in intensity, becoming even hotter.
Conversely, when a fire moves downhill, its speed decreases because the flames
have less fuel to consume, and radiant heat pre-heats less fuel in front of the fire.
For every 10-degree decrease in slope, the fire's speed is halved. It's important to
note that fires typically move more slowly as the slope declines.
5.1.2 Weather Conditions
Weather conditions are a major factor in the behavior and spread of bushfires. Hot,
dry, and windy conditions can make fires more intense and difficult to control, while
cooler and more humid conditions can slow their spread. Wind can also influence the
direction and speed of the fire, and changes in wind direction can make it more
difficult for firefighters to predict the fire's behavior. Weather forecasting is a critical
component of bushfire management, as it allows firefighters and other responders to
anticipate changes in fire behavior and take action to mitigate the risks. In addition,
many communities now use tools like automated alert systems to warn residents of
potential fire danger based on weather conditions.
The new Australian Fire Danger Rating System (AFDRS) improves and simplifies the
reporting of fire danger. Fire danger ratings describe the potential level of danger
should a bushfire starts. It is a valuable information for taking actions to protect
people and property. The AFDRS has four levels, each with a distinct title, colour
and key message.
Max Bushfire Protection Consulting 34
Page 35
Bushfire Report
5.1.3 Vegetation
The amount and type of fuel available can greatly influence the behavior of a
bushfire. Vegetation is the source of fuel of a bushfire. Vegetation that is dry and
dead, or that is densely packed, can create more intense and long-lasting fires. In
contrast, areas with little fuel or sparse vegetation may not support a fire at all. The
arrangement of fuel can also play a role, as fires that encounter a continuous "fuel
ladder" from the ground up into the canopy can become more severe. The amount of
fuel surrounding a building can directly impact a buildings survival. Vegetation
management, landscaping for bushfire and breaking the continuity of vegetation can
limit the spread of fire.
Moderate: Plan and Prepare.
Most fires can be controlled
▪ Stay up to date and be ready to act if there is a fire.
High: Be Ready to Act
Fires can be dangerous
▪ Decide what you will do if a fire starts.
▪ There’s a heightened risk. Be alert for fires in your area.
▪ If a fire starts, your life and property may be at risk. The safest option is to
avoid bushfire risk areas.
Extreme: Take Action Now to protect your life and property
Fires will spread quickly and be extremely dangerous
▪ These are dangerous fire conditions.
▪ Check your bushfire plan and make sure your property is fire ready.
▪ If a fire starts, take immediate action.
▪ If you and your property are not prepared to the highest level, go to a safer
location well before the fire impacts.
▪ Reconsider travel through bushfire risk areas.
Catastrophic: For your survival, leave bushfire risk areas
If a fire starts to take hold, lives are likely to be lost
▪ These are the most dangerous conditions for a fire.
▪ Your life may depend on the decisions you make, even before there is a fire.
▪ For your survival, do not be in bushfire risk areas.
▪ Stay safe by going to a safer location early in the morning or the night before.
▪ If a fire starts and takes hold, lives and properties are likely to be lost.
▪ Homes cannot withstand fires in these conditions. You may not be able to
leave and help may not be available.
Table 4: Australian Fire Danger Rating
5.2 Potential Bushfire Impacts and Attack Mechanisms
Bushfire attack mechanisms are typically interconnected, rarely occurring in
isolation. Both people and property often face a combination of bushfire attack
Max Bushfire Protection Consulting 35
Page 36
Bushfire Report
factors, each operating across different spatial scales. Nevertheless, strategies
aimed at mitigating the impacts of direct flame contact, radiant heat exposure, and
ember attack can be effectively addressed within the framework of land use planning
and development assessments, conducted at manageable scales.
The main sources of direct bushfire attack that give rise to loss of life, and damage to
property and infrastructure are as follows:
5.2.1 Direct Flame Contact
Direct flame contact occurs when flames from a bushfire come into direct contact
with a building, structure, or individuals. When this happens, the flames can ignite
any flammable material present and cause fires to spread rapidly. Direct flame
contact can also cause burns and other heat-related injuries to people who are in the
path of the flames.
Direct flame contact is a significant concern during a bushfire, especially for buildings
and structures that are located in close proximity to the fire. The intensity of the
flames and the duration of the exposure can have a significant impact on the severity
of the damage.
To reduce the risk of direct flame contact during a bushfire, it's essential to create a
defensible space around buildings and structures, clear flammable materials from
the area, and use fire-resistant building materials when constructing or renovating
buildings. Additionally, it's crucial to follow evacuation orders and stay informed
about the fire's behavior and movement to ensure personal safety.
5.2.2 Radiant Heat Exposure
Radiant heat exposure is a significant danger during a bushfire. When a bushfire
occurs, the heat generated by the flames causes the air surrounding the fire to heat
up, and this heat energy is then radiated out in the form of electromagnetic waves.
These waves can travel a considerable distance from the fire and can cause
surfaces that are not in direct contact with the flames to heat up.
During a bushfire, radiant heat exposure can be intense, and the effects can be
severe. Radiant heat can ignite flammable materials, such as dry vegetation or
wooden structures, and cause them to catch fire. It can also cause buildings and
structures to overheat, leading to structural damage or collapse. Additionally, people
who are too close to the flames can suffer from heat stress, dehydration, and serious
burns.
The risk of radiant heat exposure during a bushfire can be mitigated by creating a
defensible space around buildings and structures, clearing flammable materials from
the area, and using fire-resistant building materials when constructing or renovating
buildings. It's also important to follow evacuation orders and stay informed about the
fire's behavior and movement to ensure personal safety.
Max Bushfire Protection Consulting 36
Page 37
Bushfire Report
5.2.3 Ember Attack
Ember attack, often referred to as spot fires, represents a prominent hazard during
bushfires. This phenomenon occurs when burning embers, also known as firebrands
or spot fires, are carried by the wind and land in different locations, potentially
igniting new fires.
In the midst of a bushfire, the combination of hot air and flames generates updrafts
capable of lifting burning embers over considerable distances. These embers can
alight on rooftops, in gutters, or on flammable materials near buildings and
structures, leading to ignition and the potential initiation of new fires.
Ember attack poses a unique danger because it can manifest hours or even days
after the primary fire front has passed, and it has the capacity to ignite fires in areas
previously unaffected by the bushfire. Consequently, it is imperative to prepare for
ember attack through measures such as establishing a defensible space around
buildings and structures, removing flammable materials from the vicinity, and sealing
gaps and openings in buildings to prevent ember ingress.
5.2.4 Wind and Smoke Attack
Strong winds can cause a bushfire to spread more rapidly and can also increase the
likelihood of ember attack, as burning embers can be carried by the wind over long
distances. Wind can also push flames and radiant heat towards buildings and
structures, increasing the risk of direct flame contact and radiant heat exposure.
Smoke from a bushfire can also pose a danger to people's health, particularly for
those with respiratory problems. Smoke can contain particulate matter, carbon
monoxide, and other harmful pollutants that can irritate the lungs and worsen
respiratory conditions. In addition to health effects, smoke can reduce visibility,
making it more difficult for firefighters to contain the fire and for people to evacuate
safely.
5.2.5 Convection and Conduction
Both convection and conduction can play a significant role in the spread and
intensity of a bushfire. To reduce the risk of a bushfire spreading through convection
and conduction, it's important to create a defensible space around buildings and
structures, clear flammable materials from the area, and use fire-resistant building
materials when constructing or renovating buildings. It's also crucial to follow
evacuation orders and stay informed about the fire's behavior and movement to
ensure personal safety.
5.3 Bushfire Protection Measures
This section identifies the bushfire protection measures that will be implemented as
part of the proposed development to comply with the requirements of both the State
Max Bushfire Protection Consulting 37
Page 38
Bushfire Report
and local council's Bushfire Prone Area code and to minimise the impact of potential
bushfires on people and property.
The proposed measures are prepared in according with Queensland State
Government State Planning Policy - Part E (SPP 2017), the Bushfire Resilient
Communities Technical Reference Guide (QFES, 2019), the local council's Bushfire
Overlay Code, and the Australian Standard (AS 3959:2018) for Construction of
buildings in bushfire-prone areas.
The legislation mentioned above aims to protect individuals and buildings from
bushfires by ensuring that new developments meet specific Performance Outcomes
that are appropriate for the identified bushfire hazard. These Performance Outcomes
are typically achieved by properly separating the development from the bushfire
hazard, providing adequate access for firefighting vehicles, and constructing
buildings to the appropriate standards. Additionally, the legislation includes other
relevant factors that are deemed necessary for ensuring the safety of individuals and
buildings during a bushfire emergency.
5.3.1 Asset Protection Zone (APZ)
An Asset Protection Zone (APZ) is the most important bushfire protection measure.
An APZ is a designed area surrounding a building or structure that has been well
managed to reduce the risk of a bushfire impacting the building or structure. An APZ
provides:
▪ A buffer zone between a bushfire hazard and an asset
▪ An area of reduced bushfire fuel that allows suppression of fire
▪ An area from which backburning may be conducted
▪ An area which allows emergency services access and provides a relatively
safe area for firefighters and homeowners to defend their property.
A correctly designed and regularly maintained APZ will reduce the risk of:
▪ Direct flame contact on the asset
▪ Damage to the build asset from intense radiant heat
▪ Ember attack on the asset
An APZ are typically designed and created by removing vegetation and other
combustible materials from around the building or structure, reducing the fuel
available for a bushfire. The width of the APZ and the level of vegetation removal
required depend on a number of site-specific factors, including the slope of the land,
the hazardous vegetation type, and the intensity of the bushfire hazard. The property
owner is responsible for creating and maintaining regularly the designed APZ.
(1) Creating APZ by reducing bushfire fuel
The intensity of bush fires can be greatly reduced where there is little to no available
fuel for burning. To effectively manage bushfire fuels, there are several approaches
to reduce, remove, or change the condition of the fuel.
Max Bushfire Protection Consulting 38
Page 39
Bushfire Report
▪ Raking or manual removal of fine fuels
▪ Mowing or grazing of grass
▪ Removal or pruning of trees, shrubs and understorey
▪ Slashing and trittering
It is important to note that reducing fuel does not always require removal of all
vegetation, which would cause environmental damage. Trees and plants also
provide protection against bushfires by mitigating the impact of strong winds, intense
heat and flying embers (by filtering embers) and changing wind patterns. Some
ground cover vegetation is also needed to prevent soil erosion.
(2) Ongoing management for APZ
The creation of an Asset Protection Zone (APZ) establishes a controlled fuel-
managed area that serves to reduce the potential impact of direct flame contact and
radiant heat on property development, effectively acting as a defensible space. It is
crucial to emphasize that the management of vegetation and landscaping within the
APZ is of paramount importance and should maintain a minimal fuel load.
An APZ should be maintained in perpetuity to ensure ongoing protection from the
impact of bushfires, and maintenance of the APZ should be regularly undertaken,
especially in advance of the bushfire season. The requirements are set out as
follows.
(i) Inner Protection Area
The Inner Protection Area is the area closest to the building and creates a fuel-
managed area which can minimise the impact of direct flame contact and radiant
heat on the proposed development and act as an important space. Vegetation within
this area should be kept below 100 mm in height and be discontinuous.
In practical terms the Inner Protection Area is typically the curtilage around the
building, consisting of a mown lawn and well-maintained gardens.
When establishing and maintaining the inner protection zone, the following
requirements apply:
▪ General
• A minimum 1m wide area, suitable for pedestrian traffic, must be
provided around the immediate curtilage of the building
• Planting is limited in the immediate vicinity of the building
• All leaves and vegetation debris must be removed at regular intervals
during the declared fire danger period
• Planting does not provide a continuous canopy to the building
• Within 10 metres of a building, flammable objects must not be located
close to the vulnerable parts of the building
• Plants greater than 10 cm in height must not be placed within 3m of a
window or glass feature of the building
Max Bushfire Protection Consulting 39
Page 40
Bushfire Report
• Low flammability vegetation species are used
▪ Trees
• Tree canopy cover should be less than 15% at maturity
• Trees at maturity should not touch or overhang the building
• Lower limbs should be removed up to a height of 2m above the ground
• Tree canopies should be separated by 2 to 5m
• Preference should be given to smooth barked and evergreen trees
▪ Shrubs
• Create large discontinuities or gaps in the vegetation to slow down or
break the progress of fire towards buildings should be provided
• Shrubs should not be located under trees
• Shrubs should not form more than 10% ground cover
• Clumps of shrubs should be separated from exposed windows and
doors by a distance of at least twice the height of the vegetation
▪ Grass
• Grass should be kept mown regularly (as a guide grass, should be kept
to no more than 100mm in height)
• Leaves and vegetation debris should be removed regularly
(ii) Outer Protection Area
The Outer Protection Area is located between the Inner Protection Area and
unmanaged vegetation. It is an area where there is maintenance of the understorey
and some separation in the canopy. The reduction of fuel in this area aims to
decrease the intensity of an approaching fire and restricts the potential for fire spread
from crowns, reducing the level of direct flame, radiant heat and ember attack on the
inner protection zone.
▪ Trees
• Tree canopy cover should be less than 30% at maturity
• Tree canopies should be separated by 2 to 5m
▪ Shrubs
• Shrubs should not form a continuous canopy, and
• Shrubs should not form more than 20% ground cover
▪ Grass
• Grass should be kept mown regularly to height of less than 100mm
• Leaves and other debris should be removed regularly.
Max Bushfire Protection Consulting 40
Page 41
Bushfire Report
Figure 5-1: Inner protection area and Outer protection area
5.3.2 Building Construction, Siting and Design
The appropriate design and construction of buildings enhance their survivability from
bushfires. Construction measures should not be applied as a stand-alone mitigation
solution but should form part of a suite of measures. This should also include APZ,
appropriate access, water supply and landscaping. Building design needs to ensure
adequate protection of vulnerable building elements. Construction standards are
outlined in AS 3959:2018 and the NASH Standard to provide various levels of
protection for different building elements.
The outcome of the BAL assessment is BAL-19 in according with AS 3959:2018 and
the Bushfire Resilient Communities.
Max Bushfire Protection Consulting 41
Page 42
Bushfire Report
It should be noted the Building Code of Australia only requires Classes 1, 2 and 3
and certain Class 9 buildings and Class 10a building associated with those buildings
to comply with the bushfire provisions of the NCC 2022.
5.3.3 Access and Evacuation Arrangement
Developments in bushfire prone areas should be serviced by safe access/exit points
for both site personnel and emergency services personnel in the event of an
emergency. The local council’s Bushfire Hazard Overlay Code prescribes
appropriate access for fire management an evacuation to be provided as below:
▪ Do not exceed an average gradient of 12.5%
▪ Have a minimum width of 4m and 6m of vegetation clearing, can be up to
10m.
▪ Have a minimum of 4.8m vertical clearance
▪ Accommodate turning areas for fire-fighting appliances in accordance with
Qld Fire and Emergency Services’ Fire Hydrant and Vehicle Access
Guidelines
▪ Passing bays for firefighting appliances are 20m long by 3m wide, with a
minimum trafficable width of 7m at the passing bay
▪ Reversing bays for firefighting appliances are 6m wide and 8.5m deep to any
gates, meeting above turning requirements
▪ Passing bays or turning intervals located every 200m with a maximum grade
of 5%
▪ Compacted driveway to ensure all weather surfaces
The proposed development will provide with vehicular access that enables safe
evacuation for occupants and easy access by firefighting appliances. Consequently,
the proposed development is in compliance with the Council Bushfire Hazard
Overlay.
5.3.4 Water Supply
It is noted that AS 3959:2018 – Construction of buildings in bushfire-prone areas
does not include requirements for water supply for firefighting purposes, nor is water
supply a factor in determining a building’s Bushfire Attack Level (BAL) rating.
Accordingly, the building certifier should not impose conditions on the building
approval relating to water supply for firefighting purposes, unless such conditions are
required under a development permit issued by the local council or are specified in
the applicable local planning scheme.
An adequate supply of water is essential for firefighting purposes and suitable water
supply arrangements shall be provided. The proposed development should provide
Max Bushfire Protection Consulting 42
Page 43
Bushfire Report
an appropriate water supply to support effective emergency services response
includes reticulated water and/or appropriate static water supply.
The reticulated hydrant system shall be designed and constructed in accordance
with ‘QLD Fire and Emergency Services’ Fire Hydrant and Vehicle Access
Guidelines.
Where reticulated water is unavailable, an appropriate static water supply should
consist of a dedicated water tank specifically for firefighting purposes, with suitable
access for firefighting appliances. It is recommended that the tank be located within
10m of the building. To ensure durability and compliance with safety standards, it is
strongly recommended that the tank be constructed underground or from non-
combustible materials, such as steel or concrete.
The tank must include a take-off connection providing a minimum of 10,000 litres of
static water exclusively for firefighting access. The site must permit clear access for
a medium rigid fire appliance (15 tonnes) to within 6 metres of the tank.
Tanks and associated pumps must be protected from bushfire impact in accordance
with AS 2304:2011 – Water storage tanks for fire protection systems. Where the site
is serviced by a rural fire brigade, the tank shall be fitted with brigade-compatible
fittings, including a 50-millimetre ball valve and a male camlock coupling. If the tank
is underground, a minimum 200-millimetre access hole must be provided to allow
suction line access. Directional signage must clearly indicate the tank’s location at
the street frontage.
5.3.5 Landscaping Management Plan
The type, location and ongoing maintenance of landscaping are considered a
necessary bushfire protection measure. Landscaping management for bushfire is the
process of designing, constructing, and maintaining a landscape in a way that
reduces the risk of bushfire. The management strategies typically involve creating
fire breaks, reducing fuel loads, and selecting vegetation that is less flammable.
Appendix A provides a list of less flammable plants.
The landscaping management shall be carried out as the requirements set out for
Asset Protection Zone in Section 5.3.1.
5.3.6 Reducing Fuel load and Weed Management
Removing excess ground fuels and combustible material is a crucial aspect of
effective fire prevention and management. This process involves the careful
clearance of various flammable materials, including long dry grass, accumulated
dead leaves, and fallen branches. By systematically reducing these fuel sources, the
risk of fire ignition and spread is significantly mitigated. Regular maintenance of such
Max Bushfire Protection Consulting 43
Page 44
Bushfire Report clearance efforts is essential to ensure ongoing fire safety and resilience within the environment. Unmanaged invasive pest plants can swiftly amplify fuel loads, comprising fast- growing introduced grasses, dense woody weeds, and invasive climbing vines. These factors collectively escalate fuel loads, fostering a "laddering" effect, intensifying fire spread and allowing it to transition from ground to canopy. Effective weed management markedly diminishes bushfire risk to the site and surrounding properties. Max Bushfire Protection Consulting 44
Page 45
Bushfire Report
6. Conclusion
The following recommendations are provided in relation to the requirements of
Council’s Bushfire Hazard Overlay Code.
• Bushfire management area and Asset Protection Zone (APZ) have been
designed and will be established and maintained. Each lot contains a
sufficient building area to accommodate a dwelling with a predicted radiant
heat flux exposure not exceeding 29 kW/m²
• Construction of building to meet construction requirements of AS 3959:2018.
• Provision of water and service to be in accordance with the requirements.
• The location of the proposed dwelling maximizes the use of existing cleared
and open space while minimizing the clearing of native vegetation and its
impact on the environment.
In conclusion, the proposed development has been designed and managed to
ensure that the exposure of people and property to unacceptable bushfire hazard
risks has not increased. The development will mitigate bushfire risk through
appropriate siting, design, and management measures. It provides suitable access
and evacuation routes for both private and emergency service vehicles, in line with
the nature of the development and the level of bushfire risk. An adequate water
supply for firefighting purposes will be provided, and no hazardous goods will be
stored on-site. Overall, the development meets all necessary requirements to
minimize the risk of bushfires to people, property, public health, and the
environment.
This assessment assumes that vegetation on the site will be maintained according to
the client’s outlined plans. Should the proposed development require the removal of
site vegetation to meet specific BAL requirements set by either the developer or the
client, it is the client’s responsibility to comply with relevant regulations regarding
native vegetation clearing.
Although emergency management arrangements are not a mandatory measure for
the proposed development, it is recommended that residents in bushfire prone areas
prepare a bushfire survival plan.
Henry (Hongxi) Liang
BEng, GradDip (Bushfire Protection), MBA
Senior Bushfire Consultant
Max Bushfire Protection Consulting
Mobile: 0432 89 82 82
Email: [email protected]
Max Bushfire Protection Consulting 45
Page 46
Bushfire Report 7. References Australian Standard, 2018. Construction of Buildings in Bushfire-prone Areas (AS3959–2018). Leonard, J, Newnham, G, Opie, K, and Blanche, R; 2014. A New Methodology for State-wide Mapping of Bushfire Prone Areas in Queensland. CSIRO, Australia. Queensland Development Assessment Mapping System: https://sara.dsdip.esriaustraliaonline.com.au/saraviewer/ Queensland Government SPP Interactive Mapping System; 2022. http://www.dilgp.qld.gov.au/planning/state-planning-instruments/spp-interactive-mappingsystem.html. The State of Queensland, July 2017. Queensland State Planning Policy (July 2017). Queensland Department of Infrastructure, Local Government and Planning. Gold Coast. The State of Queensland, October 2019. Bushfire Resilient Communities Technical Reference Guide for the State Planning Policy State Interest ‘Natural Hazards, Risk and Resilience – Bushfire. 8. Appendix Appendix A Site Plan Appendix B Low Flammability Plant Species List Appendix C Summary of AS3959-2018 Construction Requirements for Bushfire Attack Level Max Bushfire Protection Consulting 46
Page 47
Bushfire Report Appendix A Site Plan Max Bushfire Protection Consulting 47 [OCR of page images] Bushfire Report Appendix A Site Plan Max Bushfire Protection Consulting = MAX WATTERSON = + ASSOCIATES ae | allt sa THREEDOM NOMINEES PTY LTD Proet | PLAN OF PROPOSED RECONFIGURATION OF LOT 3 ON | SP258891. (gn NSC Mapng ont: 20m Ref: 25-6775AG| 47
Page 48
Bushfire Report Appendix B Low Flammability Plant Species List This list is intended as a general guide. It is essential to conduct independent research to identify fire-resistant species specific to the region of the subject site, as suitability varies across Queensland. Notably, all plants, whether native or exotic, will combust when exposed to extreme heat or flame; therefore, additional precautions may be required. Ground covers and creeping plants • Casuarina glauca prostrate, commonly known as grey she oak or marsh she oak • Anigozanthos, commonly known as kangaroo paw • Carpobrotus glaucescens, commonly known as pigface • Hardenbergia violacea, commonly known as sarsparilla or purple coral pea • Liriope muscari, commonly known as lilyturf • Lomandra longifolia, commonly known as spiny-headed mat-rush • Lomandra hystrix, commonly known as mat-rush • Varieties of Brachyscome • Varieties of Dampiera • Dianella caerulea, commonly known as blue berry lily • Varieties of Dianella prunina • Dianella revoluta, commonly known as blue berry lily or spreading flax lily • Dichondra repens, commonly known as kidney weed • Einadia nutans, commonly known as climbing saltbush • Hardenbergia violacea, commonly known as false sarsaparilla, purple coral pea, happy wanderer, native lilac or waraburra • Scaevola aemula, commonly known as fairy fan flower • Scaevola humilis, commonly known as sandplain fan flower • Varieties of Cotyledon • Myoporum insulare, commonly known as boobialla, native juniper or blueberry tree • Eremophila glabra, commonly known as kalbarri carpet • Eremophila debilis, commonly known as winter apple • Elaeocarpus eumundi, commonly known as eumundi quandong • Elaeocarpus prima donna, commonly known as blueberry ash • Kennedia rubicunda, commonly known as Dusky coral pea or red kennedy pea • Rhododendron hybrid, commonly known as azalea • Varieties of Arctotis • Varieties of Photinia • Westringia fruticosa, commonly known as native rosemary Max Bushfire Protection Consulting 48
Page 49
Bushfire Report Shrubs • All varieties of Aloe • Correa reflexa, commonly known as nativefuchsia • Varieties of Acacia • Nerium oleander, commonly known as oleander • Varieties of Atriplex, commonly known as saltbushes • Varieties of Escallonia • Varieties of Maireana, commonly known as cottonbush • Varieties of Eremophila, commonly known as emu bushes or fuchsia bushes • Varieties of Grevillea • Melaleuca nodosa, commonly known as prickly leaf paperbark • Varieties of Syzygium • Varieties of Photinia • Varieties of Rhagodia • Rhaphiolepis indica, commonly known as india hawthorn • Strelitziacae hutch • Strelitzia banks • Srelizia nicolai • Sambucus australasica, commonly known as yellow elderberry or native elderberry • Varieties of Coprosma • Varieties of Plectranthus • Senna artemisioides, commonly known as silver cassia Deciduous trees • Brachychiton acerifolius, commonly known as the flame kurrajong • Ulmus parvifolia, commonly known as chinese elm • Morus alba, commonly known as the mullberry tree • Eriobotrya japonica, commonly known as loquot • Gleditsia triacanthos, commonly known as honey locust • Trees from the genus Prunus, including ornamental cherries, plums and peaches • Trees from the genus Malus, including apples and crab apples Max Bushfire Protection Consulting 49
Page 50
Bushfire Report
Evergreen trees
• Grevillea robusta, commonly known as silky oak
• Melia azedarach, commonly known as cape lilac, white cedar, persian lilac or chinaberry
• Lophostemon confertus, commonly known as brush box, queensland box, brisbane box
or pink box
• Tristaniopsis laurina, commonly known as water gum, kanooka or kanuka
• Rapanea variabilis, commonly known as muttonwood
• Varieties of Acacia
• Varieties of Acmena
• Varieties of Magnolia
• Cupaniopsis anacardioides, commonly known as tuckeroo or beach tamarind
• Elaeocarpus reticulatus, commonly known as blueberry ash
• Alectryon subcinereus, commonly known as native quince
• Callicoma serratifolia, commonly known as black wattle
• Canthium coprosmoides, commonly known as supple jack or sweet susie
• Cassine australis, commonly known as red olive berry or red olive plum
• Croton insularis, commonly known as Queensland cascarilla, native cascarilla bark or
silver croton
• Cuttsia viburnea, commonly known as native elderberry
• Varieties of Citrus
• Denhamia celastroides, commonly known as denhamia or orange boxwood
• Diospyros australis, commonly known as black plum or yellow persimmon
• Eupomatia laurina, commonly known as bolwarra, grey beech or native guava
• Glochidion ferdinandi, commonly known as the cheese tree or buttonwood
• Guioa semiglauca, commonly known as guioa or wild quince
• Hodgkinsonia ovatiflora, commonly known as golden ash
• Hymenosporum flavum, commonly known as native frangipani or Queensland frangipani
• Petalostigma triloculare, commonly known as quinine berry, forest quinine or bitter bark
• Podocarpus elatus, commonly known as she pine
• Rhodosphaera rhodanthema, commonly known as yellow cedar, tulip satinwood or deep
yellow wood
• Sarcopteryx stipata, commonly known as corduroy
• Scolopia braunii, commonly known as scolopia or brown birch
• Stenocarpus sinuatus, commonly known as white silky oak, tulip flower, white beefwood
Or wheel of flower tree
• Streblus brunonianus, commonly known as the whalebone tree, axehandle wood or white
handlewood
• Symplocos stawellii, commonly known as white hazelwood
• Symplocos thwaitesii, commonly known as buff hazelwood
• Varieties of Ficus (fig trees)
Max Bushfire Protection Consulting 50
Page 51
Bushfire Report
Appendix C Summary of AS3959-2018 BAL-12.5 Construction Requirements
Note: this is a summary of some portions of the standard - the building designer, builder and
subcontractors should refer to AS3959-2018 in full prior to construction.
Subfloor supports
The Standard does not provide construction requirements for sub-floor supports where the
sub-floor is enclosed in accordance with wall that conforms to the requirements for walls listed
below or is enclosed with corrosion resistant steel, bronze or aluminium mesh with a maximum
aperture of 2 mm.
Floors
The Standard does not provide construction requirements for concrete slabs on the ground.
Unenclosed subfloor space
The standard does not provide construction requirements for bearers, joists and floors that
are greater than 400mm above finished ground level
External walls
External walls that are less than 400mm from the ground, decks, carport roofs and similar
elements should be:
(a) made of non-combustible materials (e.g. full masonry, brick veneer etc.) with a
minimum thickness of 90 mm,
(b) timber logs with a density of 680 kg/m 3 and a minimum nominal thickness of 90mm;
or
(c) cladding that is fixed externally to a timber or metal frame and is:
(i) non-combustible; or
(ii) fibre cement a minimum of 6mm thick; or
(iii) bushfire-resisting timber.
Joints
All joints in the external surface material of walls shall be covered, sealed, overlapped, backed
or butt-jointed.
Vents and weepholes
Vents and weepholes in external walls are to be screened with corrosion-resistant steel,
bronze or aluminium mesh with a maximum aperture of 2 mm.
External glazed elements, assemblies and doors
Screens for windows and doors
Where fitted, screens for windows and doors shall have mesh or perforated sheet made of
corrosion-resistant steel, bronze or aluminium with a maximum aperture of 2 mm.
Windows
Max Bushfire Protection Consulting 51
Page 52
Bushfire Report
Frame material for windows less than 400 mm from the ground, decks, carport roofs and
awnings, window frames are to be made from bushfire-resisting timber, metal or metal-
reinforced uPVC.
Where glazing is less than 400mm from the ground, decks, carport roofs and awnings, glazing
shall be Grade A safety glass with a minimum 4 mm thickness.
The openable portions of windows shall be screened with a mesh with a max aperture of 2
mm made of corrosion resistant steel, bronze or aluminium.
Doors - side hung external doors, panel fold & sliding doors
Doors- shall be completely protected externally by a screen with a mesh with a max aperture
of 2mm made of corrosion resistant steel, bronze or aluminium, OR
Door panel material shall be:
(a) non-combustible; or
(b) solid timber, laminated timber or reconstituted timber, having a minimum thickness of
35 mm for the first 400 mm above the threshold;
(c) hollow core, solid timber, laminated timber or reconstituted timber with a non-
combustible kickplate on the outside for the first 400 mm above the threshold; or
(d) protected externally by a metal screen with a maximum aperture of 2 mm; or
(e) fully framed glazed door panels with framing made from metal or bushfire resisting
timber.
There is no requirement to screen the openable part of a door at this level.
Garage doors
The lower portion (within 400 mm of the ground) of vehicle access doors shall be made from:
(i) non-combustible material; or
(ii) bushfire-resisting timber; or
(iii) fibre-cement sheet, a minimum of 6 mm in thickness; or
(iv) a combination of any of items (i), (ii) or (iii) above.
All vehicle access doors to be protected with suitable weather strips, draught excluders,
draught seals or brushes.
Roofs
The following apply to all types of roofs and roofing systems:
(a) roof tiles, roof sheets and roof covering accessories shall be non-combustible,
(b) the roof/wall and roof/roof junction shall be sealed, or otherwise protected to prevent
openings greater than 2mm,
(c) roof ventilation openings, such as gable and roof vents, shall be fitted with ember
guards made of non-combustible material or a mesh or perforated sheet with a max
aperture of 2mm made of corrosion resistant steel, bronze or aluminium.
Tiled roofs shall be fully sarked.
Sheet roofs shall:
Max Bushfire Protection Consulting 52
Page 53
Bushfire Report
(a) be fully sarked with sarking, except that foil backed insulation blankets may be
installed over battens; OR
(b) have any gaps sealed at the fascia, or wall line, hips and ridges by:
(i) a mesh or perforated sheet with a maximum aperture of 2 mm, made of corrosion-
resistant steel, bronze or aluminium (this may include gutter guard), or
(ii) mineral wool, or
(iii) other non-combustible material, or
(iv) -a combination of any of the above.
Roof penetrations
The following apply to roof penetrations:
(a) roof penetrations, including roof lights, roof ventilators, roof-mounted evaporative
cooling units, aerials, vent pipes and supports for solar collectors, shall be adequately
sealed at the roof to prevent gaps greater than 3 mm.
(b) openings in vented roof lights, roof ventilators or vent pipes shall be fitted with ember
guards made from a mesh or perforated sheet with a maximum aperture of 2 mm,
made of corrosion-resistant steel, bronze or aluminium.
(c) glazed elements in roof lights and skylights may be of polymer provided a grade safety
glass diffuser, complying with AS 1288, is installed under the glazing.
Eaves linings, fascias and gables
The following apply to eaves linings, fascias and gables:
(a) gables shall comply with requirements for walls.
(b) eaves ventilation openings are to be fitted with ember guards and be made of
corrosion resistant steel, bronze or aluminium.
The Standard does not provide construction requirements for fascias, bargeboards and eaves
linings.
Gutters and downpipes
The Standard does not provide material requirements for gutters and downpipes, with the
exception of box gutters.
Box gutters are to be non-combustible and flashed at the roof junction with non-combustible
material.
If installed, gutter and valley leaf guards are to be non-combustible.
Verandas, decks, steps, ramps and landings
Decking may be spaced. There is no requirement to enclose the subfloor spaces of verandas,
decks, steps, ramps or landings.
Decking, stair treads and trafficable surfaces of ramps and landings less than 300 mm
(measured horizontally at deck level) from glazed elements that are less than 400 mm
(measured vertically) from the surface of the deck are to be made from:
(a) of non-combustible material; or
(b) of bushfire-resisting timber; or
(c) a combination of items (a) and (b) above.
Max Bushfire Protection Consulting 53
Page 54
Bushfire Report Water and gas supply pipes Above ground, exposed water and gas supply pipes shall be metal. Max Bushfire Protection Consulting 54
Page 55
Bushfire Report
Summary of AS3959-2018 BAL-19 construction requirements
Note: this is a summary of some portions of the standard - the building designer,
builder and subcontractors should refer to AS3959-2018 in full prior to construction.
• Subfloor supports
The Standard does not provide construction requirements for sub-floor supports where the
sub-floor is enclosed in accordance with wall that conforms to the requirements for walls
listed below or is enclosed with corrosion resistant steel, bronze or aluminium mesh with a
maximum aperture of 2 mm.
Where the subfloor space is unenclosed, the support posts, columns, stumps, piers and
poles are to be of non-combustible material or bushfire resisting timber.
• Floors
The Standard does not provide construction requirements for concrete slabs on the ground.
Unenclosed subfloor space
The standard does not provide construction requirements for bearers, joists and floors if the
underside element is greater than 400mm above finished ground level
• External walls
The exposed components of external walls shall be as follows:
(a) made of non-combustible materials (e.g. full masonry, brick veneer etc.) with a
minimum thickness of 90 mm, or
(b) timber logs with a density of 680 kg/m3 and a minimum nominal thickness of 90mm;
or
(c) cladding that is fixed externally to a timber or metal frame and is:
(i) non-combustible; or
(ii) fibre cement a minimum of 6mm thick; or
(iii) bushfire-resisting timber.
• Joints
All joints in the external surface material of walls shall be covered, sealed, overlapped,
backed or butt-jointed.
Vents and weepholes
Vents and weepholes in external walls are to be screened with corrosion-resistant steel,
bronze or aluminium mesh with a maximum aperture of 2 mm.
External glazed elements, assemblies and doors
• Screens for windows and doors
Max Bushfire Protection Consulting 55
Page 56
Bushfire Report
Where fitted, screens for windows and doors shall have mesh or perforated sheet made of
corrosion-resistant steel, bronze or aluminium with a maximum aperture of 2 mm, with
framing made from metal or bushfire resisting timber.
• Windows
Frame material for windows are to be made from bushfire-resisting timber, metal or metal-
reinforced uPVC.
Glazing is to be toughened glass with a minimum thickness of 5 mm if the glazing is less
than 400mm from the ground.
The openable portions of windows shall be screened with a mesh with a max aperture of 2
mm made of corrosion resistant steel, bronze or aluminium.
• Doors - side hung external doors, panel fold & sliding doors
Doors- shall be completely protected externally by a screen with a mesh with a max aperture
of 2mm made of corrosion resistant steel, bronze or aluminium, OR
Door panel material shall be:
(a) non-combustible; or
(b) solid timber, laminated timber or reconstituted timber, having a minimum thickness of
35 mm for the first 400 mm above the threshold; or
(c) fully framed glazed door panels with framing made from metal, bushfire resisting
timber or uPVC.
Door frames shall be made from metal bushfire resisting timber, metal or metal reinforced
uPVC.
Where doors incorporate glazing, the glazing shall be toughened glass with a minimum
thickness of 5mm.
Doors shall be tight fitting to the door frame and to an abutting door, if applicable.
Weather strips, draught excluders or draught seals shall be installed.
There is no requirement to screen the openable part of a door at this level.
• Garage doors
Vehicle access doors shall be made from:
(i) non-combustible material; or
(ii) bushfire-resisting timber; or
(iii) fibre-cement sheet, a minimum of 6 mm in thickness; or
(iv) a combination of any of items (i), (ii) or (iii) above.
All vehicle access doors to be protected with suitable weather strips, draught excluders,
draught seals or brushes.
Max Bushfire Protection Consulting 56
Page 57
Bushfire Report
• Roofs
The following apply to all types of roofs and roofing systems:
(a) roof tiles, roof sheets and roof covering accessories shall be non-combustible,
(b) the roof/wall and roof/roof junction shall be sealed, or otherwise protected to prevent
openings greater than 2mm,
(c) roof ventilation openings, such as gable and roof vents, shall be fitted with ember
guards made of non-combustible material or a mesh or perforated sheet with a max aperture
of 2mm made of corrosion resistant steel, bronze or aluminium.
(d) A pipe or conduit that penetrates the roof covering shall be non-combustible
Tiled roofs shall be fully sarked with the sarking covering the entire roof area including ridges
and hips and extend into gutters and fascias.
Sheet roofs shall:
(a) be fully sarked with sarking, except that foil backed insulation blankets may be
installed over battens; OR
(b) have any gaps sealed at the fascia, or wall line, hips and ridges by:
(i) a mesh or perforated sheet with a maximum aperture of 2 mm, made of corrosion-
resistant steel, bronze or aluminium, or
(ii) mineral wool, or
(iii) other non-combustible material, or
(iv) -a combination of any of the above.
• Roof penetrations
The following apply to roof penetrations:
(a) roof penetrations, including roof lights, roof ventilators, roof-mounted evaporative
cooling units, aerials, vent pipes and supports for solar collectors, shall be sealed. Sealing
material is to be non-combustible.
(b) openings in vented roof lights, roof ventilators or vent pipes shall be fitted with ember
guards made from a mesh or perforated sheet with a maximum aperture of 2 mm, made of
corrosion-resistant steel, bronze or aluminium.
(c) all overhead glazing shall be Grade A safety glass complying with AS 1288.
(d) flashing elements shall be non-combustible.
• Eaves linings, fascias and gables
The following apply to eaves linings, fascias and gables:
(a) gables shall comply with requirements for walls.
Max Bushfire Protection Consulting 57
Page 58
Bushfire Report
(b) fascias and bargeboards shall be made from bushfire-resisting timber or metal.
(c) eave linings shall be fibre-cement sheet with a minimum thickness of 4.5mm or
bushfire resisting timber.
(d) eave penetrations shall be protected as for roof penetrations.
(e) eaves ventilation openings are to be fitted with ember guards and be made of
corrosion resistant steel, bronze or aluminium.
(f) joints in eave linings, fascias and gables may be sealed with plastic joining strips or
timber storm moulds.
• Gutters and downpipes
The Standard does not provide material requirements for gutters and downpipes, with the
exception of box gutters.
Box gutters are to be non-combustible and flashed at the roof junction with non-combustible
material.
If installed, gutter and valley leaf guards are to be non-combustible.
• Verandas, decks, steps, ramps and landings
Decking may be spaced. There is no requirement to enclose the subfloor spaces of
verandas, decks, steps, ramps or landings.
Decking, stair treads, trafficable surfaces of ramps and landings, balustrades and handrails
are to be made from:
(a) of non-combustible material; or
(b) of bushfire-resisting timber; or
(c) a combination of items (a) and (b) above.
Verandah posts shall be made from non-combustible material or bushfire-resisting timber.
• Water and gas supply pipes
Above ground, exposed water and gas supply pipes shall be metal. The metal pipe shall
extend a minimum of 400mm within the building and 100mm below the ground.
Max Bushfire Protection Consulting 58
Page 59
Bushfire Report
Summary of AS3959-2018 BAL-29 construction requirements
Note: this is a summary of some portions of the standard - the building designer,
builder and subcontractors should refer to AS3959-2018 in full prior to construction.
• Subfloor supports
The Standard does not provide construction requirements for sub-floor supports where the
sub-floor is enclosed in accordance with wall that conforms to the requirements for walls
listed below or is enclosed with corrosion resistant steel, bronze or aluminium mesh with a
maximum aperture of 2 mm.
Where the subfloor space is unenclosed, the support posts, columns, stumps, piers and
poles are to be of non-combustible material or bushfire resisting timber.
• Floors
The Standard does not provide construction requirements for concrete slabs on the ground.
Unenclosed subfloor space
The standard does not provide construction requirements for bearers, joists and floors if the
underside element is greater than 400mm above finished ground level
• External walls
The exposed components of external walls shall be as follows:
(a) made of non-combustible materials (e.g. full masonry, brick veneer etc.) with a
minimum thickness of 90 mm, or
(b) timber logs with a density of 680 kg/m3 and a minimum nominal thickness of 90mm;
or
(c) cladding that is fixed externally to a timber or metal frame and is:
(i) non-combustible; or
(ii) fibre cement a minimum of 6mm thick; or
(iii) bushfire-resisting timber.
• Joints
All joints in the external surface material of walls shall be covered, sealed, overlapped,
backed or butt-jointed.
Vents and weepholes
Vents and weepholes in external walls are to be screened with corrosion-resistant steel,
bronze or aluminium mesh with a maximum aperture of 2 mm.
External glazed elements, assemblies and doors
• Screens for windows and doors
Max Bushfire Protection Consulting 59
Page 60
Bushfire Report
Where fitted, screens for windows and doors shall have mesh or perforated sheet made of
corrosion-resistant steel, bronze or aluminium with a maximum aperture of 2 mm, with
framing made from metal or bushfire resisting timber.
• Windows
Frame material for windows are to be made from bushfire-resisting timber, metal or metal-
reinforced uPVC.
Glazing is to be toughened glass with a minimum thickness of 5 mm.
The openable portions of windows shall be screened with a mesh with a max aperture of 2
mm made of corrosion resistant steel, bronze or aluminium.
• Doors - side hung external doors, panel fold & sliding doors
Doors- shall be completely protected externally by a screen with a mesh with a max aperture
of 2mm made of corrosion resistant steel, bronze or aluminium, OR
Door panel material shall be:
(a) non-combustible; or
(b) solid timber, laminated timber or reconstituted timber, having a minimum thickness of
35 mm for the first 400 mm above the threshold; or
(c) fully framed glazed door panels with framing made from metal, bushfire resisting
timber or uPVC.
Door frames shall be made from metal bushfire resisting timber, metal or metal reinforced
uPVC.
Where doors incorporate glazing, the glazing shall be toughened glass with a minimum
thickness of 6mm.
Doors shall be tight fitting to the door frame and to an abutting door, if applicable.
Weather strips, draught excluders or draught seals shall be installed.
There is no requirement to screen the openable part of a door at this level.
• Garage doors
Vehicle access doors shall be made from:
(i) non-combustible material; or
(ii) bushfire-resisting timber; or
(iii) fibre-cement sheet, a minimum of 6 mm in thickness; or
(iv) a combination of any of items (i), (ii) or (iii) above.
All vehicle access doors to be protected with suitable weather strips, draught excluders,
draught seals or brushes.
Max Bushfire Protection Consulting 60
Page 61
Bushfire Report
• Roofs
The following apply to all types of roofs and roofing systems:
(a) roof tiles, roof sheets and roof covering accessories shall be non-combustible,
(b) the roof/wall and roof/roof junction shall be sealed, or otherwise protected to prevent
openings greater than 2mm,
(c) roof ventilation openings, such as gable and roof vents, shall be fitted with ember
guards made of non-combustible material or a mesh or perforated sheet with a max aperture
of 2mm made of corrosion resistant steel, bronze or aluminium.
(d) A pipe or conduit that penetrates the roof covering shall be non-combustible
Tiled roofs shall be fully sarked with the sarking covering the entire roof area including ridges
and hips and extend into gutters and fascias.
Sheet roofs shall:
(a) be fully sarked with sarking, except that foil backed insulation blankets may be
installed over battens; OR
(b) have any gaps sealed at the fascia, or wall line, hips and ridges by:
(i) a mesh or perforated sheet with a maximum aperture of 2 mm, made of corrosion-
resistant steel, bronze or aluminium, or
(ii) mineral wool, or
(iii) other non-combustible material, or
(iv) -a combination of any of the above.
• Roof penetrations
The following apply to roof penetrations:
(a) roof penetrations, including roof lights, roof ventilators, roof-mounted evaporative
cooling units, aerials, vent pipes and supports for solar collectors, shall be sealed. Sealing
material is to be non-combustible.
(b) openings in vented roof lights, roof ventilators or vent pipes shall be fitted with ember
guards made from a mesh or perforated sheet with a maximum aperture of 2 mm, made of
corrosion-resistant steel, bronze or aluminium.
(c) all overhead glazing shall be Grade A safety glass complying with AS 1288.
(d) flashing elements shall be non-combustible.
• Eaves linings, fascias and gables
The following apply to eaves linings, fascias and gables:
(a) gables shall comply with requirements for walls.
Max Bushfire Protection Consulting 61
Page 62
Bushfire Report
(b) fascias and bargeboards shall be made from bushfire-resisting timber or metal.
(c) eave linings shall be fibre-cement sheet with a minimum thickness of 4.5mm or
bushfire resisting timber.
(d) eave penetrations shall be protected as for roof penetrations.
(e) eaves ventilation openings are to be fitted with ember guards and be made of
corrosion resistant steel, bronze or aluminium.
(f) joints in eave linings, fascias and gables may be sealed with plastic joining strips or
timber storm moulds.
• Gutters and downpipes
The Standard does not provide material requirements for gutters and downpipes, with the
exception of box gutters.
Box gutters are to be non-combustible and flashed at the roof junction with non-combustible
material.
If installed, gutter and valley leaf guards are to be non-combustible.
• Verandas, decks, steps, ramps and landings
Decking may be spaced. There is no requirement to enclose the subfloor spaces of
verandas, decks, steps, ramps or landings.
Decking, stair treads, trafficable surfaces of ramps and landings, balustrades and handrails
are to be made from:
(a) of non-combustible material; or
(b) of bushfire-resisting timber; or
(c) a combination of items (a) and (b) above.
Verandah posts shall be made from non-combustible material or bushfire-resisting timber.
• Water and gas supply pipes
Above ground, exposed water and gas supply pipes shall be metal. The metal pipe shall
extend a minimum of 400mm within the building and 100mm below the ground.
Max Bushfire Protection Consulting 62
Page 63
Bushfire Report Max Bushfire Protection Consulting 63 [OCR of page images] Bushfire Report www.ma xbp.com.: AS 3959:2018 116 APPENDIX F BUSHFIRE-RESISTING TIMBER (Normative) Fl GENERAL Bushfire-resisting timber is timber that is in solid, laminated or reconstituted form and has been tested and is deemed to be acceptable to withstand exposure up to a BAL—29 condition. Timber may be ‘bushfire-resisting’ by means of one or more of— (a) the inherent properties of the material itself; (b) being impregnated with fire-retardant chemicals; or (c) the application of fire-retardant coatings or substrates. F2 TESTING The following applies: (a) To satisfy the requirements for bushfire-resisting timber, timber shall be tested in accordance with AS/NZS 3837 and shall meet the following criteria: (i) | The maximum heat release rate shall be not greater than 100 kW/m’. (ii) The average heat release rate for 10 minutes following ignition shall be not greater than 60 kW/m? when the material is exposed to an irradiance level of 25 kW/m". (b) Where the timber has been altered by chemicals, the test samples shall be subjected to the regime of accelerated weathering described in Paragraph F3 except that where the timber is protected from the weather, as described in the AS 1684 series (for example, cladding protected by a veranda), accelerated weathering of the test samples is not required before being tested to AS/NZS 3837. External timbers are deemed to be protected if they are covered by a roof projection (or similar) at 30 degrees or greater to the vertical and they are well detailed and maintained (painted or stained and kept well ventilated). NOTE: The purpose of testing is to assess timber performance rather than to simulate a bushfire. The irradiance set for the test is not to be considered to be correlated to the BAL. F3) ACCELERATED WEATHERING Where accelerated weathering is required before testing to AS/NZS 3837, external fire- retardant-coated substrates shall be subjected to the ASTM D2898 Method B weathering regime, with the water flow rate modified to be the same as that within ASTM D2898 Method A. NOTE: Accelerated weathering does not account for mechanical wear and tear within trafficable areas and care should be exercised when using coating materials. F4 BUSHFIRE-RESISTING SPECIES The species listed in Table Fl have been tested and have met the requirements of Paragraph F2. © Standards Australia www.standards.org.au 117 AS 3959:2018 TABLE Fi BUSHFIRE-RESISTANT SPECIES Standard trade name Botanical name Ash, silvertop Eucalyptus sieberi Blackbutt Eucalyptus pilularis Gum, ted, river Eucalyptus camaldulensis Gum, spotted Corymbia maculata Ironbark, red Eucalyptus sideroxylon Kwila (Merbau) Inisia bijuga Turpentine Syncarpia glomulifera Max Bushfire Protection Consulting 63