Council archive · source document
Capital Program 2024/2025 Delivery Status · Report
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
8.1 CAPITAL PROGRAM 2024/2025 DELIVERY STATUS
Author Director Infrastructure Services, Shaun Walsh
Infrastructure Services Department
Index ECM/ Subject/ 2024 - 2025 Annual Capital Works Program
Attachments 1. Attachment 1 - Capital Program Delivery Status
EXECUTIVE SUMMARY
• This report provides a status update for the Capital Works Program as at 30 June 2025, and
excludes disaster recovery projects.
• The approved capital budget provision for the 2024/25 financial year following Budget Review 2
was $46m, inclusive of carry forwards of $22.4m.
• Actual expenditure achieved for the 2024/25 financial year was $28.8m (62.5% of budget) with
an expected carry over to address multiyear projects and commitments.
• The 2024/25 financial year actual spend reflects solid project delivery despite challenges
including resourcing and adverse weather and is consistent with previous years.
• In the 2024/25 financial year, the Capital Works Program consisted of 140 projects at various
stages of planning, design and delivery.
• The grant funding revenue for the 2024/25 financial year was $11.7m, with Council’s contribution
to these projects being $8.4m.
• The Planning and Design teams managed 25 capital projects and provided planning and design
services to over 60 projects during Quarter 4 (Q4) of the 2024/25 financial year.
• Recruitment is underway to fill key positions in the Delivery & Design teams, with new initiatives
for additional resourcing approved through the 2025/26 budget approval process.
• The Planning, Design and Delivery teams are working closely to build on our Project
Management Framework and processes.
• Capital Works Planning for the 2025/26 financial year is complete with programming now
commenced.
RECOMMENDATION
That Council note the report by the Director Infrastructure Services to the Services & Organisation
Committee Meeting dated 12 August 2025 providing an update on the delivery of the 2024/25 Capital
Works Program as at 30 June 2025.
REPORT
This report is to inform Council of the overall status of the Capital Works Program, excluding disaster
recovery projects as at the end of June 2025, marking the end of the fourth quarter of the 2024/25
financial year.
The report provides key information relating to projects within the 2024/25 Capital Works Program
and confirms the delivery status of some projects undertaken during this quarter.
It is to be noted that the Financial Summary provided in this report is for project lifecycle progress
i.e. a major project funded over multiple years, and which commenced in an earlier financial year,
may be significantly further progressed than the 2024/25 financials indicate.
Current Financial Year Projects
The 2024/25 financial year Capital Works Program consisted of 140 projects in various stages of
delivery.
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalFull text of the other 7 pages
Page 2
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
Figure 1: Capital Works Program projects by stage of delivery
Major Projects
Major projects that achieved substantial progress or reached significant milestones during Q4 of the
2024/25 financial year included:
• Cooroy, Lake Macdonald Drive Residential Subdivision – Revised design complete
• Sunrise Beach, 56 Low Way Retaining Wall – Reached completion
• Sunshine Beach, Ed Webb Park Upgrade – Stage 2 (grant milestone) reached completion
• Tewantin, 74 Goodchap Street – Reached completion
See Attachment 1 for photos of completed projects during Q4 of the 2024/25 financial year.
Emergent Projects
Emergent projects approved by Capital Works Executive (CWE) during Q4 2024/25 included:
• Noosaville, Gympie Terrace & Noosa Heads Lighting Replacement - $25,000
Variations
Variations to projects approved by Capital Works Executive (CWE) during Q4 2024/25 included:
• Tewantin, Admin Building – Replace Main Air condenser ($30,000 for increased scope of work)
• Doonan – Waste Recovery & Landfill – 561 WHS & Environmental ($80,000 realignment of
funding from North Batter Solar)
Tenders
Review of tenders for major projects during Q4 2024/25 included:
• Cooroy, Lake Macdonald Drive, Residential Subdivision
Upcoming tenders planned for Quarter 1 (Q1) 2025/26 include:
• Doonan, Landfill, Missing Batter Capping
Page 3
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
• Doonan, Noosaville/Eumundi Road Landfill Expansion of RRA
• Kin Kin, Wahpunga (Trail 4) & Woondum (Trail 3) Trail Renewal - Trail Works, Civil Works and
Fencing, Gates & Signposts
• Noosa Heads, Cooyar Street, Stormwater Bio-basin Upgrade Detailed Design
Major Programs
The below summary provides an update on a selection of major programs within the 2024/25 Capital
Works Program.
Reseal Program
The Road Reseal Program has expended $5.1m of the $5.1m budget. The following roads on the
annual reseal program were undertaken during Q4 2024/25:
• Cooran, Railway Road (to Coles Creek Road)
• Noosaville, Elizabeth Street (Roundabout at James Street)
• Noosaville, James Street (Gympie Terrace to Elizabeth Street)
• Peregian Beach, David Low Way (from Lorikeet Drive heading south)
• Sunrise Beach, Wollomia Way (from #35)
The following roads on the 2025/26 annual reseal program were undertaken during Q4 2024/25:
• Noosaville, Eenie Creek Road (Reef Street to back of Sternlight Street)
Heavy Patching Program
The Road Heavy Patching Program has expended $1.4m of the $1.5m budget. The following roads
received patching during Q4 2024/25:
• Black Mountain, Black Mountain Road
Pathway Program
The Shire Wide Pathway Program continued into Q4 of the 2024/25 financial year. Pathway
renewals completed during Q4 included:
• Cooroy, Kauri Street
• Noosaville, Quota Park
• Noosa Heads, Seagull Park
• Shire Wide - Pathway Renewal Program:
1. Noosa Heads, Alex Dan Park
2. Noosaville, Gympie Terrace
3. Tewantin, Moorindil Street
The following pathways have had their design completed during Q4 2024/25 and have been
reprofiled for construction to be undertaken within the 2025/26 financial year.
• Pomona, Summit Road
• Shire Wide - Pathway Renewal Program
• Cooran, Bridge Street
• Cooroy, Diamond Street
• Noosa Heads, Noosa Parade
Page 4
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
• Tewantin, Sheild Street/Werin Street
• Tewantin, Waratah Close
• Tewantin, Yellowwood Drive/McKinnon Drive
Noosa Biosphere Trails
Upgrade works on the Noosa Biosphere Trails have continued through Q4 of 2024/25. Works are
still ongoing on:
• Twin Hills, Wahpunga Trail – disaster landslip works (Expected completion Q2 2024/25)
• Cooran to Kin Kin, Woondum Trail (Trail 3)
• Kin Kin to Lake Macdonald Wahpunga Trail (Trail 4) - Renewal
Planning is ongoing on the following trails:
• Boreen Point to Tewantin, Cooroibah Trail
• Lake McDonald to Peregian Beach, New Weyba Trail
• Pomona to Cooroy, Kurui Trail – Renewal
See Attachment 1 for photos of completed trails works completed during Q4.
Planning and Design
The Infrastructure Planning team had a busy quarter with preparation for the 2025/26 financial year
Capital Works Program and Council endorsement of the Noosaville Foreshore Infrastructure
Masterplan being the key focus.
In addition to the above, the Planning and Design teams are currently managing over 25 Capital
projects and have provided planning and design services to over 60 projects in the 2024/25 financial
year.
The following projects have been in various stages of planning and design during Q4:
• Local Government Infrastructure Plan update – Progressing with strategic planning coordination
• Noosaville Foreshore Master Plan – Council endorsement received with planning works ongoing
• Noosa Heads, Noosa Woods Jetty Upgrade Investigation
• Noosa Heads, Main Beach Seawall Design
• Noosa, Noosa Drive Footpath and Boardwalk – Preliminary Design Completed
• Noosaville, Noosaville Foreshore Changing Places
• Noosaville, Weyba Reef Roundabout Design – Concept Design Completed
• Peregian Beach, Coastal Pathway Stage 1
• Cooyar St Bio-basin
• Landscape Infrastructure Manual
• Gympie Terrace Revetment Wall Grant Application
• Noosa Entry Signage Guidelines
• Hilton Esplanade Active St, Stormwater and Living Foreshore Upgrades
• Shire Wide, Bus Stop Program – Design nearing completion on the final bus stop in the 10-year
PTAIP program
• Shire Wide, Pathway Program
• Various trail projects
Page 5
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
• Various stormwater quality (water sensitive urban design) and slope stability investigation
projects
The Design Services Surveyor is supporting the reseal program, waste projects and bus stop and
footpath program with ongoing survey services across the organisation.
Outside of the Capital Works Program, the Planning and Design team have provided support to Civil
Operations, Traffic, Parks and Gardens, Development Assessment, Customer Experience, Strategic
Planning, Community and the CEOs office this quarter.
As our focus shifts to the 2025/26 financial year Capital Works Program, the Planning and Design
team are working closely with the Project Management team to build on our framework and
processes.
Link to Corporate Plan
Theme No. 2. - Liveability
Liveability encompasses housing, facilities and services, transport, health and wellbeing to enable
an inclusive, connected and vibrant community.
Objective 2.7
Fund and deliver sustainable assets and facilities and associated services responding to the
changing needs of the community and the challenges and opportunities of the future.
Previous Council Consideration
Nil.
Finance
The year end capital delivery expenditure as at 30 June 2025 was $28.8m or 63% of the $46m
approved 2024/25 financial year Capital Works Program budget (BR2).
Budget Review 1 will be conducted in Q1 of the 2025/26 financial year, where there is an anticipated
carryover to support ongoing multiyear projects and commitments within the 2024/25 Capital Works
Program.
Table 1 below demonstrates the approved budget and actual expenditure for the 2024/25 financial
year.
CWP Budget 2024/25
Approved Budget $46,040,296
Actuals Year to Date $28,811,592
Table 1 – Capital Finance data as at 30 June 2025
Grant Funding
The 2024/25 financial year Capital Works Program includes an unprecedented amount of grant
funding.
Figures 2 and 3 below demonstrate the non-grant funded capital projects compared to projects with
grant funding, as well as Council’s contribution towards grant funded projects.
Page 6
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
Figure 2 detail Percentage of CWP Value of CWP
Non-Grant funded Projects 56% $25.8m
Projects with Grant Funding 44% $20.2m
Figure 2 – Projects with and without grant funding.
Percentage of
Figure 3 detail Value of CWP
CWP
Non-Grant funded Projects 56% $25.8m
Grant funding revenue 26% $11.7m
Council's contribution to projects with grant funding 18% $8.4m
Figure 3 – Projects by funding source
Page 7
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
Risk & Opportunities
Q4 has presented several challenges and opportunities for Council. Despite facing constraints such
as weather and resourcing,, there has been significant progress in various areas. Below are the key
highlights:
• Staff shortages constrained the Design & Delivery teams to undertake and complete the 2024/25
Capital Works Program; however teams have worked hard to achieve high level results.
• The 2024/25 financial year has ended with a strong actual spend given the range of challenges
faced. Despite pressures of staffing shortages and budget constraints, Council has maintained
solid project delivery and investment performance consistent with previous years
• The Planning, Design and Delivery teams are collaborating closely to build on our Project
Management Framework and improve associated processes.
• Recruitment is underway to fill key positions in the Delivery & Design teams, with an additional
5 new initiatives for resources being requested through the 2025/26 budget approval process to
improve capacity for project delivery
• Capital Works Planning for the 2025/26 financial year is complete with programming now
commenced.
• Quarter 4 of the 2024/25 financial year saw the finalisation of the 2025/26 capital works program,
with two councillor workshops undertaken and the draft Program agreed for adoption.
• The Capital Works Program and budget for the 2025/26 financial year has focused on achievable
deliverables, while investigating innovative delivery models.
Human Rights
Human Rights Compatibility Statement
In developing this Report, the subject matter has been considered in accordance with the
requirements of the Queensland Human Rights Act 2019. It is considered that the subject matter
does not conflict with any human rights and supports a human rights approach to decision making
by Council. Council representatives will endeavour to act and make decisions under this report in a
manner that is compatible with human rights. This report should be read in conjunction with
Council’s Human Rights Policy.
Consultation
External Consultation - Community & Stakeholder
Nil.
Internal Consultation
Departments consulted:
Office of the CEO, Mayor & Community Services Corporate Services
Councillors
Mayor & Councillors Director Director
Chief Executive Officer Community Development x Financial Services
Executive Officers x Sport & Active Lifestyles Fleet
Community Engagement x Arts & Culture Revenue Services
People & Culture Community Connection ICT
Governance Customer Experience Procurement
Page 8
SERVICES & ORGANISATION COMMITTEE MEETING 12 AUGUST 2025
Commercial Property
Strategy & Environment Development & Regulation Infrastructure Services
Director Director x Director
Strategy & Sustainability Development Assessment x Infrastructure Planning, Design
and Delivery
Economic Development & Local Laws x Civil and Asset operations
Destination Management
Environmental Services Environmental Health x Waste
Innovation & Digital Hub Building & Plumbing x Building & Facilities
Property / Permits Disaster Management
Used in these records
Capital Program 2024/2025 Delivery Status · ReportReportsMeeting 891 · read item & discussion ↗
About this file
- File size
- 278 KB (small file)
- File type
No other editions are linked here.