1.0 INTRODUCTION
This Environmental Management Plan (EMP) has been prepared for the Noosa Bunnings.
The EMP is the essential link between environmental impacts assessment and project
activities. It is to ensure that environmental impacts identified during the assessment stage
are properly managed on site and control measures are implemented.
1.1 PROJECT DESCRIPTION
The works are located on Gateway Dr and Eumundi-Noosa Rd, Noosaville in the local
government area of the Sunshine Coast Regional Council.
The works comprises the building of the Noosa Bunnings store, as well as reconfiguration of
the Rene St round-a-bout and Gateway Drive entrance. The works are shown and described
in the Drawings (attached in the appendices), and will be constructed in accordance with the
requirements set out in the Drawings and specifications provided with the design
documentation.
The main activities to be carried out during the project are:
• Bulk Earthworks
• Round-a-bout Roadworks
1.2 OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLAN
The EMP outlines the environmental controls applying to the pre-works, during works and
post works activities associated with the Project. It has been developed based on
information for hte site provided by the client and general environmental requirements which
apply to most construction projects and also incorporates project specific environmental
sensitive work practices.
The general objectives of this EMP include to:
• Reduce or eliminate the release of pollutants to the environment;
• Reduce waste and resource depletion by utilising recycling principles where practical;
• Document all environmental management activities, including verification and
corrective actions;
• Implement and effective program for monitoring of environmental issues relating to
the Contractor's role in the project;
• Promote environmental awareness among employees;
• Support ecologically sustainable development;
• Protect and enhance the aesthetic environment;
• Minimise impacts on the local community during works;
The EMP is a working document to be updated as necessary.
Document No: OMS-EMP-C • Authonsed by Blacklaw Cwd Contractors Head Office Telephone 2 '300
Date _z a^ 20'1 aqe 'eat "I" Raun) ABN 77 106 50 724 100 Sandalwood Lane Facsimile -
Vernon: Author Forest Glen OLD 4556 office@blacklawcaalcomau
Next Review.:. a' 20' _ ' a <: ,`arrant
Page 2 of 20
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Amended Plans for approval - Bunnings WarehouseRelated documentApplication case desk ↗
About this file
- File size
- 57.8 MB (very large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.