            ENVIRONMENTAL MANAGEMENT PLAN (EMP)
            Noosa Bunnings


            1.0       INTRODUCTION

            This Environmental Management Plan (EMP) has been prepared for the Noosa Bunnings.

            The EMP is the essential link between environmental impacts assessment and project
            activities. It is to ensure that environmental impacts identified during the assessment stage
            are properly managed on site and control measures are implemented.

            1.1       PROJECT DESCRIPTION

            The works are located on Gateway Dr and Eumundi-Noosa Rd, Noosaville in the local
            government area of the Sunshine Coast Regional Council.

            The works comprises the building of the Noosa Bunnings store, as well as reconfiguration of
            the Rene St round-a-bout and Gateway Drive entrance. The works are shown and described
            in the Drawings (attached in the appendices), and will be constructed in accordance with the
            requirements set out in the Drawings and specifications provided with the design
            documentation.

            The main activities to be carried out during the project are:

                  •   Bulk Earthworks
                  •   Round-a-bout Roadworks

            1.2       OBJECTIVES OF THE ENVIRONMENTAL MANAGEMENT PLAN

            The EMP outlines the environmental controls applying to the pre-works, during works and
            post works activities associated with the Project. It has been developed based on
            information for hte site provided by the client and general environmental requirements which
            apply to most construction projects and also incorporates project specific environmental
            sensitive work practices.

            The general objectives of this EMP include to:

                  •   Reduce or eliminate the release of pollutants to the environment;
                  •   Reduce waste and resource depletion by utilising recycling principles where practical;
                  •   Document all environmental management activities, including verification and
                      corrective actions;
                  •   Implement and effective program for monitoring of environmental issues relating to
                      the Contractor's role in the project;
                  •   Promote environmental awareness among employees;
                  •   Support ecologically sustainable development;
                  •   Protect and enhance the aesthetic environment;
                  •   Minimise impacts on the local community during works;

            The EMP is a working document to be updated as necessary.




Document No: OMS-EMP-C •     Authonsed by               Blacklaw Cwd Contractors   Head Office             Telephone         2 '300
Date _z a^ 20'1                  aqe 'eat "I" Raun)     ABN 77 106 50 724          100 Sandalwood Lane     Facsimile       -
Vernon:                      Author                                                Forest Glen OLD 4556    office@blacklawcaalcomau
Next Review.:. a' 20' _               ' a <: ,`arrant
                                                                                                                         Page 2 of 20

Used in these records

About this file

File size
57.8 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Amended Plans for approval - Bunnings Warehouse.pdf · 57.8 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.