Applicant's Information Response

of 13
With regard to item 17, it should be noted that the location of the proposed structures at the front of
the site are consistent with those previously approved by Council. Council will recall that originally the
booster pump was approved directly on the property boundary but its relocation to its current position
was approved as part of minor change application MCU17/0014.01.

Similarly, a padmont was shown on the approved drawings but was located on the western side of the
frontage. The current location was discussed informally with Council and it was accepted that it was
generally in accordance with the original approval.

With regard to sight distances, the sighlines shown on A6035/21/R04 in the Engineering Plans shows
that as these are setback at least 3m from the property boundary , they will not adversely affect the
ability of pedestrians to see vehicles leaving the site. The visibility of the vehicles leaving the site will also
be improved given that the exit from parking area will be more than 1m above the footpath.

Consistent with the current approval it is proposed that the subdued muted colours will be used for
these external structures, where possible. It is anticipated that Council will include a condition to this
effect.

An elevation has now been included in the Landscape Plan to illustrate the landscape outcome at the
front of the site. The elevation shows how the landscaping will screen the booster cabinet from the
street. Due to Energex’s access requirements, it is not possible to plant in front of the pad mount so the
landscape plans show dense planting on its eastern and western sides, consistent with condition 47 of
MCU17/0014.02, to screen it as far as possible.

Council Issue – Waste Collection

“It is not clear how waste collection will be managed.”

Information Required

    18. Provide a detailed Waste Management Plan, which must include detail, but not be limited
        to the following:
            a. Number and type of bins to be collected;
            b. Location of where bins are to be collected;
            c. Wash bin area (which is to be connected to sewer infrastructure);
            d. Type of vehicle required for the collection;
            e. Provide travel paths for the required waste collection vehicle, demonstrating how
                it will manoeuvre on site without having to use more than a 3 point turn to turn
                around.

Applicant’s Response
Additional information has been added to Proposal Plan 20531 SD01 to confirm the number and type
of bins required on site and to illustrate that these can be accommodated on site.

Consistent with the approach accepted as part of MCU17/0114, the bins will be moved to the frontage
with Sidoni Lane on collection days to be emptied.

The Proposal Plans confirm that the bin enclosure will include a bin wash area which will be connected
to the sewer infrastructure.

The bins will be collected by a standard waste collection vehicle and a swept path that demonstrates
that this size vehicle will be able to collect the bins from Sidoni Lane, is provided on drawing
A6035/21/R07 in the Engineering Plans.

Council Issue – Earthworks

“The submitted information indicates that approximately 2,300m3 of material is to be excavated and
carted off site and that the carpark finished surface level is RL 5.7m (i.e. the excavated level, for
foundations and slab construction, is expected to be below RL 5.0m).

Log in to download the original (Applicant's Information Response.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.