INFINITY Noosaville Tender Programme Rev. A
ID Task Name Duration Start Finish
November December January February March April May June July August September October November
21 Oct '19 28 Oct '19 4 Nov '19 11 Nov '19 18 Nov '19 25 Nov '19 2 Dec '19 9 Dec '19 16 Dec '19 23 Dec '19 30 Dec '19 6 Jan '20 13 Jan '20 20 Jan '20 27 Jan '20 3 Feb '20 10 Feb '20 17 Feb '20 24 Feb '20 2 Mar '20 9 Mar '20 16 Mar '20 23 Mar '20 30 Mar '20 6 Apr '20 13 Apr '20 20 Apr '20 27 Apr '20 4 May '20 11 May '20 18 May '20 25 May '20 1 Jun '20 8 Jun '20 15 Jun '20 22 Jun '20 29 Jun '20 6 Jul '20 13 Jul '20 20 Jul '20 27 Jul '20 3 Aug '20 10 Aug '20 17 Aug '20 24 Aug '20 31 Aug '20 7 Sep '20 14 Sep '20 21 Sep '20 28 Sep '20 5 Oct '20 12 Oct '20 19 Oct '20 26 Oct '20
S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
1 19116 - INFINITY NOOSA TENDER PROGRAM 266 days Mon 5/08/19 Tue 1/09/20 19116 - INFINITY NOOSA TENDER PROGRAM
2 TENDER 54 days Mon 5/08/19 Mon 21/10/19 TENDER
3 Tender Released 0 days Mon 5/08/19 Mon 5/08/19
4 Tender Period 24 days Mon 5/08/19 Fri 6/09/19
5 Tender Due 0 days Fri 6/09/19 Fri 6/09/19
6 Tender Review 5 days Mon 9/09/19 Fri 13/09/19
7 VE Period 25 days Mon 16/09/19 Mon 21/10/19 VE Period
8 Contract Award 0 days Mon 21/10/19 Mon 21/10/19 21/10 Contract Award
9 KEY DATES 5 days Fri 1/11/19 Thu 7/11/19 KEY DATES
10 Hunter issue McNab Letter of Prefered Contractor 0 days Fri 1/11/19 Fri 1/11/19 1/11 Hunter issue McNab Letter of Prefered Contractor
11 Develop Build Contract 5 days Fri 1/11/19 Thu 7/11/19 Develop Build Contract
12 Hunter and McNab Execute Build Contract 0 days Thu 7/11/19 Thu 7/11/19 7/11 Hunter and McNab Execute Build Contract
13 McNab engage Consultant Team 0 days Thu 7/11/19 Thu 7/11/19 7/11 McNab engage Consultant Team
14 DESIGN 72 days Tue 22/10/19 Thu 13/02/20 DESIGN
15 DOCUMENTATION 46 days Fri 8/11/19 Fri 24/01/20 DOCUMENTATION
16 Client Design workshop 3 days Fri 8/11/19 Tue 12/11/19 Client Design workshop
17 Consultant Agreements & Receive DWG files 10 days Fri 8/11/19 Thu 21/11/19 Consultant Agreements & Receive DWG files
18 DESIGN DEVELOPMENT 11 days Fri 8/11/19 Fri 22/11/19 DESIGN DEVELOPMENT
26 HOLD POINT 1 5 days Mon 25/11/19 Fri 29/11/19 HOLD POINT 1
28 FOR TENDER DOC'S 15 days Mon 2/12/19 Fri 20/12/19 FOR TENDER DOC'S
36 HOLD POINT 2 5 days Mon 6/01/20 Fri 10/01/20 HOLD POINT 2
38 FOR CONSTRUCTION DOC'S 10 days Mon 13/01/20 Fri 24/01/20 FOR CONSTRUCTION DOC'S
47 APPROVALS 72 days Tue 22/10/19 Thu 13/02/20 APPROVALS
48 QFES 40 days Wed 13/11/19 Tue 21/01/20 QFES
49 Develop Fire Engineering Brief 5 days Wed 13/11/19 Tue 19/11/19 Develop Fire Engineering Brief
50 Review Brief 2 days Wed 20/11/19 Thu 21/11/19 Review Brief
51 Finalise Fire Engineer Report 5 days Fri 22/11/19 Thu 28/11/19 Finalise Fire Engineer Report
52 Review Report 2 days Fri 29/11/19 Mon 2/12/19 Review Report
53 Lodge QFES 1 day Tue 3/12/19 Tue 3/12/19 Lodge QFES
54 QFES reivew 25 days Wed 4/12/19 Tue 21/01/20 QFES reivew
55 QFES approval 0 days Tue 21/01/20 Tue 21/01/20 21/01 QFES approval
56 OP Works (Standard Time) 52 days Fri 25/10/19 Mon 20/01/20 OP Works (Standard Time)
57 Condition 17 - Landscapeing Works 43 days Fri 25/10/19 Tue 7/01/20 Condition 17 - Landscapeing Works
58 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
59 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
60 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
61 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
62 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
63 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
64 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
65 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
66 Condition 25 - External Frontage Works 43 days Fri 25/10/19 Tue 7/01/20 Condition 25 - External Frontage Works
67 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
68 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
69 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
70 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
71 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
72 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
73 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
74 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
75 Condition 30 - Access Works 43 days Fri 25/10/19 Tue 7/01/20 Condition 30 - Access Works
76 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
77 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
78 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
79 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
80 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
81 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
82 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
83 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
84 Condition 31 - Car Parking 43 days Fri 25/10/19 Tue 7/01/20 Condition 31 - Car Parking
85 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
86 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
87 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
88 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
89 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
90 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
91 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
92 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
93 Condition 33 - Stormwater Drainage 43 days Fri 25/10/19 Tue 7/01/20 Condition 33 - Stormwater Drainage
94 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
95 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
96 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
97 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
98 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
99 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
100 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
101 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
102 Condition 37 - Earthworks and Retaining Walls 43 days Fri 25/10/19 Tue 7/01/20 Condition 37 - Earthworks and Retaining Walls
103 Lodgement 1 day Fri 25/10/19 Fri 25/10/19 Lodgement
104 Fees Paid 1 day Tue 29/10/19 Tue 29/10/19 Fees Paid
105 Council Review Period 25 days Wed 30/10/19 Tue 3/12/19 Council Review Period
106 Earliest Possiable Approval Date 0 days Tue 3/12/19 Tue 3/12/19 3/12 Earliest Possiable Approval Date
107 RFI Issued 0 days Tue 3/12/19 Tue 3/12/19 3/12 RFI Issued
108 RFI Response 5 days Wed 4/12/19 Tue 10/12/19 RFI Response
109 RFI Assessment Period 10 days Wed 11/12/19 Tue 7/01/20 RFI Assessment Period
110 Approval 0 days Tue 7/01/20 Tue 7/01/20 7/01 Approval
111 Condition 43 - Construction Management Plan 48 days Thu 31/10/19 Mon 20/01/20 Condition 43 - Construction Management Plan
112 Draft CMP and TMP 5 days Thu 31/10/19 Wed 6/11/19 Draft CMP and TMP
113 Lodgement 1 day Fri 15/11/19 Fri 15/11/19 Lodgement
114 Fees Paid 1 day Mon 18/11/19 Mon 18/11/19 Fees Paid
115 Council Review Period 20 days Tue 19/11/19 Mon 16/12/19 Council Review Period
116 Earliest Possiable Approval Date 0 days Mon 16/12/19 Mon 16/12/19 16/12 Earliest Possiable Approval Date
117 RFI Issued 0 days Mon 16/12/19 Mon 16/12/19 16/12 RFI Issued
118 RFI Response 5 days Tue 17/12/19 Mon 6/01/20 RFI Response
119 RFI Assessment Period 10 days Tue 7/01/20 Mon 20/01/20 RFI Assessment Period
120 Approval 0 days Mon 20/01/20 Mon 20/01/20 20/01 Approval
121 OP works approval 0 days Mon 20/01/20 Mon 20/01/20 20/01 OP works approval
122 Plumbing Compliance 70 days Tue 22/10/19 Tue 11/02/20 Plumbing Compliance
123 Stage 1 - Plumbing Approval (basement) 26 days Tue 22/10/19 Tue 26/11/19 Stage 1 - Plumbing Approval (basement)
124 Submit Plumbing Compliance 1 day Tue 22/10/19 Tue 22/10/19 Submit Plumbing Compliance
125 Plumbing Compliance Assessment Period 25 days Wed 23/10/19 Tue 26/11/19 Plumbing Compliance Assessment Period
126 Plumbing Compliance 0 days Tue 26/11/19 Tue 26/11/19 26/11 Plumbing Compliance
127 Stage 2 - Plumbing Approval 26 days Mon 6/01/20 Tue 11/02/20 Stage 2 - Plumbing Approval
128 Submit Plumbing Compliance 1 day Mon 6/01/20 Mon 6/01/20 Submit Plumbing Compliance
129 Plumbing Compliance Assessment Period 25 days Tue 7/01/20 Tue 11/02/20 Plumbing Compliance Assessment Period
130 Plumbing Compliance 0 days Tue 11/02/20 Tue 11/02/20 11/02 Plumbing Compliance
131 Building Approval 48 days Mon 25/11/19 Thu 13/02/20 Building Approval
132 Stage 1 BA 11 days Mon 25/11/19 Mon 9/12/19 Stage 1 BA
133 Lodge Application 1 day Mon 25/11/19 Mon 25/11/19 Lodge Application
134 Building Approval Review & Assessment 10 days Tue 26/11/19 Mon 9/12/19 Building Approval Review & Assessment
135 Building Approval 0 days Mon 9/12/19 Mon 9/12/19 9/12 Building Approval
136 Stage 2 BA 33 days Mon 16/12/19 Thu 13/02/20 Stage 2 BA
137 Lodge Application 1 day Mon 16/12/19 Mon 16/12/19 Lodge Application
138 Building Approval Review & Assessment 20 days Tue 17/12/19 Tue 28/01/20 Building Approval Review & Assessment
139 Building Approval 0 days Thu 13/02/20 Thu 13/02/20 13/02 Building Approval
140 PROCUREMENT AND RAMP UP 204 days Fri 1/11/19 Tue 1/09/20 PROCUREMENT AND RAMP UP
141 SITE PLANNING 204 days Fri 1/11/19 Tue 1/09/20 SITE PLANNING
142 Obtain ENERGEX Advice on Overhead Power Lines 5 days Fri 1/11/19 Thu 7/11/19 Obtain ENERGEX Advice on Overhead Power Lines
143 ENERGEX Tiger Tails Installed 15 days Fri 8/11/19 Thu 28/11/19 ENERGEX Tiger Tails Installed
144 Traffic Management Plan Developed 3 days Fri 1/11/19 Tue 5/11/19 Traffic Management Plan Developed
145 CONSTRUCTION WORKS 157 days Tue 21/01/20 Tue 1/09/20 CONSTRUCTION WORKS
146 SITE ESTABLISHMENT 4 days Tue 21/01/20 Fri 24/01/20 SITE ESTABLISHMENT
147 Noosa Council Pre-Start Meeting 1 day Tue 21/01/20 Tue 21/01/20 Noosa Council Pre-Start Meeting
148 Install temp fence 1 day Wed 22/01/20 Wed 22/01/20 Install temp fence
149 Install temp crossovers 2 days Wed 22/01/20 Thu 23/01/20 Install temp crossovers
150 Install temp services 2 days Wed 22/01/20 Thu 23/01/20 Install temp services
151 Install Site Sheds 1 day Fri 24/01/20 Fri 24/01/20 Install Site Sheds
152 GROUND WORKS AND FOUNDATIONS 30 days Fri 24/01/20 Fri 6/03/20 GROUND WORKS AND FOUNDATIONS
153 Strip Site 1 day Fri 24/01/20 Fri 24/01/20 Strip Site
154 Bench out for basement 3 days Tue 28/01/20 Thu 30/01/20 Bench out for basement
155 Install Sheet Piles 5 days Fri 31/01/20 Thu 6/02/20 Install Sheet Piles
156 Establish dewatering Plant 5 days Fri 31/01/20 Thu 6/02/20 Establish dewatering Plant
157 Bulk Excavation 5 days Fri 7/02/20 Thu 13/02/20 Bulk Excavation
158 Detailed Excavation - Services and Lift Pit 2 days Fri 14/02/20 Mon 17/02/20 Detailed Excavation - Services and Lift Pit
159 FRP Lift Pit Walls inc SW Pump Well 3 days Tue 18/02/20 Thu 20/02/20 FRP Lift Pit Walls inc SW Pump Well
160 Detailed Excavation - Footings 1 day Tue 18/02/20 Tue 18/02/20 Detailed Excavation - Footings
161 FRP Footings 3 days Fri 21/02/20 Tue 25/02/20 FRP Footings
162 Install underslab services 2 days Fri 21/02/20 Mon 24/02/20 Install underslab services
163 Install waterproof Membrane 3 days Wed 26/02/20 Fri 28/02/20 Install waterproof Membrane
164 FRP Slab on ground 5 days Mon 2/03/20 Fri 6/03/20 FRP Slab on ground
165 STRUCTURE 67 days Mon 9/03/20 Mon 15/06/20 STRUCTURE
166 BASEMENT 5 days Mon 9/03/20 Fri 13/03/20 BASEMENT
171 LEVEL 1 45 days Fri 13/03/20 Wed 20/05/20 LEVEL 1
183 LEVEL 2 34 days Mon 6/04/20 Wed 27/05/20 LEVEL 2
192 LEVEL 3 34 days Tue 28/04/20 Mon 15/06/20 LEVEL 3
206 FAÇADE 71 days Wed 6/05/20 Tue 11/08/20 FAÇADE
207 LEVEL 1 69 days Fri 8/05/20 Tue 11/08/20 LEVEL 1
226 LEVEL 2 63 days Wed 6/05/20 Thu 30/07/20 LEVEL 2
250 LEVEL 3 37 days Thu 11/06/20 Thu 30/07/20 LEVEL 3
274 INTERNAL FIT OUT 72 days Fri 15/05/20 Fri 21/08/20 INTERNAL FIT OUT
275 BASEMENT 47 days Thu 21/05/20 Fri 24/07/20 BASEMENT
299 LEVEL 1 50 days Fri 15/05/20 Thu 23/07/20 LEVEL 1
320 LEVEL 2 45 days Mon 22/06/20 Thu 20/08/20 LEVEL 2
341 LEVEL 3 45 days Tue 23/06/20 Fri 21/08/20 LEVEL 3
362 EXTERNAL WORKS 29 days Wed 15/07/20 Fri 21/08/20 EXTERNAL WORKS
363 SOUTH 10 days Fri 31/07/20 Thu 13/08/20 SOUTH
367 EAST 8 days Fri 7/08/20 Tue 18/08/20 EAST
370 WEST 8 days Wed 12/08/20 Fri 21/08/20 WEST
373 NORTH 27 days Wed 15/07/20 Wed 19/08/20 NORTH
383 COMPLEATION MILESTONES 66 days Tue 2/06/20 Tue 1/09/20 COMPLEATION MILESTONES
384 STRUCTURE COMPLETE 0 days Tue 2/06/20 Tue 2/06/20 2/06 STRUCTURE COMPLETE
385 INTERNAL FIT OUT COMPLETE 0 days Fri 21/08/20 Fri 21/08/20 21/08 INTERNAL FIT OUT COMPLETE
386 EXTERNAL WORKS COMPLETE 0 days Wed 19/08/20 Wed 19/08/20 19/08 EXTERNAL WORKS COMPLETE
387 CLIENT INSPECTION 0 days Fri 21/08/20 Fri 21/08/20 21/08 CLIENT INSPECTION
388 Pratical Compleation 0 days Fri 21/08/20 Fri 21/08/20 21/08 Pratical Compleation
389 Delay Allowance 7 days Mon 24/08/20 Tue 1/09/20 Delay Allowance
390 Project Complete 0 days Tue 1/09/20 Tue 1/09/20 1/09 Project Complete
19116 - INFINITY Noosaville Tender Program 31.10.2019 Page 1 of 1
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Construction Mangement Plan Reference Document OPW19-0239.pdfRelated documentApplication case desk ↗