Construction Mangement Plan Reference Document OPW19-0239 · OPW19/0239

of 71

Plans and drawings: the text below has words only, no drawings.

Log in to see the plans as drawn
                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                Thu 14/11/19
                                                                                                                                                                                                                                                                                                                                                                                                INFINITY Noosaville Tender Programme                                                                                                                                                                                                                                                                                                                                                                                                                                                  Rev. A

ID        Task Name                                                  Duration       Start          Finish
                                                                                                                                        November                                                 December                                                       January                                                       February                                                 March                                                         April                                                          May                                                        June                                                         July                                                          August                                                       September                                                     October                                                     November
                                                                                                               21 Oct '19    28 Oct '19       4 Nov '19  11 Nov '19    18 Nov '19    25 Nov '19    2 Dec '19     9 Dec '19     16 Dec '19    23 Dec '19    30 Dec '19    6 Jan '20     13 Jan '20    20 Jan '20    27 Jan '20      3 Feb '20   10 Feb '20    17 Feb '20    24 Feb '20    2 Mar '20     9 Mar '20     16 Mar '20    23 Mar '20    30 Mar '20    6 Apr '20     13 Apr '20    20 Apr '20    27 Apr '20     4 May '20    11 May '20    18 May '20    25 May '20    1 Jun '20     8 Jun '20     15 Jun '20    22 Jun '20    29 Jun '20    6 Jul '20     13 Jul '20    20 Jul '20    27 Jul '20     3 Aug '20    10 Aug '20    17 Aug '20    24 Aug '20    31 Aug '20    7 Sep '20     14 Sep '20    21 Sep '20    28 Sep '20      5 Oct '20   12 Oct '20    19 Oct '20    26 Oct '20
                                                                                                             S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S M T W T F S S
     1    19116 - INFINITY NOOSA TENDER PROGRAM                      266 days   Mon 5/08/19 Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     19116 - INFINITY NOOSA TENDER PROGRAM
     2      TENDER                                                   54 days    Mon 5/08/19 Mon 21/10/19          TENDER
     3        Tender Released                                        0 days     Mon 5/08/19 Mon 5/08/19
     4        Tender Period                                          24 days    Mon 5/08/19     Fri 6/09/19
     5        Tender Due                                             0 days       Fri 6/09/19   Fri 6/09/19
     6        Tender Review                                          5 days     Mon 9/09/19 Fri 13/09/19
     7        VE Period                                              25 days    Mon 16/09/19 Mon 21/10/19         VE Period
     8        Contract Award                                         0 days     Mon 21/10/19 Mon 21/10/19 21/10   Contract Award
     9      KEY DATES                                                5 days      Fri 1/11/19   Thu 7/11/19                                            KEY DATES
     10       Hunter issue McNab Letter of Prefered Contractor       0 days       Fri 1/11/19   Fri 1/11/19                   1/11    Hunter issue McNab Letter of Prefered Contractor
     11       Develop Build Contract                                 5 days       Fri 1/11/19  Thu 7/11/19                                           Develop Build Contract
     12       Hunter and McNab Execute Build Contract                0 days      Thu 7/11/19   Thu 7/11/19                                   7/11     Hunter and McNab Execute Build Contract
     13       McNab engage Consultant Team                           0 days      Thu 7/11/19   Thu 7/11/19                                   7/11     McNab engage Consultant Team
     14     DESIGN                                                   72 days    Tue 22/10/19 Thu 13/02/20                                                                                                                                                                                                                                                     DESIGN
     15       DOCUMENTATION                                          46 days     Fri 8/11/19   Fri 24/01/20                                                                                                                                                                                                          DOCUMENTATION
     16          Client Design workshop                              3 days       Fri 8/11/19 Tue 12/11/19                                                    Client Design workshop
     17          Consultant Agreements & Receive DWG files           10 days      Fri 8/11/19 Thu 21/11/19                                                                       Consultant Agreements & Receive DWG files
     18          DESIGN DEVELOPMENT                                  11 days     Fri 8/11/19   Fri 22/11/19                                                                         DESIGN DEVELOPMENT
     26          HOLD POINT 1                                        5 days     Mon 25/11/19 Fri 29/11/19                                                                                         HOLD POINT 1
     28          FOR TENDER DOC'S                                    15 days    Mon 2/12/19 Fri 20/12/19                                                                                                                                      FOR TENDER DOC'S
     36          HOLD POINT 2                                        5 days     Mon 6/01/20 Fri 10/01/20                                                                                                                                                                              HOLD POINT 2
     38          FOR CONSTRUCTION DOC'S                              10 days    Mon 13/01/20 Fri 24/01/20                                                                                                                                                                                                            FOR CONSTRUCTION DOC'S
     47       APPROVALS                                              72 days    Tue 22/10/19 Thu 13/02/20                                                                                                                                                                                                                                                     APPROVALS
     48          QFES                                                40 days    Wed 13/11/19 Tue 21/01/20                                                                                                                                                                                                     QFES
     49             Develop Fire Engineering Brief                   5 days     Wed 13/11/19 Tue 19/11/19                                                                     Develop Fire Engineering Brief
     50             Review Brief                                     2 days     Wed 20/11/19 Thu 21/11/19                                                                        Review Brief
     51             Finalise Fire Engineer Report                    5 days      Fri 22/11/19 Thu 28/11/19                                                                                      Finalise Fire Engineer Report
     52             Review Report                                    2 days      Fri 29/11/19 Mon 2/12/19                                                                                                Review Report
     53             Lodge QFES                                       1 day       Tue 3/12/19   Tue 3/12/19                                                                                                Lodge QFES
     54             QFES reivew                                      25 days    Wed 4/12/19 Tue 21/01/20                                                                                                                                                                                                      QFES reivew
     55             QFES approval                                    0 days     Tue 21/01/20 Tue 21/01/20                                                                                                                                                                                         21/01       QFES approval
     56          OP Works (Standard Time)                            52 days     Fri 25/10/19 Mon 20/01/20                                                                                                                                                                                                OP Works (Standard Time)
     57             Condition 17 - Landscapeing Works                43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 17 - Landscapeing Works
     58                Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
     59                Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
     60                Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
     61                Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
     62                RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
     63                RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
     64                RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
     65                Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
     66             Condition 25 - External Frontage Works           43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 25 - External Frontage Works
     67                Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
     68                Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
     69                Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
     70                Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
     71                RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
     72                RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
     73                RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
     74                Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
     75             Condition 30 - Access Works                      43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 30 - Access Works
     76                Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
     77                Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
     78                Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
     79                Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
     80                RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
     81                RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
     82                RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
     83                Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
     84             Condition 31 - Car Parking                       43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 31 - Car Parking
     85                Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
     86                Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
     87                Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
     88                Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
     89                RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
     90                RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
     91                RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
     92                Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
     93             Condition 33 - Stormwater Drainage               43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 33 - Stormwater Drainage
     94                Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
     95                Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
     96                Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
     97                Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
     98                RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
     99                RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
 100                   RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
 101                   Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
 102                Condition 37 - Earthworks and Retaining Walls    43 days     Fri 25/10/19 Tue 7/01/20                                                                                                                                                                        Condition 37 - Earthworks and Retaining Walls
 103                   Lodgement                                     1 day       Fri 25/10/19  Fri 25/10/19              Lodgement
 104                   Fees Paid                                     1 day      Tue 29/10/19 Tue 29/10/19                        Fees Paid
 105                   Council Review Period                         25 days    Wed 30/10/19 Tue 3/12/19                                                                                                  Council Review Period
 106                   Earliest Possiable Approval Date              0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     Earliest Possiable Approval Date
 107                   RFI Issued                                    0 days      Tue 3/12/19   Tue 3/12/19                                                                                        3/12     RFI Issued
 108                   RFI Response                                  5 days     Wed 4/12/19 Tue 10/12/19                                                                                                                 RFI Response
 109                   RFI Assessment Period                         10 days    Wed 11/12/19 Tue 7/01/20                                                                                                                                                                        RFI Assessment Period
 110                   Approval                                      0 days      Tue 7/01/20   Tue 7/01/20                                                                                                                                                              7/01     Approval
 111                Condition 43 - Construction Management Plan      48 days    Thu 31/10/19 Mon 20/01/20                                                                                                                                                                                                 Condition 43 - Construction Management Plan
 112                   Draft CMP and TMP                             5 days     Thu 31/10/19 Wed 6/11/19                                            Draft CMP and TMP
 113                   Lodgement                                     1 day       Fri 15/11/19  Fri 15/11/19                                                        Lodgement
 114                   Fees Paid                                     1 day      Mon 18/11/19 Mon 18/11/19                                                                Fees Paid
 115                   Council Review Period                         20 days    Tue 19/11/19 Mon 16/12/19                                                                                                                            Council Review Period
 116                   Earliest Possiable Approval Date              0 days     Mon 16/12/19 Mon 16/12/19                                                                                                                   16/12    Earliest Possiable Approval Date
 117                   RFI Issued                                    0 days     Mon 16/12/19 Mon 16/12/19                                                                                                                   16/12    RFI Issued
 118                   RFI Response                                  5 days     Tue 17/12/19 Mon 6/01/20                                                                                                                                                                       RFI Response
 119                   RFI Assessment Period                         10 days     Tue 7/01/20 Mon 20/01/20                                                                                                                                                                                                 RFI Assessment Period
 120                   Approval                                      0 days     Mon 20/01/20 Mon 20/01/20                                                                                                                                                                                       20/01     Approval
 121                OP works approval                                0 days     Mon 20/01/20 Mon 20/01/20                                                                                                                                                                                       20/01     OP works approval
 122             Plumbing Compliance                                 70 days    Tue 22/10/19 Tue 11/02/20                                                                                                                                                                                                                                                  Plumbing Compliance
 123                Stage 1 - Plumbing Approval (basement)           26 days    Tue 22/10/19 Tue 26/11/19                                                                                   Stage 1 - Plumbing Approval (basement)
 124                   Submit Plumbing Compliance                    1 day      Tue 22/10/19 Tue 22/10/19          Submit Plumbing Compliance
 125                   Plumbing Compliance Assessment Period         25 days    Wed 23/10/19 Tue 26/11/19                                                                                  Plumbing Compliance Assessment Period
 126                   Plumbing Compliance                           0 days     Tue 26/11/19 Tue 26/11/19                                                                         26/11     Plumbing Compliance
 127                Stage 2 - Plumbing Approval                      26 days    Mon 6/01/20 Tue 11/02/20                                                                                                                                                                                                                                                   Stage 2 - Plumbing Approval
 128                   Submit Plumbing Compliance                    1 day      Mon 6/01/20 Mon 6/01/20                                                                                                                                                                        Submit Plumbing Compliance
 129                   Plumbing Compliance Assessment Period         25 days     Tue 7/01/20 Tue 11/02/20                                                                                                                                                                                                                                               Plumbing Compliance Assessment Period
 130                   Plumbing Compliance                           0 days     Tue 11/02/20 Tue 11/02/20                                                                                                                                                                                                                                      11/02       Plumbing Compliance
 131             Building Approval                                   48 days    Mon 25/11/19 Thu 13/02/20                                                                                                                                                                                                                                                     Building Approval
 132                Stage 1 BA                                       11 days    Mon 25/11/19 Mon 9/12/19                                                                                                                Stage 1 BA
 133                   Lodge Application                             1 day      Mon 25/11/19 Mon 25/11/19                                                                                 Lodge Application
 134                   Building Approval Review & Assessment         10 days    Tue 26/11/19 Mon 9/12/19                                                                                                                Building Approval Review & Assessment
 135                   Building Approval                             0 days     Mon 9/12/19 Mon 9/12/19                                                                                                        9/12     Building Approval
 136                Stage 2 BA                                       33 days    Mon 16/12/19 Thu 13/02/20                                                                                                                                                                                                                                                     Stage 2 BA
 137                   Lodge Application                             1 day      Mon 16/12/19 Mon 16/12/19                                                                                                                            Lodge Application
 138                   Building Approval Review & Assessment         20 days    Tue 17/12/19 Tue 28/01/20                                                                                                                                                                                                                    Building Approval Review & Assessment
 139                   Building Approval                             0 days     Thu 13/02/20 Thu 13/02/20                                                                                                                                                                                                                                          13/02      Building Approval
 140        PROCUREMENT AND RAMP UP                                  204 days    Fri 1/11/19   Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  PROCUREMENT AND RAMP UP
 141          SITE PLANNING                                          204 days    Fri 1/11/19   Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                  SITE PLANNING
 142             Obtain ENERGEX Advice on Overhead Power Lines       5 days       Fri 1/11/19  Thu 7/11/19                                           Obtain ENERGEX Advice on Overhead Power Lines
 143             ENERGEX Tiger Tails Installed                       15 days      Fri 8/11/19 Thu 28/11/19                                                                                      ENERGEX Tiger Tails Installed
 144             Traffic Management Plan Developed                   3 days       Fri 1/11/19  Tue 5/11/19                                      Traffic Management Plan Developed
 145             CONSTRUCTION WORKS                                  157 days   Tue 21/01/20 Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    CONSTRUCTION WORKS
 146                SITE ESTABLISHMENT                               4 days     Tue 21/01/20 Fri 24/01/20                                                                                                                                                                                                            SITE ESTABLISHMENT
 147                   Noosa Council Pre-Start Meeting               1 day      Tue 21/01/20 Tue 21/01/20                                                                                                                                                                                                     Noosa Council Pre-Start Meeting
 148                   Install temp fence                            1 day      Wed 22/01/20 Wed 22/01/20                                                                                                                                                                                                      Install temp fence
 149                   Install temp crossovers                       2 days     Wed 22/01/20 Thu 23/01/20                                                                                                                                                                                                        Install temp crossovers
 150                   Install temp services                         2 days     Wed 22/01/20 Thu 23/01/20                                                                                                                                                                                                        Install temp services
 151                   Install Site Sheds                            1 day       Fri 24/01/20  Fri 24/01/20                                                                                                                                                                                                          Install Site Sheds
 152                GROUND WORKS AND FOUNDATIONS                     30 days     Fri 24/01/20   Fri 6/03/20                                                                                                                                                                                                                                                                                               GROUND WORKS AND FOUNDATIONS
 153                   Strip Site                                    1 day       Fri 24/01/20  Fri 24/01/20                                                                                                                                                                                                          Strip Site
 154                   Bench out for basement                        3 days     Tue 28/01/20 Thu 30/01/20                                                                                                                                                                                                                         Bench out for basement
 155                   Install Sheet Piles                           5 days      Fri 31/01/20  Thu 6/02/20                                                                                                                                                                                                                                    Install Sheet Piles
 156                   Establish dewatering Plant                    5 days      Fri 31/01/20  Thu 6/02/20                                                                                                                                                                                                                                    Establish dewatering Plant
 157                   Bulk Excavation                               5 days       Fri 7/02/20 Thu 13/02/20                                                                                                                                                                                                                                                    Bulk Excavation
 158                   Detailed Excavation - Services and Lift Pit   2 days      Fri 14/02/20 Mon 17/02/20                                                                                                                                                                                                                                                           Detailed Excavation - Services and Lift Pit
 159                   FRP Lift Pit Walls inc SW Pump Well           3 days     Tue 18/02/20 Thu 20/02/20                                                                                                                                                                                                                                                                  FRP Lift Pit Walls inc SW Pump Well
 160                   Detailed Excavation - Footings                1 day      Tue 18/02/20 Tue 18/02/20                                                                                                                                                                                                                                                              Detailed Excavation - Footings
 161                   FRP Footings                                  3 days      Fri 21/02/20 Tue 25/02/20                                                                                                                                                                                                                                                                           FRP Footings
 162                   Install underslab services                    2 days      Fri 21/02/20 Mon 24/02/20                                                                                                                                                                                                                                                                         Install underslab services
 163                   Install waterproof Membrane                   3 days     Wed 26/02/20 Fri 28/02/20                                                                                                                                                                                                                                                                                  Install waterproof Membrane
 164                   FRP Slab on ground                            5 days     Mon 2/03/20     Fri 6/03/20                                                                                                                                                                                                                                                                                              FRP Slab on ground
 165                STRUCTURE                                        67 days    Mon 9/03/20 Mon 15/06/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                      STRUCTURE
 166                   BASEMENT                                      5 days     Mon 9/03/20 Fri 13/03/20                                                                                                                                                                                                                                                                                                              BASEMENT
 171                   LEVEL 1                                       45 days     Fri 13/03/20 Wed 20/05/20                                                                                                                                                                                                                                                                                                                                                                                                                                                LEVEL 1
 183                   LEVEL 2                                       34 days    Mon 6/04/20 Wed 27/05/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                LEVEL 2
 192                   LEVEL 3                                       34 days    Tue 28/04/20 Mon 15/06/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     LEVEL 3
 206                FAÇADE                                           71 days    Wed 6/05/20 Tue 11/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                        FAÇADE
 207                   LEVEL 1                                       69 days     Fri 8/05/20 Tue 11/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       LEVEL 1
 226                   LEVEL 2                                       63 days    Wed 6/05/20 Thu 30/07/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                LEVEL 2
 250                   LEVEL 3                                       37 days    Thu 11/06/20 Thu 30/07/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               LEVEL 3
 274                INTERNAL FIT OUT                                 72 days     Fri 15/05/20 Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                           INTERNAL FIT OUT
 275                   BASEMENT                                      47 days    Thu 21/05/20 Fri 24/07/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                   BASEMENT
 299                   LEVEL 1                                       50 days     Fri 15/05/20 Thu 23/07/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                LEVEL 1
 320                   LEVEL 2                                       45 days    Mon 22/06/20 Thu 20/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                         LEVEL 2
 341                   LEVEL 3                                       45 days    Tue 23/06/20 Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            LEVEL 3
 362                EXTERNAL WORKS                                   29 days    Wed 15/07/20 Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            EXTERNAL WORKS
 363                   SOUTH                                         10 days     Fri 31/07/20 Thu 13/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                          SOUTH
 367                   EAST                                          8 days      Fri 7/08/20 Tue 18/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                     EAST
 370                   WEST                                          8 days     Wed 12/08/20 Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                            WEST
 373                   NORTH                                         27 days    Wed 15/07/20 Wed 19/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       NORTH
 383                COMPLEATION MILESTONES                           66 days     Tue 2/06/20 Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    COMPLEATION MILESTONES
 384                   STRUCTURE COMPLETE                            0 days      Tue 2/06/20   Tue 2/06/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                 2/06     STRUCTURE COMPLETE
 385                   INTERNAL FIT OUT COMPLETE                     0 days      Fri 21/08/20  Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               21/08      INTERNAL FIT OUT COMPLETE
 386                   EXTERNAL WORKS COMPLETE                       0 days     Wed 19/08/20 Wed 19/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                             19/08     EXTERNAL WORKS COMPLETE
 387                   CLIENT INSPECTION                             0 days      Fri 21/08/20  Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               21/08      CLIENT INSPECTION
 388                   Pratical Compleation                          0 days      Fri 21/08/20  Fri 21/08/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                               21/08      Pratical Compleation
 389                   Delay Allowance                               7 days     Mon 24/08/20 Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                    Delay Allowance
 390                   Project Complete                              0 days      Tue 1/09/20   Tue 1/09/20                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                                       1/09       Project Complete




19116 - INFINITY Noosaville Tender Program 31.10.2019                                                                                                                                                                                                                                                                                                                                                                               Page 1 of 1

Used in these records

About this file

File size
7.5 MB (large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Construction Mangement Plan Reference Document OPW19-0239.pdf · 7.5 MB (large file)

The download may take up to a minute.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.