Council archive · source document
10/0662 - Operational Works [As Published] · 142010.662
2009/1689
7 ADVISORY NOTES _
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.
5,
Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act
if the cost of operational works exceeds $80,000, then a portable long service leave levy is
required to be paid. In accordance with Section 77.(1) of the Act, Council is required to sight
the approved form issued by the Building and Construction Industry (Portable Long Service
Leave) Authority that confirms that the requirements of the Act have been satisfied. A
statutory declaration outlining the cost of the operational works must be submitted to Council
with the lodgement of any application for operational works over the site.
Noise from residential building works shall comply with the following —
2.1. Limited to between 7:00am to 6:30pm Monday to Saturday.
2.2. All reasonable measures are taken to minimise noise emissions.
2.3. Not permitted on Sunday or public holidays.
The development should be undertaken in a manner that causes no detrimental effect upon
the amenity of the neighbourhood by reason of the creation of excessive noise, lighting, air-
borne hazards, atmospheric pollutants {including dust or odours) nuisance or any other
emissions in accordance with the nuisance provisions of the Environmental Protection
Regulation 1998 or Council’s Local Law No. 12 - Control of Nuisances.
Connection to Council live water mains must be undertaken by Council at the applicants
cost.
Water meters must be located on alternative boundaries to power boxes
Infrastructure Contributions and Infrastructure Charge
8.
An advice notice outlining the estimated infrastructure contributions payable and the basis
for their calculation under the current Planning Scheme Policies and Council Policies is
attached with this Development Permit.
For properties located in the catchment area for the Coastal Major Road Network
Infrastructure Charges Plan, this development permit may trigger an Infrastructure Charge to
be issued in accordance with the Infrastructure Charges Plan and Chapter 5 of the
"Integrated Planning Act 1997”
Please contact Council's Infrastructure Charges Officer (email:
[email protected]) a minimum of 5 business days prior to payment of the
infrastructure contributions and/or charge notice so a payment advice detailing the amounts
applicable at the time of payment may be issued to accompany the payment.
Payment of infrastructure contributions and/or infrastructure charge notices will not be
accepted by credit card transaction.
Aboriginal Cultural Heritage Act 2003
There may be a requirement. to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003 (ACH Act).
The ACH Act establishes a cultural heritage duty of care which provides that: "A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. \t is an offence to fail to comply with the duty of care, Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the ACH Act
can also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural
heritage or the cultural heritage value of Aboriginal cultural heritage.
Paga 8 of 14
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
10/0662 - Operational Works [As Published]Related documentApplication case desk ↗
About this file
- File size
- 7.8 MB (large file)
- File type
No other editions are linked here.
Original file
Log in to download the original file
The download may take up to a minute.