Murray - 1802-3881 SER - Early referral response - with conditions · OPW18/0056
Attached to the e-mail Operational Works Appliction – Prescribed Tidal Works - 17 Wesley Ct Noosa Heads.
1802-3881 SER
Attachment 1—Conditions to be imposed
No. Conditions Condition timing
Operational work
Schedule 10.17.3.2.1 - The chief executive administering the Planning Act 2016 nominates the Director-
General of the Department of Transport and Main Roads to be the enforcement authority for the
development to which this development approval relates for the administration and enforcement of any
matter relating to the following condition(s):
1. The development must be carried out generally in accordance with the At all times
following plan:
Site Plan, Layout & Water Allocation, prepared by The Jetty
Specialist, dated 30/1/18, reference JSP-SJ-29030, revision B
2. (a) Provide written notice to: (a) At least two (2)
weeks prior to
Regional Harbour Master the
Maritime Safety Queensland commencement
Macarthur Avenue East of works
Pinkenba QLD 4008
(b) Within two (2)
when the development authorised under this approval is scheduled to weeks of the
commence. completion of
works
Each notice must state this application number, the location and name
of registered place and the condition number under which the notice is
being given.
(b) Provide written notice to:
Regional Harbour Master
Maritime Safety Queensland
Macarthur Avenue East
Pinkenba QLD 4008
when the development authorised under this approval has been
completed.
Each notice must state this application number, the location and name
of registered place and the condition number under which the notice is
being given.
3. (a) “As Constructed” drawings of the approved structure must be Within two (2)
provided to: weeks of the
completion of the
Regional Harbour Master works
Maritime Safety Queensland
Macarthur Avenue East
Pinkenba QLD 4008
4. All vessels, structures, plant and equipment associated with the While the works are
construction of the approved works must be lit/marked in accordance occurring
with the following specifications and requirements such that
undertaking the construction works does not cause a risk to the safe
navigation of ships:
Department of State Development, Manufacturing, Infrastructure and Planning Page 3 of 5
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Murray - 1802-3881 SER - Early referral response - with conditions.pdfRelated documentApplication case desk ↗
About this file
- File size
- 267 KB (small file)
- File type
No other editions are linked here.