Sealed Judgment (4 Arakoon) - 26.05.26
ii. dispute resolution procedures
h. details on the location of external fill/dump sites/sources, the haulage route, type of
vehicle to be utilised during filling operations and frequency of usage. NB any damage
to the existing road system as a result of haulage operations shall be fully repaired at
the applicant’s expense
i. it is acknowledged that the preliminary Construction Management Plan will be a draft
document requiring finalisation upon appointment of the Principal Contractor employed
to construct the works and a final document will be required to be submitted at the Pre-
Start Meeting for the project.
Private Infrastructure
15. All private infrastructure for the development must be designed to meet the planning scheme
requirements unless otherwise agreed by the relevant authority
Road Reserve Permit
16. This development permit provides the applicant with written authority to undertake the
prescribed works. Any additional activities that are undertaken inside Council’s road reserve
for the purpose of acting on this development permit and any associated building permit may
require a Road Reserve Permit. These additional activities may include, but are not limited
to, hoarding, pedestrian diversions, laneway closures, etc. To apply for a Road Reserve
Permit, or for more information, Contact Council’s Road Reserve Officer at
[email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original (Sealed Judgment (4 Arakoon) - 26.05.26.pdf)
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.