Minor Change Report 132008 478 02 {As Published}
DG-500-001.9 C PVC Barrel Vault Double Basketball Courts 10.03.2021
Roof Plumbing Plan, prepared by Greenline
DG-500-001.10 C PVC Barrel Vault Double Basketball Courts 10.03.2021
Stormwater Drainage Plan, prepared by
Greenline
DG-500-001.11 C PVC Barrel Vault Double Basketball Courts 10.03.2021
Illuminance Plan, prepared by Greenline
DG-500-001.12 C PVC Barrel Vault Double Basketball Courts 10.03.2021
Electrical Plan, prepared by Greenline
C. Include the following additional condition:
Stormwater Management
61. Runoff from outlets of the downpipes of the shade sails must not exceed the available
capacity of the drainage systems the downpipes are directed towards. To achieve this, a
100% pervious roof must be installed or alternatively prior to the issue of a Development
Permit for Building Works provide to the satisfaction of Council:
a) Certification from a suitably qualified and experienced RPEQ engineer who is familiar
with the existing drainage system and approved Integrated Water Management Plan for
the site prepared by Callaghan and Toth for the Corporation of the Trustees of the Roman
Catholic Archdiocese of Brisbane, February 2020 (Ref 1923 IWMP.doc), that the
additional 265m2 of catchment directed to the western concrete lined spoon drain and
additional 380m2 directed to the outlet into the drain that receives flows from the eastern
catchment will not exceed the capacity of those respective existing drainage systems;
and
b) Design and certification by a suitably qualified and experienced RPEQ engineer (i.e.
including who is familiar with the existing drainage system and approved Integrated
Water Management Plan for the site prepared by Callaghan and Toth for the Corporation
of the Trustees of the Roman Catholic Archdiocese of Brisbane, February 2020 - Ref
1923 IWMP.doc) of any works necessary to increase the capacity of the drains that
receive discharges from downpipes, to facilitate their free drainage towards the bio
retention basin, and incorporation of appropriate scour protection in line with QUDM and
Noosa Plan PSP6 Engineering Design Standards where necessary to prevent scour.
C. Note the report is provided in accordance with Section 83(9) of the Planning Act 2016
Page 13 of 13
Document Set ID: 21473273
Version: 4, Version Date: 18/05/2021
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.