                                                Officer:            Glen Conforti
                                                Direct Telephone:   (07) 5449 5379
                                                Response Address:   PO Box 141, Tewantin QLD 4565
                                                Email:              [email protected]
                                                Our Reference:      2007/2179
                                                Your Reference:
7 November 2008

R J Neller
PO Box 284
PEREGIAN BEACH QLD 4573



Dear Sir

                          Change to an Existing Approval
                                     Integrated Planning Act 1997

I refer to your request to make a change to an existing approval. On 6 November 2008 Council
decided your requested changes.
Details of the decision with the consolidated conditions are as follows:
1        APPLICATION DETAILS

    Application No:                 2007/2179
    Street address:                 66 Tingira Crescent, Sunrise Beach
    Real property description:      Lot 30 RP 126838
    Planning Scheme:                The Noosa Plan

2        DECISION DETAILS

Council on 26 August 2008 decided to issue the following type of approval:-
       Preliminary Approval for Building Works - Additions & Alterations to Detached House
In relation to the request to make a change to the existing approval, Council on 6 November 2008
decided to:
A.       Agree to delete Conditions 7, 7.1 and 7.2
B.       Issue a Decision Notice – Change to an Existing Approval

3        RELEVANT PERIOD OF APPROVAL

The relevant period for this Development Approval is identified in the Assessment Manager
conditions.
4        ASSESSMENT MANAGER CONDITIONS

1.       Development undertaken in accordance with this approval must generally comply with the
         approved plans of development. The approved plans are numbered, titled and dated:
          Plan         /     Rev.    Plan / Document Name                            Date
          Document No.


                                                                                               Page 1 of 8
Full text of the other 7 pages

Page 2

                                                                                     2007/2179


     Sheet 1/8                  Site Plan – Deborah Wagner Architect      26.7.08
     Sheet 2/8                  Lower Level Floor Plan – Deborah          26.5.08
                                Wagner Architect
     Sheet 3A/8                 Upper Level Floor Plan – Deborah          26.7.08
                                Wagner Architect
     Sheet 4A/8                 Clerestory & Roof Plans – Deborah         26.7.08
                                Wagner Architect
     Sheet 5A/8                 Elevations   1   –   Deborah    Wagner    26.7.08
                                Architect
     Sheet 6A/8                 Elevations   2   –   Deborah    Wagner    26.7.08
                                Architect
     Sheet 7A/8                 Sections 1 – Deborah Wagner Architect     26.7.08
     Sheet 8A/8                 Sections 2 – Deborah Wagner Architect     26.7.08

     and as may be amended by these conditions and annotations on the plans.
2.   The rear balcony shall not extend beyond the average outermost seaward projection of
     buildings on directly adjoining properties as outlined on the Approved Survey Plans. The
     approved plans are numbered, titled and dated:
     Plan         /     Rev.    Plan / Document Name                      Date
     Document No.
     08067-1            A       Partial Detail Plan – Donald James        14.3.2008
                                Colston Cadastral Surveyor
     08067- HEIGHT      A       Heights Survey Plan – Donald James        13.8.2008
                                Colston Cadastral Surveyor

3.   A verification survey of the building is to be carried out by a Licensed Surveyor and a
     certificate lodged with Council at completion of work confirming compliance with the maximum
     allowable building height and the maximum permissible seaward building line as required by
     either the conditions of approval or the Planning Scheme.
4.   External colours and finishes of the building shall comprise of muted/environmental tones that
     blend with the natural environment.
5.   Security in the form of a cash bond or trading bank guarantee to the sum of $1,500 must be
     submitted, to secure performance of all conditions of this approval, prior to the issue of a
     Development Permit for building works. The cash bond or trading bank guarantee will be
     returned on performance of the conditions of approval less any costs incurred by Council in
     respect of enforcing performance of this permit.
6.   The development must be undertaken and operated in a manner that causes no detrimental
     effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
     lighting nuisance or other emissions.
7.   Deleted.
8.   The proposed development shall have all kitchen, laundry and bathroom fittings that comply
     with the AAA Water Conservation Rating System as defined by the AS/NZS 6400 (Water
     Efficient Products - Rating and Labelling 2003) and AS/NZS 3500 (National Plumbing and
     Drainage Standard Part 1.2), with toilets to comply with the AAAA Water Conservation Rating
     System. All tap ware and shower roses shall not exceed a maximum flow of 9 litres per min.
     Dishwashers and washing machines are excluded from this requirement.

                                                                                    Page 2 of 8

Page 3

                                                                                        2007/2179

9.    All hot water systems installed shall be either solar systems; electric heat pump systems; or
      gas systems (LPG or natural).
10.   Existing trees on the site and within road reserves are to be retained, except where required to
      be removed due to building operations or the conduct of the approved use. All other
      vegetation shall be protected from interference resulting from clearing or construction activities
      by:
      10.1   Clearly marking vegetation to be retained with flagging tape;
      10.2   Installing protective fencing around the drip line of the vegetation;
      10.3   Low impact construction techniques are used around vegetation to minimise
             interference with the vegetation.
11.   Cleared vegetation is to be suitably processed by one of the following methods and removed
      from the site: -
      11.1    Processing through a woodchipper or shredder. The resulting mulch is to be stockpiled
              loose in heaps of less than 1000 cubic metres, less than 2.5 metres high with a
              minimum of 10 metres between edges of heaps.
      11.2    Disposal for firewood.
      11.3    Disposal for landscaping purposes.
      11.4    Transport to alternative site for breaking down materials provided that all necessary
              permits have been obtained to allow the alternate site to be used for this purpose.
      11.5   The Applicant is advised that other methods may be considered provided full details of
             the method are submitted.
      11.6    The applicant is advised that burning off is an unacceptable method of disposal.
12.   Buildings and structures (including swimming pools, sheds, tennis courts or outbuildings) are
      not constructed under overhead electricity transmission lines, or within any easements.
13.   The rear fence adjacent to the beachfront shall be no more than 1.2 metres in height, be of
      open construction (at least 50% transparent) and constructed of lightweight materials.
      13.1    Gates must not be installed along the rear property boundary.
Demolition
14.   Infrastructure including reticulated water, sewerage, stormwater, and electricity are to be
      protected from damage and made safe to the standard required by the regulatory authority;
15.   All infrastructure must be disconnected, capped or sealed including:-
      15.1    electricity meters removed and electrical wires disconnected; and

      15.2    telephone lines are disconnected; and

      15.3    high speed data cables and television provider boxes are disconnected and removed
              to the standard required by the regulatory authority;

16.   All building materials containing asbestos, including asbestos cement sheeting or roofing and
      lagging, must be removed from the building and disposed of in accordance with industry best
      practice.




                                                                                       Page 3 of 8

Page 4

                                                                                    2007/2179

17.    Waste generated during construction must be stockpiled in a centralised location and covered
       as required to prevent material being blown onto adjoining properties including the road
       reserve or food waste from generating vermin. All site waste must be disposed of to an
       approved waste disposal facility either directly or via an approved waste receptacle and
       collection service.
18.    Sediment and erosion control measures must be placed on site prior to the works
       commencing and shall be maintained until all works are complete. The erosion and sediment
       control measures shall be in accordance with the “Best practice guidelines for control of
       stormwater on building sites” prepared by Healthy Waterways (available at
       www.healthywaterways.org). If such measures are not in place or are not satisfactory, ‘on the
       spot’ fines may be issued. Such fines can be issued if sediments from the site are found to
       enter or have the potential to enter Council’s stormwater system or natural waterways.
Currency
19.    The Preliminary Approval for Building Work lapses if building work has not happened by 26
       August 2010, unless an application to extend the currency is approved by Council.

5      REFERRAL AGENCY CONDITIONS
The referral agencies applicable to this application are:

 Referral Trigger            Referral Status     Referral Agency       Referral Address

 Nil

6      APPROVED PLANS/DOCUMENTS

The approved plans and / or documents for this development approval are listed in the Assessment
Manager conditions.

7      ADVISORY NOTES

The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1.     The requirements of the Environmental Protection Amendment Regulation (No. 2) 1999 and
       Local Law No. 12, prevents a builder or building contractor carrying out building work on a
       building site in a way that makes or causes audible noise to be made from the building work:-
       1.1.   On a Sunday or public holiday, at any time; or
       1.2.   On a Saturday or a business day, before 7.00am or after 6.30pm.
       A maximum penalty of $1,500 applies to an offence under this legislation.

2.     Prior to the commencement of the development, a plumbing assessment must be obtained
       from Noosa Council’s Plumbing Services Section in accordance with the Plumbing & Drainage
       Act 2002 (as applicable).
Aboriginal Cultural Heritage Act 2003
There may be a requirement to establish a Cultural Heritage Management Plan and/or obtain
approvals pursuant to the Aboriginal Cultural Heritage Act 2003.




                                                                                   Page 4 of 8

Page 5

                                                                                          2007/2179

The ACH Act establishes a cultural heritage duty of care which provides that: “A person who carries
out an activity must take all reasonable and practicable measures to ensure the activity does not
harm Aboriginal cultural heritage”. It is an offence to fail to comply with the duty of care. Substantial
monetary penalties may apply to individuals or corporations breaching this duty of care. Injunctions
may also be issued by the Land and Resources Tribunal, and the Minister administering the Act can
also issue stop orders for an activity that is harming or is likely to harm Aboriginal cultural heritage or
the cultural heritage value of Aboriginal cultural heritage.
You should contact the Cultural Heritage Co-ordination Unit on 07 3238 3838 to discuss any
obligations under the ACH Act.

8     PROPERTY NOTES
Not applicable

9     PRELIMINARY APPROVAL OVERRIDING SCHEME
A preliminary approval under section 3.1.6 of Integrated Planning Act 1997 has been granted and as
such the level of assessment and applicable codes for any development approval resulting from this
approval are identified in the conditions.

10    FURTHER DEVELOPMENT PERMITS REQUIRED

 Type of Development Permit required            Subject of the required Development Permit
 Development Permit for Building Works          All Building Works

11    SELF ASSESSABLE CODES
The developer must comply with the following codes for self-assessable development related to the
development approved under this Decision Notice:
Detached House Driveways Code

12    SUBMISSIONS
Not applicable

13    REASONS / GROUNDS FOR APPROVAL DESPITE CONFLICT WITH SCHEME
Not applicable

14    RIGHTS OF APPEAL

You are entitled to appeal against this decision. A copy of the relevant appeal provisions from the
Integrated Planning Act 1997 is attached.

15    OTHER DETAILS

Should you wish to obtain more information about Council’s decision electronic copies are available
on line at www.sunshinecoast.qld.gov.au, or at Council Offices.

DECISION NOTICE HISTORY
 Original Decision Notice issued 26 August
  2008.
 Change to an Existing Approval issued 6
  November 2008 with deletion of Conditions 7,
  7.1 & 7.2.


                                                                                         Page 5 of 8

Page 6

                           2007/2179

Yours faithfully,




Tracy Jones
SENIOR PLANNING OFFICER




                          Page 6 of 8


[OCR of page images]
2007/2179

 

Yours faithfully,

Tracy Jones
SENIOR PLANNING OFFICER

Page 6 of 8

Page 7

                                                                                                       2007/2179


                                                        Appeal Rights
                                                        INTEGRATED PLANNING ACT 1997 & 1998 REGULATION




The following is an extract from the Integrated                         (6) If an application involves assessment against a
Planning Act (Chapter 4).                                           concurrence agency code, appeal rights for submitters
                                                                    for the application are not available against the part of
Division 8 - Appeals to                court   relating   to        the approval that represents the concurrence agency’s
development applications                                            response for the code.
Appeals by applicants                                               Appeals by advice agency submitters
4.1.27.(1) An applicant for a development application               4.1.29.(1) An advice agency may, within the limits of its
may appeal to the court against any of the following-               jurisdiction, appeal to the court about the giving of a
(a) the refusal, or the refusal in part, of a development           development approval for a development application if-
      application;                                                  (a) the development      application   involves    impact
(b) a matter stated in a development approval, including               assessment; and
      any condition applying to the development, and the            (b) the advice agency told the applicant and the
      identification of a code under section 3.1.6;1                   assessment manager to treat its response to the
(c) the decision to give a preliminary approval when a                 application as a submission for an appeal.
      development permit was applied for;                              (2) The appeal must be started within 20 business
(d) the length of a currency period;                                days after the day the decision notice or negotiated
                                                                    decision notice is given to the advice agency as a
(e) a deemed refusal.                                               submitter.
    (2) An appeal under subsection (1)(a) to (d) must be            Appeals for matters arising after approval given
started within 20 business days (the “applicant’s appeal
                                                                    (co-respondents)
period”) after the day the decision notice or negotiated
decision notice is given to the applicant.                          4.1.30.(1) For a development approval given for a
                                                                    development application, a person to whom any of the
    (3) An appeal under subsection (1)(e) may be started
                                                                    following notices have been given may appeal to the
at any time after the last day a decision on the matter
                                                                    court against the decision in the notice-
should have been made.
                                                                    (a) a notice giving a decision on a request for extension
Appeals by submitters
                                                                       of the currency period for an approval;
4.1.28.(1) A submitter for a development application may
                                                                    (b) a notice giving a decision on a request to make a
appeal to the court about-
                                                                       minor change to an approval.
(a) the giving of a development approval, including any
                                                                        (2) The appeal must be started within 20 business
      conditions (or lack of conditions) or other provisions
                                                                    days after the day the notice of the decision is given to
      of the approval; or
                                                                    the person.
(b) the length of a currency period for the approval.
                                                                        (3) Subsection (1)(a) does not apply if the approval
    (2) The appeal must be started within 20 business               resulted from a development application (superseded
days (the “submitters appeal period”) after the day the             planning scheme) that was assessed as if it were an
decision notice or negotiated decision notice is given to           application under a superseded planning scheme.
the submitter.
                                                                       (4) Also, a person who has made a request
    (3) If a person withdraws a submission before the               mentioned in subsection (1) may appeal to the court
application is decided, the person may not appeal the               against a deemed refusal of the request.
decision.
                                                                       (5) An appeal under subsection (4) may be started at
   (4) If an application involves both impact assessment            any time after the last day the decision on the matter
and code assessment, appeal rights for submitters are               should have been made.
available only for the part of the application involving
impact assessment.                                                  Division 9 - Appeals to court about other matters
    (5) If an application is processed under section                Appeals for matters arising after approval given
6.1.28(2), appeal rights for submitters for the application         (no co-respondents)
are available only for the aspects of the development that          4.1.31.(1) A person to whom any of the following notices
would have required public notification under the                   have been given may appeal to the court against the
repealed Act.                                                       decision in the notice-
                                                                    (a) a notice giving a decision on a request to change or
                                                                       cancel a condition of a development approval.
1
    Section 3.1.6 (Preliminary approval may override local
    planning instrument)
                                                                                                      Page 7 of 8

Page 8

                                                                                                2007/2179

(b) a notice under section 6.1.442 giving a decision to      (c) the decision to give a preliminary approval when a
    change or cancel a condition of a development                  development permit was applied for;
    approval.                                                (d) the length of a period mentioned in section 3.5.21
    (2) The appeal must be started within 20 business              currency period;
       days after the day the notice of the decision is      (e) a deemed refusal.
       given to the person.
                                                                 (2) An appeal under subsection (1)(a) to (d) must be
    (3) Also, a person who has made a request                started within 20 business days (the “applicant’s appeal
       mentioned in subsection (1)(a) may appeal to the      period”) after the day the decision notice or negotiated
       court against a deemed refusal of the request.        decision notice is given to the applicant.
    (4) An appeal under subsection (3) may be started at         (3) An appeal under subsection (1)(e) may be started
       any time after the last day the decision on the       at any time after the last day a decision on the matter
       matter should have been made.                         should have been made.
Appeals against decisions to change approval conditions      The Registrar for the Building and Development
under the repealed Act                                       Tribunal may be contacted at the website
4.1.33A.(1) A person who is dissatisfied with a decision     http://www.localgovernment.qld.gov.au/
made on an application to change the conditions
attached to an approval given under section 2.19(3)or        For Infrastructure Charges Only
section 4.4 of the repealed Act may appeal to the court      4.1.36 Appeals about particular infrastructure
against-                                                     charges
(a) the decision; or                                         (1) This section applies to a person who has been
(b) a deemed refusal of the application.                     given, and is dissatisfied with, an infrastructure charges
                                                             notice or a regulated State infrastructure charges notice.
    (2) An appeal under subsection (1)(a) must be
started within 20 business days after the day notice of      (2) The person may appeal to the court against the
the decision is to be given to the person.                   notice.
    (3) An appeal under subsection (1)(b) may be started     (3) The appeal must be started within 20 business days
at any time after the last day a decision on the matter      after-
should have been made.                                       (a) if the notice is given because of a development
Appeals against local laws                                        approval or master plan approval-the day the
                                                                  applicant is given notice of the decision about the
4.1.33B.(1) An applicant who is dissatisfied with a
                                                                  approval; or
decision of a local government or the conditions applied
under a local law about the use of premises or the           (b)    otherwise-the day the notice is given to the person.
erection of a building or other structure permitted by the   (4)    An appeal under this section may only be about-
planning scheme may appeal to the court against the
                                                             (a) whether a charge in the notice is so unreasonable
decision or the conditions applied.                              that no reasonable relevant local government, State
    (2) The appeal must be started within 20 business            infrastructure provider or coordinating agency could
days after the day notice of the decision is given to the        have imposed it; or
applicant.
                                                             (b) an error in the calculation of the charge.
For Building Works Only                                      (5) To remove any doubt, it is declared that an appeal
Rights of appeal conferred by Section 4.2.9 of the           under this section can not be about the methodology
Integrated Planning Act 1997 as follows:                     used to establish the charge in the relevant infrastructure
Division 3 – Appeals to tribunals relating to                charges schedule or regulated State infrastructure
development applications                                     charges schedule.
Appeals by applicants
4.2.9(1) An applicant for a development application may
appeal to the Building and Development Tribunal against
any of the following-
(a) the refusal, or the refusal in part, of a development
    application;
(b) a matter stated in a development approval, including
    any condition applying to the development, and the
    identification of a code under section 3.1.6;3


2
   Section 6.1.44 (Conditions may be changed or
  cancelled by assessment manager or concurrence
  agency in certain circumstances)
3
  Section 3.1.6 (Preliminary approval may override local
  planning instrument)
                                                                                               Page 8 of 8

Used in these records

About this file

File size
59 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

SUPERSEDED Decision Notice - Change to an Existing Approval - 010.2007.00002179.002 [As Published].pdf · 59 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.