10.   Demonstrate that the site can be developed with no net increase in runoff from
      the site for storm events up to a 1 in 100 year Average Recurrence Interval. In
      this regard the stormwater drainage system designed for the site will need to
      incorporate an adequate detention system (holding tanks and rainwater tanks) to
      retain these flows, which can be utilised for irrigation, toilet flushing, hose down of
      paved surfaces, and ground water recharging.
      The present proposal and Stormwater Management Plan does not address this
      issue.
      In this regard additional flows into the existing drainage system in the David Low
      Way will not be supported.

11.   Demonstrate that the site can be drained without the use of pumps in accordance
      with Specific Outcome O17 of Table 14-46 of the Driveways & Carparking Code.
      In this regard the basement proposal cannot be supported unless it can be
      drained by gravity means.
      The applicant is also advised that given stormwater from the carparking and
      driveway areas of will contain contaminants such as oil, grease, and fuel, all
      stormwater runoff will need to be collected and discharged through a suitable
      grease/oil arrestor and/or Gross Pollutant Traps to separate these contaminants
      and prevent them from entering Council’s drainage system.
Traffic Issues

12.   The previously submitted traffic report shall be amended to reflect the new
      proposal plan (and any changes that may be generated as a result of this
      information request) and resubmitted for Council to review.

Engineering Reports

13.   Please arrange for all engineering design plans and engineering reports
      submitted with the application to be certified by an appropriately qualified
      Registered Professional Engineer Queensland (RPEQ), as it is noted that none of
      the plans nor any of the engineering reports have been prepared, checked, and
      approved by an authorised person. In this regard none of the plans or the
      engineering reports will be assessed in detail until a RPEQ has authorised them.
      Council therefore reserves the right to make a subsequent request for further
      information upon review and assessment of the authorised documentation with
      no consequence to IDAS time lines set by the Integrated Planning Act.
      The applicant and any consultants assisting in the preparation of this
      development proposal are advised that an independent check of some or all of
      the technical reports and plans submitted may be forwarded to Council’s own
      expert specialists, and the cost of this independent review will be borne by the
      applicant.


Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.




  Award Winner - Australian Clean Beach
    Challenge 2004 Litter Prevention

Used in these records

About this file

File size
25 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

06_2689 - Request for further Info [As Published].pdf · 25 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.