Attachment 3 - Traffic Further Issues Response_TTPlus10553_20220330.pdf
Department Principal:
Bryce Trevilyan
Project Contact:
Bryce Trevilyan
ABN: 54 619 700 239
Queensland
6 Mayneview Street, Milton Qld 4064
Date 30-Mar-2022 PO Box 1779, Milton BC, Qld 4064
P: +61 7 3871 0411 F: +61 7 3367 3317
TTPlus Ref: 10553
E: [email protected]
Phil Starkey
Noosa Springs Real Estate Pty Ltd
[email protected]
Dear Phil
Noosa Springs Resort Complex — Traffic Engineering response to further matters raised by
Council
Prefacing Comment
1. The advice in this report follows on from previous reports that have been produced by Traffic & Transport Plus
(TTPlus) for the proposed development, namely our traffic engineering assessment dated 18-Jun-2021 and our
response to Council’s RFI dated 22-Nov-2021. I have received a further request from Council for more
information about the proposal in an email from Council officer Patrick Murphy dated 18 March 2022. It contains
four specific queries.
Query 1
2. I note that with regards to Council’s first query “Need clarity as to whether the resort facilities can be used by
the public – this would need to be factored into a reviewed car parking analysis”. The proposal is described in
our 18-Jun-2021 report paragraph 9 “The proposal under assessment is to redevelop the north-eastern portion
of the land parcel, whilst leaving the southern and western areas largely unchanged. A 112 room hotel, spread
over 5 buildings is proposed, including ancillary facilities (bar, dining, café, pools) and associated servicing
arrangements. Post construction, the existing golf, day spa and function facilities are to be retained.”. The only
addition is the hotel — the existing facilities on site remain open to the public and are assumed to produce traffic
and parking demand at the rate previously observed and therefore their operation is accounted for under
existing/observed conditions.
3. In TTPlus’s experience, it is not routine for significant numbers of externally based patrons to frequent an internal
resort restaurant — it is not to say that there may not be some instances where this may occur, but at a design
level, it is considered to be somewhat insignificant. In any event, as will be seen in the car parking availability
analysis presented later in this advice, during the time at which such behaviour may occur (evening), there is
ample spare car parking available on site.
Traffic Transport Engineering www.ttplus.com.au
[OCR of page images]
TRAFP IAG RANSFORT
me Dis
Department Principal:
Bryce Trevilyan
Project Contact:
Bryce Trevilyan
ABN: 54 619 700 239
Queensland
6 Mayneview Street, Milton Qld 4064.
Date 30-Mar-2022 PO Box 1779, Milton BC, Qld 4064
TTPlus Ref: 10553 P: +61 7 3871 0411 F: +61 7 3367 3317
E: [email protected]
Phil Starkey
Noosa Springs Real Estate Pty Ltd
[email protected]
Dear Phil
Noosa Springs Resort Complex — Traffic Engineering response to further matters raised by
Council
Prefacing Comment
The advice in this report follows on from previous reports that have been produced by Traffic & Transport Plus
(TTPlus) for the proposed development, namely our traffic engineering assessment dated 18-Jun-2021 and our
response to Council’s RFI dated 22-Nov-2021. | have received a further request from Council for more
information about the proposal in an email from Council officer Patrick Murphy dated 18 March 2022. It contains
four specific queries.
Query 1
| note that with regards to Council's first query “Need clarity as to whether the resort facilities can be used by
the public — this would need to be factored into a reviewed car parking analysis”. The proposal is described in
our 18-Jun-2021 report paragraph 9 “The proposal under assessment is to redevelop the north-eastern portion
of the land parcel, whilst leaving the southern and western areas largely unchanged. A 112 room hotel, spread
over 5 buildings is proposed, including ancillary facilities (bar, dining, café, pools) and associated servicing
arrangements. Post construction, the existing golf, day spa and function facilities are to be retained.”. The only
addition is the hotel — the existing facilities on site remain open to the public and are assumed to produce traffic
and parking demand at the rate previously observed and therefore their operation is accounted for under
existing/observed conditions.
In TTPlus’s experience, it is not routine for significant numbers of externally based patrons to frequent an internal
resort restaurant — it is not to say that there may not be some instances where this may occur, but at a design
level, it is considered to be somewhat insignificant. In any event, as will be seen in the car parking availability
analysis presented later in this advice, during the time at which such behaviour may occur (evening), there is
ample spare car parking available on site.
Traffic Transport Engineering www.ttplus.com.au