2.      Provide amended plans that detail the provision of a 2.0 metre landscaped setback to
        the street frontage.
Issue - Stormwater
The submitted documentation does not include a Stormwater Management Plan.
Information Required
3.      Provide a preliminary Stormwater Management Plan that includes, but not be limited to,
        details of how rain water on landscaped and impervious areas will be collected and
        released from the site. The preliminary plan must be prepared by a suitably qualified
        person.
Please note that the stormwater drainage system must be a gravity system and pumps are
not acceptable.


Issue - Access and Manoeuvring
The submitted plans do not include sufficient detail on the access driveway and manoeuvring
areas.
Information Required
4.      Provide additional detail on the access driveway and manoeuvring areas. The detail
        must be prepared by a suitably qualified person (RPEQ – Registered Professional
        Engineer of Queensland) and include, but not be limited to:
         a.      levels and grades of the access driveway and manoeuvring areas;
         b.      dimensions of the proposed driveway and manoeuvring;
         c.      a design generally in accordance with RS-049, RS-050 and any associated
                 addendum;
         d.      a longitudinal section extending from the centreline of the formation in Orient
                 Drive to the garage level; and
         e.      demonstrate that a B99 vehicle will not bottom out or scrape while
                 entering/exiting the driveway.
6.   Provide a Turning Path Plan demonstrating how a B99 vehicle can enter and exit each
        proposed carpark. The plan must be prepared by a suitably qualified person (RPEQ –
        Registered Professional Engineer of Queensland).


Issue
A site inspection indicates that the construction of the proposed driveway will potentially impact
a mature and well established tree within the road reserve. Council are concerned that the
location of the proposed driveway will create a potential conflict between the low-lying canopy
of the existing tree and vehicles using the driveway.
Information Required
7.      Provide additional detail (species, size, height, etc) demonstrating if the existing tree is
        to be removed or how the health of the existing tree will be managed during the proposed
        works and in the longer term. If the existing tree is to remain, demonstrate that a B99
        vehicle will not collide with the low-lying canopy of the existing tree.


3.      DUE DATE FOR RESPONSE TO FURTHER ADVICE

A response to the further advice is required by 23rd May 2022 Email your response to
[email protected] 2 of 3

Used in these records

About this file

File size
163 KB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

ECM_21919312_v1_Further Advice Assessment Manager 51988 2764 01.pdf · 163 KB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.