7 ADVISORY NOTES
The following Advisory Notes are for information purposes only and do not form conditions of
approval:
1. Approval of this development application will trigger an Infrastructure Charge in accordance
with the Coastal Major Road Network Infrastructure Charges Plan. An estimate only of the
amounts payable for each Stage is as follows:-
Per Staging Plan PMM Group - Ref 6812-61H dated 8 September 2003
Stage
A B1 B2 B3 C D
Current at December March March March March December
CPI 2004 2010 2010 2010 2010 2004
CMRNICP $ 195,132 $ 54,644 $ 66,787 $ 103,217 $ 176,076 $ 12,765
These amounts will subject to variations in the Consumer Price Index, All Groups Brisbane
until the date of payment. Infrastructure Charge Notices will be issued in accordance with
Chapter 5 of the Integrated Planning Act 1997 and will require payment of the charges prior to
the endorsement of the Plan of Survey for each Stage.
With regard to Stage D, the future development of the Forest Cluster Precinct will attract
further Infrastructure charges that will be assessed at the time of the future applications.
2. Payment via credit card transaction will not be an acceptable method of payment for
development contributions conditioned in this permit or for infrastructure charge notices issued
separately.
3. Pursuant to the Building and Construction Industry (Portable Long Service Leave) 1991 Act if
the cost of operational works exceeds $80,000, then a portable long service levy is required to
be paid. In accordance with Section 77.(1) of the Act, Council is required to sight the approved
form issued by the Building and Construction Industry (Portable Long Service Leave) Authority
that confirms that the requirements of the Act have been satisfied. A statutory declaration
outlining the cost of the operational works must be submitted to Council with the lodgement of
any application for operational works over the site.
Additional Advisory Note
4. The applicant is advised that development contributions and infrastructure charges applicable
to this development approval have been based on the following Uses Class/ Uses and
applicable quantities:-
Approved Development
Existing Development
Per Staging Plan PMM Group - Ref 6812-61H dated 8 September 2003
Existing Use Existing Approved Use Class /
Approved Quantity
Class / Use Quantity Use
Stage A = 88 house lots
Stage B1 = 18 house lots
Stage B2 = 16 house lots +
Detached House 1 x vacant lot Detached House 6 group house lots
Stage B3 = 34 house lots
Stage C = 58 house lots
Stage D = 5 house lots
Page 23 of 27
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
SUPERSEDED - Change to an Existing Approval (Construction Staging Plan) [As Published]Related documentApplication case desk ↗
About this file
- File size
- 123 KB (small file)
- File type
No other editions are linked here.