7.6          Eumundi Noosa Road / Gateway Drive Intersection
The proposed development will result in relatively low and insignificant increase in peak hour traffic volumes
at this intersection. Table 7.6 details the surveyed (2021) peak hour volumes entering and leaving the
roundabout intersection at the Gateway Drive leg of the intersection, and the additional volumes generated
by the proposed development and its proportion of the existing volumes.

Table 7.6: Comparison of Peak Hour Volumes on Gateway Drive Leg

  Peak Period                        Northbound                                          Southbound
                         (Traffic Flow Leaving Roundabout)                 (Traffic Flow Approaching Roundabout)
                       Existing      Development           % of            Existing    Development       % of
                       Volume          Volume             Existing         Volume        Volume         Existing
  Weekday AM             434               10              2.2%              354            6             1.7%
  Weekday PM             323                6              1.9%              428            7             1.5%
  Saturday               507               14              2.8%              485            15            3.1%



As indicated, the traffic demands associated with the proposed development equates to between 1.5% to
3.1% of existing traffic volumes. Typically, the warrant for undertaking detailed performance analysis of the
potential traffic impacts of any development is where the development traffic demands exceed 5% of the
existing traffic volumes. As such, it is concluded that the additional traffic demands generated by the
proposed development at the intersection are insignificant and do not warrant detailed performance
analysis of the intersection.

7.7          Conclusion
The traffic impact analysis, as detailed in the above sections, indicates that the proposed site accesses would
operate with ample spare capacity and would not adversely impact the operation and performance of the
existing Bunnings site access located immediately south of the subject site, and no adverse traffic impacts
are anticipated to occur at the Eumundi Noosa Rd / Gateway Dr roundabout intersection.




Site: Hardware & Trade Supplies Development – 178 Eumundi Noosa Rd, Noosaville QLD
Reference: 21BRT0226

Used in these records

About this file

File size
15.0 MB (very large file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

Attachment D - Traffic Response.pdf · 15.0 MB (very large file)

The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.