2017-07-17 General Committee Agenda
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
GENERAL COMMITTEE MEETING AGENDA 17 JULY 2017
6 OPERATIONAL PLAN PROGRESS REPORT - 4TH QUARTER 2016-17
DOCUMENT INFORM AT ION
Author Chief Executive Officer, Brett de Chastel
CEO’s Office
Index ECM/ Subject/ Corporate Planning
Attachments 1. Operational Plan Progress
2. Key Performance Indicators
EXECUTIVE SUMMARY
Not applicable.
RECOMMENDATION
That Council note the report by the Chief Executive Officer to the General Committee Meeting
dated 17 July 2017 providing an update on progress with the implementation of the Operational
Plan to 30 June 2017 and details of Council’s Key Performance Indicators.
REPORT
As usual, this quarterly report is in two parts. The first part provides Council with an overview of
progress in implementing the annual Operational Plan. The second part focuses on the Key
Performance Indicators (KPIs) which are reported to Council on a quarterly basis.
This report relates to the final quarter of the 2016/17 financial year.
1 OPERATIONAL PLAN UPDATE
Only the major initiatives are included in the Operational Plan with day to day “business as usual”
activities included in Branch Plans.
The Branch Plans are being used by Managers to manage day to day activities. They are an
effective tool for ensuring that all of the “business as usual” activities are undertaken and that any
minor projects are followed through. They are reported to Council by Directors on a quarterly
basis.
Details of each Operational Plan project is set out in Attachment 1 with an assessment of
whether the issue in completed, on target or behind schedule. Comments are also provided for
the information of Councillors about the status of each issue. It is important to note that this is
“as at 30 June 2017” i.e. the end of the fourth quarter.
There were 30 initiatives in the 2016/17 Operational Plan. Many of these initiatives span several
years. Examples include the implementation of the Local Economic Plan, the Peregian Digital
Hub project, Waste Contract implementation, Social Plan etc.
The status of our Operational Plan projects is:
Not started: 0
Behind Schedule: 6 (not been completed by 30 June – details below)
On track: 14 (including multiyear projects)
Completed: 10
Page 14 of 37
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.