GENERAL COMMITTEE MEETING AGENDA 17 JULY 2017
Figure 3: Operating Expenditure Position by Type
$45
$40
YTD Budget ($m)
$35
YTD Actual ($m)
$30
$25
$20
$15
$10
$5
$0
Finance Costs
Materials
Depreciation
Employees
Other
Capital Revenue
Capital revenue of $11.2m received for the year includes $3.1m of cash contributions from
developers, contributed assets of $5.2m (new infrastructure assets provided as a condition of
development) and together with $2.9m received as grant funding towards capital projects.
Figure 4: Capital Revenue by Type
$6.0
YTD Budget ($m)
$5.0
YTD Actual ($m)
$4.0
$3.0
$2.0
$1.0
$0.0
Contributed assets
Cash contributions
Grants / subsidies
Capital Program
Actual capital expenditure (excluding commitments) is $18.2 million against budget of $24.6
million. Committed expenditure (which includes costs for projects expected to be completed in
July and August 2017) totals a further $4 million bringing the total of actual and committed funds
to $22.1 million (90% of the total program). Total actual capital expenditure will increase once
expenditure accruals are finalised as part of end of financial year processing.
Page 8 of 37
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.