Decision Notice - Approved by Delegation of Authority - OPW26 0079 (As Published)

of 7
               4.     ASSESSMENT MANAGER CONDITIONS

               APPROVED PLANS
               1.     Development undertaken in accordance with this approval must generally comply with the
                      approved plans of development. The approved plans are listed in the following table unless
                      otherwise amended by these conditions.

                        Plan No.       Rev.   Plan/Document Name                                           Date

                        WD - 1.02      -      Driveway Crossover Details – Project No. 23-021              11/06/2026
                                              Prepared by Applicant

               CURRENCY PERIOD
               2.     The Currency Period for this development approval lapses if the development has not
                      substantially started by 25 August 2028, unless an application to extend the currency period
                      is approved by Council.
               SITE SPECIFIC CONDITIONS
                      Bonds
               3.     A site control and/or compliance bond of $5000 is to be submitted to Council prior to the pre-
                      start meeting. The pre-start meeting will only be held once Council's Construction
                      Engineering Officer has confirmation that the bond monies have been received by Council.
               4.     The bond will be refunded less any costs incurred by Council in ensuring compliance with
                      these conditions or any additional inspections incurred for substandard work or work
                      undertaken not in accordance with this permit.
               GENERAL CONDITIONS
                      Engineering
               5.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to Council at the prestart meeting.
               6.     The principal contractor must have all the appropriate insurance and public liability
                      documentation to carry out the works. The principal contractor is also responsible to ensure
                      that any subcontractors also have the appropriate insurance and public liability
                      documentation. Certificates demonstrating currency of public liability insurance and works
                      insurance covering the works must be submitted to Council prior to the prestart meeting.
               7.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
               8.     A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during the construction phase.
                      b.      Appropriate traffic signage in accordance with the Manual of Uniform Traffic Control
                              Devices (MUTCD)
                      c.      Provision for safe pedestrian access across the frontage of the site both.
               9.     Any conflict between the development and an existing or proposed service must be referred
                      to the relevant service authority for determination prior to commencement of works.




                                                                                                           Page 2 of 7
Document Set ID: 25101244
Version: 3, Version Date: 28/08/2026

Log in to download the original (Decision Notice - Approved by Delegation of Authority - OPW26 0079 (As Published).pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.