2022-10-24 General Committee Meeting- Item 7 - Attachment 1 - Noosa Oyster Ecosystem Restoration Project - Final Report (1)
Text sections have not been matched to the original PDF pages. Use the original document to check page numbers.
Community engagement, volunteering
and media 424,397 177,722 171,912 147,451 497,085
Community engagement products, engagement
coordination, sub-contractor identification,
contracting and management, volunteer briefings,
volunteer recruitment, stakeholder meetings,
personal protective equipment, media statements,
media management and education material
production and distribution.
Project Management
240,000 102,017 135,947 5,329 243,293
Production of Project Management Plan, Monitoring
Evaluation and Reporting Plan, Communications
Plan, project risk assessments, plan and risk
refinements and revisions, government permitting,
legal, technical science support.
Total expenditure
2,400,000 434,554 809,452 1,157,451 2,401,456
* Expenditures are exclusive of GST
** Total expenditures are subject to minor accounting adjustments on project closure
Expenditure against major contracts
A breakdown of expenditure against major contracts is given in Table 10.
Table 10: Major contracts*
Contractor/Partner Work area Expenditure
NorthGroup Bathymetric surveys of 6 potential oyster restoration sites in the 12,000
Noosa River estuary
Ecological Service Professionals Ecological habitat mapping at 6 potential oyster restoration sites 38,994
in the Noosa River estuary
Ecological Service Professionals Baseline ecological and shoreline erosion monitoring at 4 34,965
restoration sites plus relevant control sites in the Noosa River
estuary
Integrated Coastal Management Oyster reef patch engineering design support – concept models 33,900
and reef patch placement at 4 restoration sites in the Noosa
River estuary
Integrated Coastal Management Coordination and technical support for development approvals 10,000
(state/local) for on-water restoration works at 4 restoration sites
in the Noosa River estuary
Integrated Coastal Management Oversight and Registered Professional Engineer of Queensland 24,290
(RPEQ) certification of reef construction works
M&J Marine Services Reef construction, channel markers, drone surveys of restoration 660,000
sites.
Noosa Environmental Education Hub Community outreach - Senior schools engagement project 31,500
68
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.