SUPERSEDED - Minor Change Existing Approval 131999.982622.5
1.2. Elevations, Drawing No. 05.06.38-002 A prepared by Accord Designs Pty Ltd and
dated June 2006;
1.3. Typical Elevation and Fabrication Layout Plan, Drawing No. 05.06.38-005 A prepared
by Accord Designs Pty Ltd and dated June 2006;
1.4. Annotated Site Plan (Stage 1 only) Drawing No. B1001/DD3 Issue C prepared by
Loucas Zahos Architects and dated August 2006;
and as may be amended by these conditions.
2. The infill panel of shade cloth and support cables between the two shade structures are not
approved and shall not be constructed.
3. The development must be undertaken and operated in a manner that causes no detrimental
effect upon the amenity of the neighbourhood by reason of the creation of excessive noise,
lighting nuisance or other emissions.
4. Existing trees on the site and within road reserves are to be retained. Further additional
planting shall be provided in the existing garden beds adjacent to the shade structures to
replace vegetation that has been removed for the central shade structures and to buffer the
visual dominance of the structures, as detailed below:-
4.1. Central shade structure –
4.1.1. southern garden bed – 2 x 45L native species and native grasses at 300mm
centres to fill the garden bed;
4.1.2. northern garden bed – 2 x 45L native species and native grasses at 300mm
centres to fill the garden bed;
4.2. Eastern Shade Structure –
4.2.1. southern and northern garden beds – native grasses at 300mm centres to fill
the garden beds.
The 45L native species shall include either of the following plants – Syzygium Cascade,
Callistemon Eureka, Callistemon Taree Pink, Callistemon Endeavour, Acmena smithii or
Backhousia myrtifolia.
The native grasses shall include either of the following species – Lomandra longifolia,
Dianella caerulea or Isolepsis nodosa.
5. The area within the diamonds surrounding the posts of the centre shade structures shall be
treated with materials such as paving etc.
6. The shade structures must be covered with pervious material only.
7. Security in the form of a cash bond or trading bank guarantee to the sum of $3000 must be
submitted, to secure performance of all conditions of this approval, prior to the issue of a
Development Permit for building works. The cash bond or trading bank guarantee will be
returned on performance of the conditions of approval less any costs incurred by Council in
respect of enforcing performance of this permit. Council reserves the right to call upon the
bond or guaranteed sum referred to in this approval to effect compliance with conditions.
Land Development
Car Parking
8. The proposed shade structures shall be constructed such that they do not impede the
existing carapaces and aisle to such an extent that they no longer comply with AS/NZS
2890.1:2004 for user class 3A.
9. The shade structures shall be designed and constructed to provide a minimum head
clearance (headroom) at any point of 2.3m.
Page 7 of 11
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalSearchable page text hides email addresses. Original files are unchanged and may show email addresses.