Decision Notice - Change to an Existing Approval - 010.2005.00001189.005 [As Published] · 132005.1189.05
2005/1189
Erosion and Sediment Control
66. Any person acting on this permit shall prevent erosion and sediment export from leaving the
site. Site control measures such as silt fencing, controlled gravel access to the site and
controlled disposal of waste, will be necessary.
In this regard plans detailing the methods of controlling erosion and sediment are required to
be submitted to the Council for approval prior to obtaining a Development Permit for
Operational Works.
General
67. For the following classes of work associated with development, a Development Permit for
Operational Works must be obtained prior to commencement of works relating to that class of
work. The application may combine any or all of these classes of work:-
67.1. Access and/or Carparking.
67.2. Stormwater Drainage.
67.3. Frontage Works.
67.4. Sewer reticulation (including new mains, relocations, diversions).
67.5. Site Filling.
67.6. Landscaping.
68. A suitably qualified Registered Professional Engineer shall prepare engineering drawings and
specifications for all engineering works that will become Council infrastructure, which shall be
submitted in conjunction with an application for a Development Permit for Operational Works.
In this regard a DXF/DWG file on GDA94 zone 56 grid of the proposed cadastre layout is to be
submitted in conjunction with any application for Operational Works.
69. Digital detailed design drawings and calculations shall be submitted with any application for a
Development Permit for Operational Works in respect of roadworks and stormwater drainage
works. To avoid conflict with underground pipes or services, all existing and proposed
services required by the development shall be shown on the plans.
70. To facilitate production of As Constructed drawings it is suggested that all design drawings are
submitted in the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the
use of ADAC are available at www.adac.com.au).
71. Any damage caused to any public utility during the course of construction shall be repaired to
Council’s standards and at no cost to Council.
72. Any alteration of any public utility or other facilities necessitated by the development of the
land or associated construction works external to the site shall be at no cost to Council.
73. The transportation of all materials to and from the site shall be undertaken in a manner such
that no particle matter escapes onto a public road. All vehicles carrying materials either to or
from the site shall be covered to prevent materials including dust being windblown from the
vehicle.
74. As Constructed drawings and data shall be certified by a qualified experienced Civil Engineer
for design intent, and a Licensed Surveyor shall certify the cadastre and the location, level and
type of all services and structures. All of which shall be submitted to Council for checking and
for Council’s records.
The data must fully detail levels for all engineering works including but not limited to drainage
structures, finished ground levels and pavement surface levels. The data shall be submitted in
the Asset Design and As Constructed (ADAC) digital format. (Guidelines on the use of ADAC
are available at www.adac.com.au).
Approval of works shall not be granted until all As Constructed information has been supplied
and accepted by Council.
Page 11 of 19
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
Decision Notice - Change to an Existing Approval - 010.2005.00001189.005 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 97 KB (small file)
- File type
No other editions are linked here.