4325IR Response
Attached to the e-mail Response to the Information Request - MCU17/0028 REC17/0012 & OPW17/0120.
BOOTLE MAX WATTERSON+ASSOCIATES | | a \ | CONSULTING SURVEYORS & PLANNERS Baka 22™ June, 2017 Ref: 16/4325 Your Ref: MCU17/0028 The Chief Executive Officer Noosa Council PO Box 141 TEWANTIN Q 4565 Attention: Patrick Murphy Dear Sir, Re: Development Application for: Material Change of Use —- MCU17/0028 Reconfiguration of a Lot —- REC17/0012 Operational Work — OPW17/0120 Lot 102 on C5604 23 Tewantin Road, Cooroy Applicant: Tea 4 Two Pty Ltd. | refer to the above-mentioned matter and your letter of Information Request dated 9" May, 2017 and | respectfully supply the following information with respect to numbered points of the Request: 1. The Development Application was referred to the Department of Infrastructure, Local Government and Planning in accordance with Section 272 of the Sustainable Planning Act. The Department has issued an approval of the driveway location onto Tewantin Road and included Conditions of approval that the driveway must be designed and constructed in accordance with the standard drawing IPEWA RS-049 & RS-50 and DTMR Road Planning and Design Manual. It is noted that approval from the Referral Agency states that a further application is required to be lodged with the department regarding the legal point of access and to carry out the works in the road reserve. The department have advised the applicant that this application should be lodged following approval of the Development Application by Council. 2. Please find attached a response prepared by Callaghan & Toth (contained in Appendix A), including proposed Works Plans (contained in Appendix B); stating that the proposed works will not have any impact upon the overland flow paths. 3. The above-mentioned response prepared by Callaghan & Toth also provides certification that sightlines are suitable and that there will be no creation of a fall risk. PRINCIPAL 12 Maple Street (PO Box 639) Cooroy Q 4563 ABN 59 847 644 252 Max L. Watterson PH 07 5442 6121 Cadastral Surveyor (Qid) FAX 07 5442 5125 B.Surv(UNSW). M.S.S.S.1 EMAIL [email protected]
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
Large file: the download may take up to a minute.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.
Full text of the other 9 pages
Page 2
The above-mentioned response prepared by Callaghan & Toth includes an attached response from Telstra stating that their cables will be not be required to be re-located. No other services ar affected by the works. The above-mentioned response prepared by Callaghan & Toth addresses the Specific Outcomes O13 of the Transport, Roads and Drainage Code. The above-mentioned response and Plans prepared by Callaghan & Toth address the issue of stormwater drainage to Olivine Lane. The planning report of the Development Application stated that a 14 metre rear setback is proposed from the proposed dwelling to the rear boundary; this setback is from the rear dwelling to the Olivine Lane boundary; which is the rear boundary of the community title scheme. It is noted that a 2 metre setback has been proposed from the rears of the dwellings to the common boundary within the community title scheme. Notwithstanding the above this please find below an assessment of the development with respect to Specific Outcome O8 of the Cooroy and Lake Macdonald Locality Code: $08 Buildings and other structures are appropriately designed and sited to- a) Provide amenity for users as well as preserve the visual and acoustic privacy of adjoining and nearby properties. e¢ The development enhances the amenity of the users by providing direct access to private landscaped open space; e A discrete change of level between the dwellings provides complete visual privacy as neither dwelling can overlook its neighbour; e The skillion roof of the new dwelling has been designed to have minimal visual impact on the existing dwelling.; and e Acoustic and visual privacy is provided by screening, fencing and landscaping. There is also complete separation of living areas between each dwelling. The outlook for the proposed new dwelling living area is toward the northwest and the existing dwelling to the north-east, screened from the neighbouring property. b) Preserve any existing vegetation that will buffer the proposed building from adjoining uses. e The existing vegetation adjacent to the existing dwelling will be retained; e Proposed landscaping will provide a buffer and will screen the new building from the existing (as shown on the Landscaping Plan); and e The existing vegetation along the northern boundary will be retained and enhanced with additional planting providing a buffer to the adjoining properties.
Page 3
Ww c) Allow for landscaping to be provided between buildings. Landscaping between the two communities titled dwellings | provided along the timber screen fencing. Existing vegetation will be preserved and enhanced along the northern, eastern and western boundaries as well as between buildings. d) Maintain the visual continuity and pattern of buildings and landscape elements within the street. The visual continuity of the existing streetscape of Tewantin Road is maintained by retaining and enhancing the existing dwelling by providing screened outdoor landscaped living space, which is currently not provided at the property. The proposed deck and carport addition to the existing dwelling are set well back from the street and will have minimal impact upon the streetscape. The proposed new dwelling is conceived as low key single sympathetic addition to the streetscape in keeping with the surrounding rural village character. Retention of the existing weatherboard country style garage has a dual benefit of preserving an existing element of the streetscape as well as providing a visual buffer from the property across Olivine Lane. MCU17/0028 — Plans of Development The Plans of the Development lodged with the Development Application included a covered space on each Lot of the community title scheme and a visitor's car space on the rear Lot only; whereas the Works Plans lodged with the Application include a covered space and a visitor’s space on each Lot. Please find attached amended Plans of the Development (contained in Appendix C), which include the provision of the car parking in accordance with the Works Plans. Please note that this submission completes our response to your Information Request. | thank you for your consideration in this matter. Yours faithfully Vie Max Watterson
Page 4
APPENDIX A Response to Information Request prepared by Callaghan & Toth
Page 5
Callaghan & Toth Consulting Engineers Pty Ltd ABN No. 45140292324 8/41 Sunshine Beach Road Noosa Junction P.O Box 2305 Noosa Heads 4567 Callaghan & Toth www.callaghanandtoth.com.au Ph: 07 5474 9081 Fax: 07 54749041 4st June 2017 Civil, Environmental & Hydraulic Engineers = File No. 1622 Development Planning Officer Noosa Council Via Email: [email protected] Attention: Patrick Murphy RE: REPONSE TO INFORMATION REQUEST MCU17/0028 OPW17/0120 REC17/0012 AT 23 TEWANTIN ROAD, COOROY In reply to Noosa Council Information Request dated 9" May 2017 we enclose our response to items as follows: Issue 1: The proposed access driveway to Tewantin Road is a significant structure in a Main Roads controlled road. The structure has the potential to create adverse impacts on the existing services, vegetation and drainage patterns. Information Required: Response 1: Response 2: Response 3: 1. Provide written approval from the Department of Transport and Main Roads for the proposed access driveway works and associated retaining structures. 2. Provide comment from the design engineer that addresses the potential impacts on the adjoining property due to the changes in overland flows created by the proposed access driveway. 3. Provide RPEQ certification that states that: a. the designed structure will provider suitable sight lines to pedestrians on the footpath in Tewantin Road. b. the proposed retaining structures do not create an unacceptable fall risk in the road reserve or within the property. 4. Provide written approval from any third party service provider (Telstra, Unitywater etc.) whose assets (both above and below ground) may be affected by the works. Refer to separate written approval from the department of Transport and Main Roads for the proposed driveway works. Our driveway location ensures that there is no impacts on the adjacent property due to changes in overland flow paths. The survey contours show that the verge runoff flows is at 90° approximately to the road and so our driveway design will not divert these flows. The small retaining wall is set 300mm inside the client's boundary to drain any local depressions. a) | certify that we have checked the sight lines to pedestrians on the footpath and that they exceed the requirements in F1G 3.2 of AS 2890.1 b) | certify that retaining walls are more than 500mm away from the edge of the pathway and are only a max of 0.75m high which is less than the minimum 1m high wall requiring a barrier. The edge is also raised to define the change of grade. The design ensures that the public will not use the driveway. Therefore | certify that the structure does not create an unacceptable fall risk in the road reserve or within the property. X:JOBSICT Projects in progress\1622 23 tewantin rd\Correspondence\Response to Noosa Council Info Request.doc
Page 6
Response 4: Issue 2: Telstra cables are the only service crossed by the driveway. See attached an email from Telstra stating that their cables do not require alteration or relocating as a result of the new driveway construction. The site has a frontage to Olivine lane and aside from a new stormwater outlet, the applicant is not proposing any new works. This intent does not appear to be in accordance with Specific Outcome O13 of the Transport, Roads and Drainage Code. The proposed stormwater outlet is located within a section of layback kerb and in close proximity to an existing stormwater outlet from the adjoining development. Information Required: Response 5: Response 6: 5. Demonstrate how the proposed development achieves Specific Outcome O13 of the Transport, Roads and Drainage Code. 6. Provide additional detail on the proposed stormwater outlet to Olivine lane. The detail must include: a. any necessary kerb changes; b. the relationship with the existing stormwater outlet from the adjoining development; and c. The discharge rate from the development site. Below we list the items to be addressed in 013-S13.1: a. We have provided the same sealed road width as the rest of the lane and as other developments in the lane were required to complete. b. We investigated extending the concrete kerb and channel to the north boundary but found that to do that and maintain the sealed road width for the existing laneway the west edge of the seal would be 1.2m from the boundary on the opposite side of the lane instead of the 1.6m now. We believe this is not a desirable outcome as the table drain is already encroaching on the boundary and so did not proceed further. a) & c) We have provided additional detail on our Plan 1622-02 which shows that the stormwater outlet from the site now connects directly into the gully pit. This now complies with 14.147(013) Frontage Works. b) There is no relationship with the existing stormwater outlet from the adjoining development. d) The existing verge is already formed and graded and turfed which is to a higher standard than the rest of the lane. As we believe the intention is to leave the rest of the lane verge vegetated we believe the existing verge fulfils the outcome. e) The laneway frontage has a suitable existing access crossing which allows turn paths for vehicles to enter and leave the site. Our design for a new driveway in Tewantin Road provides a suitable vehicular kerb and footpath crossing. f) There is no room on either frontage verge for a constructed bikeway and no other frontage verges have a bikeway and so the design achieves these outcome. g) Olivine Lane does not have room in the verge for a constructed footpath. The lane itself is used as a footpath for the remainder of the lane and so we believe our design achieves the outcome. There is a constructed footpath on the Tewantin Road frontage which we have designed to be reconstructed to conform to Council's standards as part of the Driveway Design. X:\JOBSICT Projects in progress\1622 23 tewantin rd\Correspondence\Response to Noosa Council Info Request.doc
Page 7
h) Tewantin Road has a fully constructed carriage way in existence. The laneway carriage way fronting the development has a width of 4.6 to 3.0m which is wider than the remainder of the laneway width of 3 m. however this widening has caused the table drain on the northwest side to encroach on private property. The laneway width of 3 m for the rest of the lane has not been requested to be widened in other development applications and we believe the width is the maximum achievable. Therefore our design achieves the outcome. i) Unitywater have been consulted regarding the sewer and advise that since the development complies with Queensland Development Code MPI.4 the existing sewer can remain. No water mains require relocation, no electricity poles or cables require relocating. Telstra has responded that relocation of their cables is not required. Therefore this outcome has been achieved. j) Stormwater drainage works now designed to drain directly into the existing gully pit in the lane frontage. This is the highest standard outcome in accordance with Council's Standards. k) As the development is a community title scheme, the installation of electrical cables and conduits will be addressed at the building approvals stage. $13.2 As per items above the roads and drainage have been designed to achieve the best outcome possible in the laneway and in Tewantin Road. Issue 3: Schedule 1 — Minimum Boundary Setbacks of the Noosa Plan specifies a 6 metre rear setback requirement. The development proposes 2.0 metre setbacks for both the existing and new dwelling. It is noted that the planning report details that a 14 metre rear setback is proposed. Information required: 7. Demonstrate how the proposed reduced setbacks comply with Specific Outcome O8 of the Cooroy and Lake Macdonald Locality Code. Response 7: Setbacks: Refer to separate response in relation to setbacks. If you require any additional information or clarification please do not hesitate to contact us. Yours faithfully, Callaghan & Toth A D Toth BE Environmental RPEQ (Env) (civil) MIEAust CPEng NPER CPESC Director Please view www.callaghanandtoth.com.au for all information on our company profile and terms and conditions for services rendered X:JOBSICT Projects in progress\1622 23 tewantin rd\Correspondence\Response to Noosa Council Info Request.doc
Page 8
M Gmail FW: Build driveway with retaining wall over existing telstra cables at 23 Tewantin road Cooroy- tejinder Bevan, Clint <[email protected]> 23 May 2017 at 07:27 To: Callaghan and Toth <[email protected]> Ce: Sinclair/Muhling <[email protected]> Hi Lex. Thank you for this query and the additional information. Please accept this as notification that based on the information you have provided, Telstra does not require any alteration or relocation to this section of network due to the proposed crossover and retaining wall construction. Feel free to contact me directly if you have to discuss this further. Regards Clint Bevan Mob 0408 155 652 Network Integrity Team. Field Delivery. Telstra Operations. 36 King St, Caboolture. QLD. 4510. Mail:_clint.n.bevan@Team. Telstra.com P PLEASE CONSIDER THE ENVIRONMENT BEFORE YOU PRINT THIS E-MAIL! This communication may contain CONFIDENTIAL or copyright information of Telstra Corporation Limited (ABN 33 051 775 556). If you are not an intended recipient, you MUST NOT keep, forward, copy, use, save or rely on this communication, and any such action is unauthorised and prohibited. If you have received this communication in error, please reply to this e-mail to notify the sender of its incorrect delivery, and then delete both it and your reply. From: Callaghan and Toth [mailto:[email protected]] Sent: Monday, 22 May 2017 4:19 PM To: Bevan, Clint <[email protected]> Cc: Sinclair/Muhling <[email protected]> [Quoted text hidden] [Quoted text hidden]
Page 9
APPENDIX B Operational Works Plans Prepared by Callaghan & Toth (Drawing No. 1622-01C — 07C)
Page 10
APPENDIX C Amended Plans of the Development Prepared by Richard Muhling (Drawing No. T42S1A, T42L1A & T42E1A)