Attachment A - Approved Decision Notice MCU210027

of 19

Page text shows just the words. Original shows the document exactly as it was published.

                      a.      the works shown on the Approved Plans;
                      Services
               27.    Unless otherwise stipulated by telecommunications legislation at the time of construction, the
                      development must be provided with all necessary conduits, pits and pipes to accommodate
                      the future connection of optic fibre technology telecommunications.
               28.    Certification must be submitted to Council from all relevant service providers (Energex, NBN
                      and Unitywater) which certifies that the development has met the requirements of this
                      Decision Notice and all applicable legislation at the time of construction.
                      Easements
               29.    A 4 metre wide easement for Stormwater purposes must be registered against the title of the
                      property in favour of Noosa Council over the proposed easement identified on the Approved
                      Plans.
               30.    Unless otherwise agreed in writing by the relevant service provider, any public or third party
                      infrastructure located on the subject site must be placed within an easement registered
                      against the title of the property.
               31.    All easements must be designed in accordance with the planning scheme and granted at no
                      cost to the Grantee. Where the Grantee is Council or a service authority, the easement
                      documentation must be in accordance with the Grantee’s standard easement terms. Draft
                      easement documentation must be submitted to Council for endorsement.
               32.    All works must be kept clear of any existing or proposed easements on the subject land,
                      unless agreed otherwise in writing by the Grantee.
                      Earthworks and Retaining Walls
               33.    All fill and associated batters must be contained entirely within the subject site unless written
                      permission from the respective landowner(s) is provided to Council. All earthworks must be
                      undertaken in accordance with the provisions of Australian Standard AS3798: Guidelines on
                      Earthworks for Commercial and Residential Developments and the conditions of this
                      Decision Notice.
               34.    Where the development involves excavation or filling over, or adjacent to, drainage, water
                      supply or sewerage infrastructure, all access chamber surface levels must be adjusted to
                      provide a freeboard of 100mm above the finished ground surface level.
               35.    All retaining walls must be designed and constructed in accordance with the planning scheme
                      and must be certified by an RPEQ where exceeding 1.0m in height. All retaining walls that
                      are publicly accessible and exceed 1.0m in height must be fitted with a commercial grade
                      safety fence.
                      ENVIRONMENTAL HEALTH
                      Waste Storage
               36.    The developer must provide waste storage and disposal facilities in accordance with
                      Planning Scheme Policy PSP - 9 Waste Management, including an external imperviously
                      paved area correctly sized for all refuse and recycling containers and suitably screened from
                      public places and neighbouring properties.
               37.    A bin wash area is required with a cold-water tap, hose and drain outlet connected to sewer,
                      via a bucket trap. The drain outlet is to be designed to prevent storm water entry to the
                      sewerage system which can be achieved by a bunded area, with a nib wall height of 100mm
                      maximum, enclosing a wash area of 700mm x 700mm minimum (max 0.7m²). Alternatively,
                      the waste area can be roofed, or any other appropriate design approved by Council.
                      Noise
               38.    Written certification is required from a suitably qualified person confirming that sound
                      pressure levels from all mechanical plant and equipment comply with the following:
                      a.      Air-conditioning and Refrigeration

                                                                                                        Page 5 of 19
Document Set ID: 21498653
Version: 7, Version Date: 17/06/2021
Log in to download the original file

Attachment A - Approved Decision Notice MCU210027.pdf · 245 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.