Attachment A - Approved Decision Notice MCU210027

of 19

Page text shows just the words. Original shows the document exactly as it was published.

               PRIOR TO COMMENCEMENT OF WORKS
                      Engineering
               3.     All necessary approvals from external service providers (e.g. Unitywater) and external parties
                      on which the development works are proposed have been obtained and a copy supplied to
                      Council.
               4.     A condition report of the drainage system must be completed and submitted to council prior
                      to the prestart meeting. The condition report is to include:
                      a.      a CCTV inspection of the pipe section between the existing eastern most pit on the
                              subject site (to be retained) and the connecting pit on Weyba Road;
                      b.      photos of the existing stormwater gully pit on James St fronting the subject site.
               5.     A condition report including photographs of the frontage of the site must be completed and
                      submitted to council prior to the prestart meeting.
               6.     A condition report of all the properties neighbouring the subject site must be completed and
                      submitted to council prior to the prestart meeting.
               7.     Certificates demonstrating currency of public liability insurance and works insurance covering
                      the works must be submitted to Council prior to the prestart meeting.
               8.     Council must be contacted at least 5 working days prior to any works commencing to
                      organise a prestart. The contact number to arrange a pre-start meeting is 5329 6500. The
                      pre-start meeting must include the relevant parties for the following aspects of the works:
                      a.      Civil engineering works;
                      b.      Landscape works;
                      c.      Erosion and sediment control works;
                      d.      Other relevant parties.
               9.     A Construction Management Plan must be submitted to Council prior to the pre-start meeting
                      and must specifically address the following:
                      a.      Traffic Management during all aspects of the construct phase including:
                              i.       A Traffic Management Control Plan in accordance with Manual of Uniform Traffic
                                       Control Devices (MUTCD) detailing all temporary signage and traffic control
                                       measures prior to construction;
                              ii.      Maintenance of safe pedestrian access across the frontage of the site both during
                                       daily construction and after daily construction has ceased;
                              iii.     Proposed fencing to the site during the construction phase of the development;
                              iv.      Adequate parking arrangements for construction workers;
                              v.       No queuing of trucks is permitted on residential streets, especially prior to
                                       7.00am. Further parked trucks must have engines turned off;
                      b.      Maintenance and protection of water quality and existing drainage lines through the
                              construction site through the implementation of appropriate erosion and sediment
                              control measures;
                      c.      Establishment of a communication protocol with the general public, adjoining owners,
                              emergency services and local businesses to advise of agreed construction times,
                              impacts on traffic and services and other relevant issues;
                      d.      Include a post out to the local residents and businesses advising of the proposed
                              development, the expected time frames and the site contact details.
                      e.      Include signage in prominent locations on the boundaries of the site advising of the
                              proposed development, the expected time frames and the site contact details.
                      f.      identification of complaint management procedures including:


                                                                                                          Page 9 of 19
Document Set ID: 21498653
Version: 7, Version Date: 17/06/2021
Log in to download the original file

Attachment A - Approved Decision Notice MCU210027.pdf · 245 KB (small file)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.