Fauna Management
79. Vegetation must only be removed or disturbed in accordance with a Fauna
Management Plan (or part thereof) prepared by a qualified person* and endorsed
through an Operational Works approval.
*(Refer to Advisory Note)
80. Permanent artificial nesting boxes must be installed within the Koala Habitat (Core) to
provide compensatory habitat for arboreal mammals and hollow dependent avian
species. The works must be undertaken in accordance with an Operational Works
approval.
Bushfire Management
81. The development must be carried out in accordance with the approved Bushfire Hazard
Assessment Report & Mitigation Plan version 4 dated 30 April 2022, and as amended
by the Further Advice letter from Rob Friend and Associates Pty Ltd dated 10 February
2023, listed within this Decision Notice, with the exception of the following:
a. Establishment of an additional evacuation point offsite within the golf course that
is separated from buildings and is located outside of identified bushfire hazard
prone areas or potential impact buffer.
The report must be resubmitted to Council incorporating the above amendments prior
to the issue of any Development Permit for Operational Works.*
*(Refer to Advisory Note)
82. Certification must be submitted to Council from a qualified person* which certifies that
the development has been constructed in accordance with the bushfire management
conditions of this Decision Notice. *(Refer to Advisory Note)
83. Certification must be submitted to Council from a qualified Person which certifies that
the development is sufficiently serviced by reticulated water with hydrant standpipes,
in ground hydrants and water pressure to meet firefighting needs in an emergency.
84. A copy of the Bushfire Hazard Assessment Report & Mitigation Plan and evacuation
procedure listed within this Decision Notice must be provided to the nearest fire
authority.
*(Refer to Advisory Note)
WASTE DISPOSAL
85. Prior to the issue of any Operational Works approvals for this development an
Operational Waste Management Plan must be submitted to Council. The Waste
Management Plan must be in accordance with the Waste management Code and
Planning Scheme Policy 9 - Waste Management.
86. The developer must provide waste storage and disposal facilities in accordance with
Planning Scheme Policy 9 - Waste Management. The facilities must include an
impervious area, within the site, correctly sized for all refuse and recycling containers
and suitably screened from public places and neighbouring properties. A bin wash area
is required with a cold-water tap, hose and drain outlet connected to sewer, via a bucket
trap. The drain outlet must be designed to prevent storm water entry to the sewerage
system.
87. Refuse containers must be provided in accordance with the requirements of the
Environmental Protection (Interim Waste) Regulation 1996 and (Waste Management)
Regulation 2000, for the storage and collection of refuse.
88. Storage, disposal and management of solid, liquid and vegetative waste is conducted
in a safe and ecologically sustainable manner without environmental nuisance. In this
regard, vegetated waste must be disposed of via a green waste bin or at a local transfer
station.
Page 16 of 310
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalVery large file: the download may take a few minutes. If you are on mobile data, it is best to wait until you are on Wi-Fi.
Searchable page text hides email addresses. Original files are unchanged and may show email addresses.