3. Compliance with Condition 14 of the MCU approval (06/1155). In this regard,
payment of security in the form of a cash bond or trading bank guarantee to the
sum of $15,000 is required, to secure performance of all conditions of the MCU
approval (06/11155) approval.
Land Development
4. Please provide sections through the property, indicating the natural surface and
proposed excavation levels. Sections in both North/South and East/West
directions would be appreciated.
5. All erosion and sediment controls should be contained within the developed
property. The plan submitted indicates sediment fences across the footpath area
of the road reserve.
6. Council requires a Traffic Management Plan highlighting the truck movements
and routes in removing the excavated material from the site. No queuing of trucks
is permitted in the adjacent streets as they are residential streets and in the main
narrow. The TMP shall also indicate the provision of signs, traffic controllers and
the provisions for pedestrians using the Bryan Street footpath.
7. The construction entry/exit shall be located on the property side of the existing
footpath in Bryan Street.
8. The note on plan No. 06N498-C03A referring to construction of the new pram
ramp and the reference to Council’s standard drawing No. 9006. Please delete
DRG 9006 as Council is currently making changes to its standard drawings and
advice should be sought from Council’s Construction Technical Officer at the time
of contruction.
9. Please confirm the floor level of the basement car park. Also advise if the
stormwater drainage lines can drain to the kerb and channel in Bryan Street by
gravity means and with adequate cover over the pipes.
Please provide four (4) copies of all information that you are providing. In addition, it
would assist Council if you could also provide an electronic copy of your response.
Please be aware that under Section 3.2.12 of the Integrated Planning Act, the applicant
is to respond to any information request within 12 months of the request or otherwise,
the application lapses.
Under the provisions of the Integrated Planning Act 1997, you as the applicant, have
three options available in response to this Information Request. You may give the
assessment manager (in this instance Council) and each referral agency (if any):-
1. all of the information requested; or
2. part of the information requested together with a letter asking the assessment
manager and each referral agency to proceed with the assessment of the
application; or
3. a letter:-
3.1. stating that you do not intend to supply any of the information requested;
and
Award Winner - Australian Clean Beach
Challenge 2004 Litter Prevention
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalUsed in these records
00155852.001.pdfRelated documentPublic source context ↗
Request for Further Information - 010.2007.00000528.001 [As Published]Related documentApplication case desk ↗
About this file
- File size
- 11 KB (small file)
- File type
No other editions are linked here.