Appendix B - Prelodgment notes

of 4
                    A stormwater management plan and design are required, that address in particular the
                    following:
                 • Allow for the collection, control and containment of the existing overland flows from
                    adjoining properties.
                 • Provide any necessary stormwater detention and/or retention measures to maintain the
                    stormwater runoffs from the site to its predevelopment rates.
                 • The stormwater design should aim at disposing of the stormwater flows directly into
                    Council’s existing pit/pipeline rather than into the kerb line.
                 5. Erosion & Sediment Control:

                 •    Given the steepness of the site and the proposed earthworks, a design for E&SC
                      prepared by suitably qualified persom must provided in accordance with “Best Practice
                      Erosion and Sediment Control” published by the International Erosion Control
                      Association (Australasian Chapter) (IECA, 2008)

                 Note: The applicant suggests that a Combined MCU and OPW may be submitted for the
                 proposal. As such a detailed engineering design for the civil works in compliance with the
                 relevant standards will be required to address, but not limited to, the above issues.


                 6.      INFRASTRUCTURE CHARGES

                 A request for written advice for an Infrastructure Charges Contribution Estimate relevant to
                 your proposal may be obtained for a fee.
                 7.      FURTHER ADVICE TO BE SOUGHT

                 You are advised to contact Unitywater and any relevant Queensland Government Agencies
                 for their specific requirements in respect of your proposal.
                 Yours faithfully,




                 Patrick Murphy
                 Coordinator Planning




                  This document is a record of prelodgement discussions and will not be made available for public viewing. Prelodgement
                  discussions are conducted to explore development options and requirements, identify issues and provide guidance to prospective
                  applicants about Council’s policies for development. The recorded discussion items and outcomes in no way imply or commit to
                  an approval of the proposal on the part of Council or Council officers, nor guarantee that all potential issues associated with a
                  development proposal have been raised / identified. When a formal development application is lodged, the proposal will be
                  assessed on its planning merits in accordance with Council’s policy framework existing at the time of the assessment.
Document Set ID: 21234939
Version: 9, Version Date: 17/09/2020

Log in to download the original (Appendix B - Prelodgment notes.pdf)

Searchable page text hides email addresses. Original files are unchanged and may show email addresses.

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.