RFI - 075-028 SWMP Report
CONCLUSION
The pre and post development scenario for the subject has been reviewed to ensure non-actionable nuisance
of flows.
The following conclusions have been made:
• based on the design and proposed detention system, the construction of the development on the
subject site will have negligible impact to the downstream overland flow path.
• the development on the subject site will result in non-actionable nuisance of stormwater runoff
quantities with all runoff to outlet to lawful points of discharge.
It is anticipated the report, when reviewed in conjunction with the planning report and the development plans;
will assist in supporting the application seeking development approval.
Yours Faithfully,
GLENN AINSWORTH
MIEAust CPEng NER RPEQ CPESC
BAX ENGINEERING PTY. LTD.
Ph: 0407 021 300
Page 15 of 18
2261 david low way, peregian beach, qld 4573 acn: 626 671 092 [email protected]