135 Lake Weyba Rd Earthworks Certification L1
5 Conclusions
All test results indicate that the compaction requirements specified in Table 5.1 of AS3798
has been achieved for the fill placed by AG and tested by CQA.
Level 1 Supervision in accordance with AS 3798 has been undertaken on the following Site
areas:
o Lots 1, 2 and 4, 135 Lake Weyba Drive, Noosaville, Queensland
The fill placed on the site by AG in the areas detailed above may be considered ‘Controlled
Fill’ in accordance with AS2798.
Any other fill present on site shall be treated a ‘Uncontrolled Fill’ in accordance with AS2798
unless documentary evidence can be provided to the contrary.
This certification only provides an assurance of the density of the fill placed by AG and
tested by CQA. Where varying depths of fill are placed over unknown underlying materials,
differential consolidation is likely and should be considered during any overlying
construction.
Unless otherwise stated, this certification does not address any other issues which may be
relevant to foundation and building construction.
Report Prepared by:
Phil Band BEng MSc MIEAust CPEng NER AGS RPEQ 23841
135 Lake Weyba Rd Earthworks Certification L1
March 23
3