INTEGRATED PLANNING ACT 1997
Operational! work that is tidal work or
work in coastal management district
For more information refer to Guide 18. For
more information about prescribed tidal work in
local government tidal areas refer to Guide 24.
‘Unless you answered "none of the above" to Q9,
the application requires assessment by the
Environmental Protection Agency (EPA).

Han agency other than EPA is the assessment
manager for the application, EPA is a
concurrence agency for the application in
telation to this matter.

Local government is the assessment manager
for ali prescribed tidal work.

9.

The application involves operational work that is: ( tick the applicable boxes)

C1 (i) _ tidal work" as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; oF

O¥i)
D iii

IDAS Assessment Checklist, Version 19.0, 2 March 2007

tidal work that is prescribed tidal work" other than in a canal’? -complete Part P of Form 1; OF

carried out within a coastal management district under the Coastal Act and for ~ complete
Part M of Form 1 if any box/es (a) to (i) below are ticked.

Oe)

Do)
Oo
Od)
Oe)
OW
O@)

On)
oO

constructing or installing works in a watercourse between MHWS and HAT (ie.
other than those works in tidal water) Where the development has been determined not
to be assessable against the Water Act 2000 ;

constructing a canal’ intended to be connected to tidal waters;

constructing an artificial waterway;
reclaiming land under tidal water;

disposing of dredge spoil or other solid waste material in tidal water;
interfering with quarry material on State coastal land above high-water mark;
draining or allowing drainage or flow of water or other matter across State

coastal land above high-water mark;

removing or interfering with coastal dunes on land, other than State coastal land,

that is in an erosion prone area and above high-water mark;

constructing a bank or bund wall to establish a ponded pasture on land, other
than State coastal land, above high-water mark; or

wo none of the above.

 

Operational work below high water
mark

For more information refer to Guide 18, For
more information about prescribed tidal work in
local government tidal areas refer to Guide 24.
‘Unless you answered “none of the above" to
Q10, the application triggers referral to

Queensland Transport (QT) (Maritime Setety

Qld) as a concurrence agency.

Local government is the assessment manager
for all prescribed tidal work.

10. The application involves operational work that is: ( tick the applicable box/es)

C1 (i) tidal work's as defined under the Coastal Protection and Management Act 1995 (the
Coastal Act) that is not prescribed tidal work - complete Part M of Form 1; or

(1) (ii) tidal work that is prescribed tidal work" - complete Part P of Form 1; of
CO iii) carried out within a coastal management district's under the Coastal Act and for -

C1 (a) disposing of dredge spoil or other solid waste material in tidal water - complete Part

Oo)
Oo

Mof Form 1;

reclaiming land under tidal water - complete Part M of Form 1; or

constructing a canal’, if the canal is associated with reconfiguring a lot - complete

et) none of the above.

Part M of Form 1;

 

Coastal management

For more information refer to Guide 18.

Unless you answered “none of the above" to
Q11, the application requires assessment by the
Environmental Protection Agency (EPA).

Man agency other than EPA is the assessment
manager for ihe application, EPA is a
concurrence agency for the application in
felation to this matter.

 

11.

The application involves: (tick the applicable box/es) :
a material change of use assessable under a planning scheme involving operational

Diy
Ow)

wi

work carried out completely or partly in a coastal management district's

a material change of use assessable under a planning scheme involving building
work, carried out completely or partly in a coastal management district that is -

« the construction of a new premises with a GFA'® of at least 1000m? ,

« the enlargement of the GFA of existing premises by more than 1000m?

reconfiguring a lot assessable under schedule 8 of the IPA where the land is situated
completely or partly in a coastal management district

reconfiguring a lot'’ assessable under schedule 8 of the IPA and in connection with
the construction of a canal'? - complete Part M of Form 1

none of the above

 

10 Tidal work is defined in sch 10 af the IPA.

11 Prescribed tidal work is defined in the Coastal Protection and Management Regulation 2003 and includes certain tidal works completely or Partly within a local government tidal area.

12 Canal means canal as defined under ihe Coastal Protection and Management Act 1995

13 Tidal work is defined in sch 10 of the IPA.

14 Prescribed tidal work is detined in the Coastal Protection and Management Regulation 2003 and inctudes certain tidal works completely or partly within a loca! govemment tidal area.
15 Coastal management district is defined in sch 10 of the PA and means a coastal management district under the Coastal Protection and Management Act 1995, other than an area declared as a

coastal Management district under section 47(2) of that Act.

16 GFA is defined in sch 14 of the IPA to mean the gross floor area. For a definition of how to calculated GFA, go to the planning scheme against which the application is being assessed.
17 Under $117 of the Coastal Protection and Management Act 1995, an application for reconfiguration, where the feconfiguration is associated with the construction of an artificiat waterway, must be

accompanied by the application for the operational works to construct the artificial waterway.

Page 4

Used in these records

About this file

File size
1.4 MB (small file)
File type
PDF

No other editions are linked here.

Original file

Log in to download the original file

07_0399 - Preliminary Building Work assessable against the Planning Scheme 103 Noosa Dr [As Published].pdf · 1.4 MB (small file)

The supporting record

Open full page ↗

Source document

Analyse documents ↗Open full page ↗

My Comparisons

Choose two to four records of the same kind. Drag using a handle or use the “Compare” buttons.

Your selected records are saved in this browser for your account. Results use the filters on the page where you choose “Compare selected”.