accommodate a dwelling and ancillary buildings
and use areas;
c) for lots less than 2,500m2, maximise
separation of buildings from hazardous
vegetation.
513.2 Residential lots are designed so that their
size and shape allow for efficient emergency
access to buildings for fire fighting appliances
Table 13.10 Flood Hazard Areas
Column 1 Column 2
Specific Outcomes Probable Solutions
13.38 Effects of use and subdivision
5afety and floodplain function
014 The proposed use does not compromise the Not applicable. The proposed lots do not fall
safety of people or property from floods up to under the Flood Hazard Area.
and including a 1% AEP (1:100year ARI )flood
event.
Hazardous materials
016 Public safety and the environment are not 516.1 Hazardous materials are not
adversely affected by the detrimental impacts of manufactured and stored on the site.
floodwater on hazardous materials
manufactured or stored in bulk.
Infrastructure
017Sewerage treatment plants maintain their 517.1 Components of the sewerage treatment
function during flood events up to a 1% AEP plants that are likely to fail or may result in
1:100 year ARI) flood event. contamination are-
a) located above the level of a 1% AEP (1:100
ARI) flood event; or
b) are designed and constructed to exclude
water inundation or infiltration and resist
hydrostatic and hydrodynamic forces as a result
of inundation.
018 Community Uses and Infrastructure Uses 518.1 Community Uses and Infrastructure Uses
are able to function effectively during and are sited and constructed to ensure that floor
immediately after flood events. levels are not less than the AEP (or ARI )levels
identified below-
a) Emergency service facilities- 0.2% AEP (1:500
ARI);
b) Emergency shelter- 0.5% AEP (1:200ARt);
c) Police station- 0.5% AEP (1:200ARI);
d) Hospital- 0.2% AEP (1:500ARI);
e) Electricity substation- 0.2% AEP (1:500ARI);
f) Water treatment plant- 0.2% AEP (1:500ARI);
g) Power station- 0.5% AEP (1:200ARI);
h) Major electrical switch yard- 0.5% AEP (1:200
See the original
The page text is free to read. Viewing or downloading an original file needs an account.
Log in to see the originalLog in to download the original file
The download may take a few minutes. On mobile data, it is best to wait for Wi-Fi.